What is major difference between "hammer efficiency" and "coefficient of restitution" at what time using Haley's formula in pile driving?

 

Answer

Hammer effectiveness refers to ratio of kinetic energy of hammer to rate energy. In spirit, there are undoubtedly sure energy losses made by hammer itself prior to real impact on driven pile. For example, these losses can include misalignment of hammer, energy losses because of guiding friction, mistaken dropping height etc

Coefficient of compensation refers to a price indicating strain energy through collision regained after bodies reverted back to their unique shapes. If coefficient of restitution is like to unity, it means that collision is flexible and all energy has been returned after impact action. Thus, this is an index showing degree impact action in terms of flexibility.

 


Related Discussions:- Haley''s formula in pile driving

Explain the angle of wall friction, A retaining wall 4.5 m high with vertic...

A retaining wall 4.5 m high with vertical back supports a backfill with horizontal surface. The unit weight of the fill is 18 kN/m 3 and the angle of internal friction is 36°. The

Surveying, what is compass survey and and its method

what is compass survey and and its method

What will be the increase in horizontal thrust, A 9 metre high retaining wa...

A 9 metre high retaining wall retains a soil with the following properties: φ = 36°; γ = 18 kN/m 3 . What will be the enhance in horizontal thrust if the soil slopes up from the

State the design process of prestressed concrete, State the Design process ...

State the Design process of Prestressed Concrete Most of the times, the design process is an interactive and trial procedure in which the cycle of analysis - design - analysis

Main principle of post-grouting for mini-piles, Question What is main p...

Question What is main principle of post-grouting for mini-piles? Answer During course of post-grouting , a tube with a hole at its base is lowered into pile and g

Geotech, soil sample investigation

soil sample investigation

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd