Flexibility in contracts, Other Management

Assignment Help:

Flexibility in contracts

In the "1? and "2? modes, the single entity is the Lump Sum Turnkey Contract (LSTK), EPC contractor and the D-B contractor respectively. In both these modes, the contractor acts as a single point responsibility for the implementation of the project i.e. the contractor accepts financial liability for failure to meet any of the salient project deliverables of schedule, cost and performance. The drawback in this model is that you cannot change design or introduce new scope.

Mode "3? allows a good deal of flexibility to you, i.e. you will be able to maintain both executive control and open options for as long as possible, to respond to external conditions in this mode.

Theoretically, in mode "3?, the single entity model can be achieved if you can designate a project manager for in house project planning and project engineering personnel can report for the duration of the project.

In such a case, this team should have certain features which set it apart from the traditional function of a project company. For example:

  • A centralised clearing system should be established for timely project decisions involving diverse interests.
  • The team should get directly involved in managing participation by parties normally outside its direct control. The team should handle diverse activities such as feasibility studies, changing requirements, regulatory requirements, so on all of which are time-phased, and which require coordinated planning, scheduling, and control.
  • Organisational conflicts are bound to occur which need to be dealt with by top management.
  • The project staff hired will have to get back to their original function as you may not hire them in near future.

Construction projects are one-time undertakings and they do not justify for you to set up an in house staff, both from the viewpoint of efficient utilisation of staff and lack of project management skills. Hence, for medium size and big size projects, the project manager and the project team should be an outside agency and you can nominate a representative to whom the outside agency?s project manager reports. The benefits provided by the outside agency are that the agency?s services are more flexible; the agency usually has access to varied resources, and costs little in comparison to the total project commitment throughout its life.

This outside agency is popularly known as Project Management Company (PMC). You award the contracts for supplies and construction while the entire coordination and interfacing of the project works are carried out by the PMC.

In summary, you have understood that the degree of flexibility owned by you is greater in the D-B-B mode of contracting compared with the LSTK EPC mode of contracting. Some flexibility for changes can also be incorporated in the LSTK EPC mode, for example, escalation formula for providing financial compensation to contractor, mutually agreed basis for computing compensation for  marginal  extra  works  i.e.  works  not  envisaged  in  the original contract. Generally, a LSTK contractor will be inclined to demand a higher compensation and grant of longer time extensions for project completion when faced with major extra works.

The degree of flexibility in the D-B mode would fall between that of D-B-B mode and LSTK mode.


Related Discussions:- Flexibility in contracts

Tangible and intangible value, Tangible and Intangible Value The value ...

Tangible and Intangible Value The value which communities create includes the tangible results like the standard manual, the improved skills or the reduced costs through faster

Cluster sampling, Cluster Sampling In cluster sampling there  is  a su...

Cluster Sampling In cluster sampling there  is  a successive random . sampling of units. The first unit  to  be sampled is large grouping or clusters. For example,  in  drawin

Choice of bindery- factors to be considered , Choice of Bindery: Factors to...

Choice of Bindery: Factors to be Considered  Outside binders are normally selected through competitive bidding or through free selection. Whatever the case, the librarians sho

Implementation of the project and assign a time frame, Government has decid...

Government has decided to construct a tunnel via le Pouce Mountain to provide an alternative access to Port Louis for road users coming from the east. Assuming that roads on both s

State two reasons for establishing a marcom plan, Question: (a) Th...

Question: (a) There are different types of advertising strategies adopted by Organizations in order to increase their sales force. The strongest advertising strategies

Objectives of the reform process for the public sector, Question : a) ...

Question : a) The process of reform and modernisation of the public sector in Mauritius started as far back as in the 1990s. What according to you have been the major pressu

Customer marketing interface, five to make a displeased student to patonise...

five to make a displeased student to patonise a school canteen

User needs and use and user studies, User Needs and Use and User Studies: ...

User Needs and Use and User Studies: Libraries, information centres and databanks are now known as information facilities which exist for the benefit of users. The management

Inadequacies of the traditional public administration, Question 1: The ...

Question 1: The Public Sector is undergoing a major transformation. What according to you, are the imperatives that are driving the change process ? Question 2: What

Sponsorship, Hi, i need to motivate a sponsorship program to exco as part o...

Hi, i need to motivate a sponsorship program to exco as part of my marketing assignment. I have no idea how to do this. Can you help?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd