Flexibility in contracts, Other Management

Assignment Help:

Flexibility in contracts

In the "1? and "2? modes, the single entity is the Lump Sum Turnkey Contract (LSTK), EPC contractor and the D-B contractor respectively. In both these modes, the contractor acts as a single point responsibility for the implementation of the project i.e. the contractor accepts financial liability for failure to meet any of the salient project deliverables of schedule, cost and performance. The drawback in this model is that you cannot change design or introduce new scope.

Mode "3? allows a good deal of flexibility to you, i.e. you will be able to maintain both executive control and open options for as long as possible, to respond to external conditions in this mode.

Theoretically, in mode "3?, the single entity model can be achieved if you can designate a project manager for in house project planning and project engineering personnel can report for the duration of the project.

In such a case, this team should have certain features which set it apart from the traditional function of a project company. For example:

  • A centralised clearing system should be established for timely project decisions involving diverse interests.
  • The team should get directly involved in managing participation by parties normally outside its direct control. The team should handle diverse activities such as feasibility studies, changing requirements, regulatory requirements, so on all of which are time-phased, and which require coordinated planning, scheduling, and control.
  • Organisational conflicts are bound to occur which need to be dealt with by top management.
  • The project staff hired will have to get back to their original function as you may not hire them in near future.

Construction projects are one-time undertakings and they do not justify for you to set up an in house staff, both from the viewpoint of efficient utilisation of staff and lack of project management skills. Hence, for medium size and big size projects, the project manager and the project team should be an outside agency and you can nominate a representative to whom the outside agency?s project manager reports. The benefits provided by the outside agency are that the agency?s services are more flexible; the agency usually has access to varied resources, and costs little in comparison to the total project commitment throughout its life.

This outside agency is popularly known as Project Management Company (PMC). You award the contracts for supplies and construction while the entire coordination and interfacing of the project works are carried out by the PMC.

In summary, you have understood that the degree of flexibility owned by you is greater in the D-B-B mode of contracting compared with the LSTK EPC mode of contracting. Some flexibility for changes can also be incorporated in the LSTK EPC mode, for example, escalation formula for providing financial compensation to contractor, mutually agreed basis for computing compensation for  marginal  extra  works  i.e.  works  not  envisaged  in  the original contract. Generally, a LSTK contractor will be inclined to demand a higher compensation and grant of longer time extensions for project completion when faced with major extra works.

The degree of flexibility in the D-B mode would fall between that of D-B-B mode and LSTK mode.


Related Discussions:- Flexibility in contracts

Prospectus, This is a document which contains all relevant investor informa...

This is a document which contains all relevant investor information regarding the operations of an organization issuing privacies.

Describe the concept of Estate Management, Question: a. Estate Managem...

Question: a. Estate Management is a fairly new discipline of the Built Environment. Describe the concept of Estate Management and how its evolution during the past decade.

Define creativity, Question 1 What are special events? Give example. Wh...

Question 1 What are special events? Give example. What is meant by vision statement? What are the components of a good vision statement? Question 2 Every bidding doc

Public catalogue -circulation area in library building, Public Catalogue  ...

Public Catalogue  -Circulation Area in library building in library management Public catalogue is the key to the document collection in a library and frequently used by the re

Applying six sigma strategy to project management processes, A pplying Six...

A pplying Six Sigma business strategy to project management processes When an organisation would like to introduce the Six Sigma for the new management strategy, the following

Case study: royal blue, Case Study Royal Blue the national passenger ...

Case Study Royal Blue the national passenger carrier for commercial flight, appointed a new advertising company, Amadeus. Amadeus was hired to spearhead a more customer orien

Jit component in an organization''s tqm program, QUESTION a) ISO 9001:2...

QUESTION a) ISO 9001:2008 series embraces eight quality management principles. By using relevant examples in the business context, discuss the potential benefits an organizatio

Challenges in quality improvement, C hallenges Quality improvement can...

C hallenges Quality improvement can create conflicting situations and could result in complications. Project team members may be disillusioned by the past failures. The past e

Contract close-out, C ontract  close-out:   Contract  close-out  be...

C ontract  close-out:   Contract  close-out  begins  with  checking  for physical completion, i.e., whether all services have been performed and products delivered. Closeout

Purpose of the integrated management project, The Integrated Management Pro...

The Integrated Management Project is designed to: develop your capability to think and act strategically test your ability to apply the concepts taught and techniques le

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd