Haley''s formula in pile driving, Civil Engineering

Assignment Help:

Question

What is major difference between "hammer efficiency" and "coefficient of restitution" at what time using Haley's formula in pile driving?

 

Answer

Hammer effectiveness refers to ratio of kinetic energy of hammer to rate energy. In spirit, there are undoubtedly sure energy losses made by hammer itself prior to real impact on driven pile. For example, these losses can include misalignment of hammer, energy losses because of guiding friction, mistaken dropping height etc

Coefficient of compensation refers to a price indicating strain energy through collision regained after bodies reverted back to their unique shapes. If coefficient of restitution is like to unity, it means that collision is flexible and all energy has been returned after impact action. Thus, this is an index showing degree impact action in terms of flexibility.

 


Related Discussions:- Haley''s formula in pile driving

Explain fluid mechanics or properties – viscosity, Explain Fluid Mechanics ...

Explain Fluid Mechanics or Properties – Viscosity A measure of a fluid's resistance to flow when acted upon by an external force such as pressure or gravity. Also termed, "Abso

Conics, what is the eccentricity of ellipse

what is the eccentricity of ellipse

Define in biref about the final prestress, Define in biref about the Final ...

Define in biref about the Final Prestress The stress which exists after all losses of prestress have occurred substantially is known as final prestress. This may be calculated

Show the process of waterproofing for bridge decks, Q. Show the process of ...

Q. Show the process of Waterproofing for bridge decks? Waterproofing materials such as membranes are applied on top of bridge deck surface since:  (i)  Vehicular traffic (f

Methods of design of prestressed concrete member, Methods of design of pres...

Methods of design of prestressed concrete member What are different approaches or methods of design of prestressed concrete members? What are important considerations  in th

Determine the flow rate from the dewatering well, A construction project in...

A construction project involves excavation below grade. A 24 inch diameter dewatering well is installed from grade (EL 586) to 80 ft below grade to lower the water table. Soil bori

Cement, uses of heavy weight aggregate

uses of heavy weight aggregate

Civil, vcdjvoidj pirioi oique

vcdjvoidj pirioi oique

Define the planning an underwater inspection, Define the Planning an Underw...

Define the Planning an Underwater Inspection? Planning for underwater inspection is important because of - Unknown factors which may be discovered during the diving - Th

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd