Q.- Explain the Unit hydrograph Method for estimation of peak flood discharge in a river.

Ans.-

Unit hydrograph Method

A hydrograph is a representation of hydraulic characteristic of river discharge . A point on the hydrograph shows the available discharge at that time . The area under the hydrograph came between any two intervals of time say t1 to t2 shows the volume of water that has passed the measuring point in time t1 to t2.

A concept of unit hydrograph is based on the fact that for a given point in a given stream of a basin the storm of different intensity but of the same unit duration produces hydrograph of surface run off of equal length of time and of the similar shape. The ordinates are proportional to the magnitude of rain fall with the assumption that the rain fall is distributed uniformly over the entire area.

The unit hydrograph is thus defined as the hydrograph which is produced by a rainfall of given duration uniformly distributed over the catchment and which produces a direct run off volume of a unit depth of 1 cm over the entire catchment area.

Hydrograph method consists of constructing a unit hydrograph or distribution graph for the catchment and then by use of given rainfall data, the hydro graph runoff is calculated.


Related Discussions:- Explain the unit hydrograph method

Non destructive inspection steel/cast iron substructure, Explain the Non De...

Explain the Non Destructive Inspection Steel/Cast Iron Substructures Some of the structural defects in steel structures may not be visible during visual inspection. In that eve

Road location in dune areas, Road Location in Dune Areas: The followi...

Road Location in Dune Areas: The following principle should be observed in locating a road in dune areas : (a) Align a road where sand is covered by vegetation. (b) Sel

Engineering survey, With respect to implementation of Civil Engineering pro...

With respect to implementation of Civil Engineering projects explain the relevance of application of the principle of ''Working from Whole to Part''

Survey, what is road survey ?

what is road survey ?

Geology, http://www.expertsmind.com/engineering-homework-assignment-help.as...

http://www.expertsmind.com/engineering-homework-assignment-help.aspx

Explain the contracted rectangular weir, Explain the Contracted Rectangular...

Explain the Contracted Rectangular Weir Weir plate has sides which extend above the maximum water surface, directing the flow through an opening (b = weir length). Typically th

Define Statically indeterminate structures, Statically indeterminate struct...

Statically indeterminate structures a. Fall into two categories: 1.  Beam problems with additional supports/restraints 2.  Axial bar members subjected to temperature/forc

Shear lag in typical box-girder bridge, Shear lag in typical box-girder bri...

Shear lag in typical box-girder bridge For multiple-cell box girders, there are normally two arrangements. First one is that independent cells are connected by their top flang

Determine the amount of excavated material, The footprint of a proposed off...

The footprint of a proposed office building is overlaid on the existing contours topographic map of a sloping site as shown in the figure. The structural bays which are 65-ft by 65

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd