Question:
The following diagram shows a C.P.A.-network modeling the stages in the construction project. Each arc is labeled with the letter denoting the activity it represents and a weight that denotes the number of days needed to complete that activity. Activities A and B can start as soon as the project commences, and the project is finished when I and K have been completed. The arc labeled Z represents a dummy activity introduced to model the logical structure of the network.
(a) List the prerequisite activities for (i) G and (ii) I in this construction project. Explain why it is necessary to introduce the dummy activity Z to obtain the C.P.A.-network.
(b) Say what a vertex in a C.P.A.-network represents. Copy the network above and give its vertices an acyclic labeling v1, v2,..., v8, where v1 represents the start of the manufacturing process.
(c) Say what is meant by the early event time ET (v) and the late time event LT (v) for an event v. Calculate ET (v) and LT (v) for each event in this project, entering these times in the appropriate boxes on your diagram.
(d) What is the shortest time in which this project can be completed?
(e) Suppose an activity is represented by the arc vivj with weight w (vivj). Say how the total float time for this activity is calculated. Tabulate the total float time for each activity in this project.
(f) Identify all the critical activities in this project and find the critical path(s) in this C.P.A.-network.
QUESTION 1 (i) Why ethics is important in procurement? (ii) How a public official involved in planning or conducting public procurement proceedings or contract administratio
Direct contracting is another procurement method that is used under a limited number of exceptional circumstances. In Direct contracting method, contract for works or supply is ma
REQUIREMENTS FOR THE ORGANISATION OF RESOURCE SHARING LIBRARY NETWORKS One of the significant aspects that needs attention is that in a resource sharing network, each particip
M ergers Merger happens when two companies, mostly of the same size, agree to go forward as a single new company in the best interest of both. The shareholders of the involved
Six Sigma - Cynics view The Six Sigma has taken on the life of its own. The cynics might see it as "the next big thing" which will fade as soon as the new buzzword will come al
Meaning of Classification: Systematic grouping of entities (both abstract and concrete) to meet one's requirement is known as classification. Classification lies at the root o
Question 1: (a) Describe the characteristics of a confined space. (b) By reference to entry into a confined space, describe briefly the factors that should be considered
Steps of Organisational Change Organisational change is characterised by a set of actions that may cause a strategic shift in its functioning or a change in processes, tasks an
QUESTION 1 (a) Describe the role of public sector in the development of tourism Industry? (b) Describe the role of private sector in the development of tourism Industry?
QUESTION 1 (a) State 5 criteria which should be taken into consideration when planning a safe place of work. (b) Briefly describe them. QUESTION 2 (a) Define a safe
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd