Find speed for two hours with hss tools, Mechanical Engineering

Assignment Help:

Find speed for two hours with HSS tools

Find speed for two hours tool life for dry machining of free cutting mild steel with HSS tool.

Solution

From Table 3, a value of C = 74 m/min is chosen while for HSS tool a mean value of n = 0.125 has been assumed.

V tn = C

V = C /t n

=  74 /1200.125

= 74 /1.82

= 40.67

= 40.67 metres/minute

Table 3: Constant C for Taylor's Equation

990_Tool Life Equation 1.png


Related Discussions:- Find speed for two hours with hss tools

Cutting test, Cutting Test:             Once the sand blasted blade we...

Cutting Test:             Once the sand blasted blade were went through the washing process. Quality Control technician will randomly pick 15 pieces of blade to go for cutting

Combustion chamber and radiant section, Q. Combustion Chamber and Radiant S...

Q. Combustion Chamber and Radiant Section? The combustion chamber and the radiant heat transfer section of the Steam Generators shall be a horizontal, multiple pass arrangement

Wire-frame entities-representing ellipse and parabolas, wire-frame entities...

wire-frame entities-representing ellipse and parabolas

Find out the axial moment of inertia, Find out the axial moment of inertia:...

Find out the axial moment of inertia: Find out the axial moment of inertia of a rectangular area of base b and height d around centroidal axis GX and the base B 1 B 2 . So

Thermocouple, calibration curve standard temparature vs indicator tempratur...

calibration curve standard temparature vs indicator temprature.

Determine the point of intersection jets, A tank has two identical orifices...

A tank has two identical orifices in one of its vertical sides. The upper orifice is 3m below the water surface and lower one is 5m below the water surface. If the value of Cv for

Explain the information phase of radial drilling machine, Information Phase...

Information Phase: Step: To secure all and complete information and gather facts and from best sources.   Our project is selected based on the current problem face by the

What is the difference between mis and erp, MIS MIS:- Management Infor...

MIS MIS:- Management Information System Produces reports on user demand MIS is use for the Decision making reports It Collect data form of all department then produce

Conceptual engineering phase in project development, Q. Conceptual engineer...

Q. Conceptual engineering phase? During this phase, a conceptual engineering estimate will be prepared by Project Management with input from all disciplines. Activities at t

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd