Q.- Explain the Unit hydrograph Method for estimation of peak flood discharge in a river.

Ans.-

Unit hydrograph Method

A hydrograph is a representation of hydraulic characteristic of river discharge . A point on the hydrograph shows the available discharge at that time . The area under the hydrograph came between any two intervals of time say t1 to t2 shows the volume of water that has passed the measuring point in time t1 to t2.

A concept of unit hydrograph is based on the fact that for a given point in a given stream of a basin the storm of different intensity but of the same unit duration produces hydrograph of surface run off of equal length of time and of the similar shape. The ordinates are proportional to the magnitude of rain fall with the assumption that the rain fall is distributed uniformly over the entire area.

The unit hydrograph is thus defined as the hydrograph which is produced by a rainfall of given duration uniformly distributed over the catchment and which produces a direct run off volume of a unit depth of 1 cm over the entire catchment area.

Hydrograph method consists of constructing a unit hydrograph or distribution graph for the catchment and then by use of given rainfall data, the hydro graph runoff is calculated.


Related Discussions:- Explain the unit hydrograph method

Determine the active thrust on the wall, A retaining wall 9 m high retains ...

A retaining wall 9 m high retains granular fill weighing 18 kN/m 3 with level surface. The active thrust on the wall is 180 kN per metre length of the wall. The height of the wall

Calculate dead, A building cross section is shown below. The building consi...

A building cross section is shown below. The building consists of eight (8) of the shown frames placed at distance of 20 feet oc for a total length of 140 feet. The glulam beams ar

Reciprocal ranging, what do you mean by reciprocal ranging explain with a n...

what do you mean by reciprocal ranging explain with a neat sketch

State the needs for high strength steel and concrete, State the Needs for h...

State the Needs for high strength steel and concrete In  prestressed  concrete construction, tendons have 3  small area of cross-section compared  to the cross-sectional  area

Bridge engineering, long span bridge or continuous bridge which is more pre...

long span bridge or continuous bridge which is more preferable and why ??? what is the major problem in continuous bridge and what would be its effect if there is any differential

What do you mean by stock verification sheets, Q. What do you mean by Stock...

Q. What do you mean by Stock Verification Sheets? The proper custody and accountal of stores is the prime duty and function of an executive or the stockholder. To ensure this v

Explain the departure of a line - transportation, Explain the Departure of ...

Explain the Departure of a line - Transportation Departure of a line is the distance that the line extends in an east or west direction. A line that runs towards east has a pos

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd