Flexibility in contracts, Other Management

Assignment Help:

Flexibility in contracts

In the "1? and "2? modes, the single entity is the Lump Sum Turnkey Contract (LSTK), EPC contractor and the D-B contractor respectively. In both these modes, the contractor acts as a single point responsibility for the implementation of the project i.e. the contractor accepts financial liability for failure to meet any of the salient project deliverables of schedule, cost and performance. The drawback in this model is that you cannot change design or introduce new scope.

Mode "3? allows a good deal of flexibility to you, i.e. you will be able to maintain both executive control and open options for as long as possible, to respond to external conditions in this mode.

Theoretically, in mode "3?, the single entity model can be achieved if you can designate a project manager for in house project planning and project engineering personnel can report for the duration of the project.

In such a case, this team should have certain features which set it apart from the traditional function of a project company. For example:

  • A centralised clearing system should be established for timely project decisions involving diverse interests.
  • The team should get directly involved in managing participation by parties normally outside its direct control. The team should handle diverse activities such as feasibility studies, changing requirements, regulatory requirements, so on all of which are time-phased, and which require coordinated planning, scheduling, and control.
  • Organisational conflicts are bound to occur which need to be dealt with by top management.
  • The project staff hired will have to get back to their original function as you may not hire them in near future.

Construction projects are one-time undertakings and they do not justify for you to set up an in house staff, both from the viewpoint of efficient utilisation of staff and lack of project management skills. Hence, for medium size and big size projects, the project manager and the project team should be an outside agency and you can nominate a representative to whom the outside agency?s project manager reports. The benefits provided by the outside agency are that the agency?s services are more flexible; the agency usually has access to varied resources, and costs little in comparison to the total project commitment throughout its life.

This outside agency is popularly known as Project Management Company (PMC). You award the contracts for supplies and construction while the entire coordination and interfacing of the project works are carried out by the PMC.

In summary, you have understood that the degree of flexibility owned by you is greater in the D-B-B mode of contracting compared with the LSTK EPC mode of contracting. Some flexibility for changes can also be incorporated in the LSTK EPC mode, for example, escalation formula for providing financial compensation to contractor, mutually agreed basis for computing compensation for  marginal  extra  works  i.e.  works  not  envisaged  in  the original contract. Generally, a LSTK contractor will be inclined to demand a higher compensation and grant of longer time extensions for project completion when faced with major extra works.

The degree of flexibility in the D-B mode would fall between that of D-B-B mode and LSTK mode.


Related Discussions:- Flexibility in contracts

Write short notes on any two kinds of leaders, Question 1 Define communica...

Question 1 Define communication. Explain function and purpose of communication Question 2 Write down the advantages and disadvantages of oral communication Question 3 Wh

Debt management policy, ‘The overall objective of debt management is to min...

‘The overall objective of debt management is to minimise the cost of borrowing to the organisation.' Required: I. Explain factors which need to be taken into account, other t

Library catalogue and the five laws of library science , LIBRARY CATALOGUE ...

LIBRARY CATALOGUE AND THE FIVE LAWS OF LIBRARY SCIENCE The Five Laws. of Library Science are a set of basic guiding principles for designing and operating a library or a libr

Total quality management , T otal  Quality Management (TQM) It ...

T otal  Quality Management (TQM) It is developed by W. Edwards Demming TQM is a series of business practices designed to monitor the quality of production throughout al

Entrepreneurship, #question. I want detailed information about entrepreneur...

#question. I want detailed information about entrepreneurship.

Grunig-hunts public relations model, Problem 1 Strong employee relation...

Problem 1 Strong employee relations equals solid organizations. Companies that interact effectively with workers financially outperform those that don't. Identify and descri

Proposal or renewal sub system, Proposal or Renewal Sub System: Type  ...

Proposal or Renewal Sub System: Type                                         Web-based Application Role                                          Software Engineer Team s

ASSIGNMENT , How will you influence people to strive willingly for group o...

How will you influence people to strive willingly for group objectives in your organisation(Target based industry) ? apply your interpersonal influence through communication proces

What is the required rate of return on the project, QUESTION a. The ris...

QUESTION a. The risk free rate is 10 percent and the expected return on the market portfolio is 14 percent. A firm considers a project that is expected to have a beta of 1.3, w

Collation - binding processes, Collation: Collation is the first task ...

Collation: Collation is the first task in the binding processes. All the parts and the pages of a volume have to be correctly sequenced. In the case of periodicals, collation

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd