Flexibility in contracts, Other Management

Assignment Help:

Flexibility in contracts

In the "1? and "2? modes, the single entity is the Lump Sum Turnkey Contract (LSTK), EPC contractor and the D-B contractor respectively. In both these modes, the contractor acts as a single point responsibility for the implementation of the project i.e. the contractor accepts financial liability for failure to meet any of the salient project deliverables of schedule, cost and performance. The drawback in this model is that you cannot change design or introduce new scope.

Mode "3? allows a good deal of flexibility to you, i.e. you will be able to maintain both executive control and open options for as long as possible, to respond to external conditions in this mode.

Theoretically, in mode "3?, the single entity model can be achieved if you can designate a project manager for in house project planning and project engineering personnel can report for the duration of the project.

In such a case, this team should have certain features which set it apart from the traditional function of a project company. For example:

  • A centralised clearing system should be established for timely project decisions involving diverse interests.
  • The team should get directly involved in managing participation by parties normally outside its direct control. The team should handle diverse activities such as feasibility studies, changing requirements, regulatory requirements, so on all of which are time-phased, and which require coordinated planning, scheduling, and control.
  • Organisational conflicts are bound to occur which need to be dealt with by top management.
  • The project staff hired will have to get back to their original function as you may not hire them in near future.

Construction projects are one-time undertakings and they do not justify for you to set up an in house staff, both from the viewpoint of efficient utilisation of staff and lack of project management skills. Hence, for medium size and big size projects, the project manager and the project team should be an outside agency and you can nominate a representative to whom the outside agency?s project manager reports. The benefits provided by the outside agency are that the agency?s services are more flexible; the agency usually has access to varied resources, and costs little in comparison to the total project commitment throughout its life.

This outside agency is popularly known as Project Management Company (PMC). You award the contracts for supplies and construction while the entire coordination and interfacing of the project works are carried out by the PMC.

In summary, you have understood that the degree of flexibility owned by you is greater in the D-B-B mode of contracting compared with the LSTK EPC mode of contracting. Some flexibility for changes can also be incorporated in the LSTK EPC mode, for example, escalation formula for providing financial compensation to contractor, mutually agreed basis for computing compensation for  marginal  extra  works  i.e.  works  not  envisaged  in  the original contract. Generally, a LSTK contractor will be inclined to demand a higher compensation and grant of longer time extensions for project completion when faced with major extra works.

The degree of flexibility in the D-B mode would fall between that of D-B-B mode and LSTK mode.


Related Discussions:- Flexibility in contracts

Fixed interest bearing instrument, QUESTION When an investment is made ...

QUESTION When an investment is made in a fixed interest-bearing instrument, the risk is that the secondary market rate at which these instruments trade will increase, with a re

Define the term quality, Question 1 Define the term Quality Question 2 W...

Question 1 Define the term Quality Question 2 What is the objective of Reliability? Discuss various issues involved in ensuring Reliability Question 3 What are the basic princ

Explain the hawthorne studies, Question: There is no one specific metho...

Question: There is no one specific method of categorizing organization theories. However, it is generally accepted that: (a) The Type 1 theorists, also known as the classica

Requirements for direct contracting, Requirements for direct contracting  ...

Requirements for direct contracting  Let us now look at the requirements for direct contracting:    The requirement of direct contracting should be such that it can be ju

What is strategic management, QUESTION a) What is Strategic Management?...

QUESTION a) What is Strategic Management? b) With the help of a diagram describe the main elements of strategic management process c) Why strategy implementation often is

Requirements for force account , Requirements for force account  Let us...

Requirements for force account  Let us now look at the requirements for force accounting:  Force account should be justifiable as to why competitive bids cannot be invite

HEALTH INFORMATION MANAGEMENT, WHAT IS A RECORD FORMAT THAT DIVIDES THE RE...

WHAT IS A RECORD FORMAT THAT DIVIDES THE RECORD INTO SECTIONS?

Specifications of library reinforced binding, Specifications of Library Rei...

Specifications of Library Reinforced Binding: End papers:  Endpapers are to be of good tough opaque paper of approved mild colour, with at least one plan white leaf betwee

Request for proposal (rfp), Request for Proposal (RFP) The RFP document...

Request for Proposal (RFP) The RFP document for procurement of consultant is similar to tender document for procurement for works and goods. RFP provides all the instructions

Requirements of shopping , Requirements of shopping  Let us now look at...

Requirements of shopping  Let us now look at the requirements for shopping:  The value of the work or goods should be of a lesser value and the nature of business should

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd