East Coast Manufacturing, Inc. plans to locate a new production facility in Hartford, Philadelphia, or Baltimore. Six location factors are important: cost per product unit, labor availability, union activities, local transportation, proximity to similar industry and proximity to raw materials. The weighting of these factors, the scale for each factor and the scores for each location are shown below. Different SME's (subject matter experts) scored each of the non-economic factors. So, unfortunately, the scores for the non-economic factors are scaled differently. The scales are indicated on the table. On the scale, the highest score is always the best value. For example, for the scale 1-5, the best value is 5. For each of the Non-economic factors, it is possible to score the maximum.
Location Factor
Factor Weight
Scale
Hartford
Philadelphia
Baltimore
Cost per product unit
0.55
$48
$59
$52
Labour availability
0.15
0-5
2.5
4.0
Union activities
0.10
0-3
2.7
1.8
0.9
Local transportation
1.2
2.4
Proximity to similar industry
0.05
0-1
0.5
1.0
0.7
Proximity to raw materials
0.6
0.4
For the following, calculate all results three decimal place (example, 0.xxx or x.xxx).
a) Using the factor scoring (or equivalent the factor rating) approach we studied in class and modified as appropriate, which site do you recommend? Why?
b) With everything else remaining the same as in the problem statement, what must the cost per product unit for Philadelphia be so that its total factor score is equal to the total factor score for Hartford?
Legacy Systems and Improvements Please respond to the following: •From the e-Activity, discuss the challenges legacy systems pose for enterprise system integration. Provide specifi
Interaction - Service Process Matrix Interaction refers to the degree to which the customer can intervene in the process (eg in a restaurant, the customer may call a waiter at
The production manager at company XYZ needs to prepare forecasts of product demand in order to plan for appropriate production quantities. In the past, demand for the product has b
what are the wastes and how to overcome them?
How would you go about analyzing an organizational structure in terms of creating a work breakdown structure? What are the major organizational characteristics that you would evalu
Atkinson department is installing new computer system. They have to perform several activities. Following table provides information about the project: Activity
Suppose you realize one day that you are dissatisfied with your job. What might you do to improve your situation? What are the basic differences between management and leadership?
All work packages in a project: Answer Do not have to be at the same level of the WBS Must be at the same level of the WBS Do not have to be referenced in the Work Brea
which of the following is a characteristic shared by frame relay and ATM? a. the use of virtual circuits b. the use of fixed-sized packets known as cells c. the use of ded
Productivity is a relative measure is true or false
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd