Explain the unit hydrograph method, Civil Engineering

Assignment Help:

Q.- Explain the Unit hydrograph Method for estimation of peak flood discharge in a river.

Ans.-

Unit hydrograph Method

A hydrograph is a representation of hydraulic characteristic of river discharge . A point on the hydrograph shows the available discharge at that time . The area under the hydrograph came between any two intervals of time say t1 to t2 shows the volume of water that has passed the measuring point in time t1 to t2.

A concept of unit hydrograph is based on the fact that for a given point in a given stream of a basin the storm of different intensity but of the same unit duration produces hydrograph of surface run off of equal length of time and of the similar shape. The ordinates are proportional to the magnitude of rain fall with the assumption that the rain fall is distributed uniformly over the entire area.

The unit hydrograph is thus defined as the hydrograph which is produced by a rainfall of given duration uniformly distributed over the catchment and which produces a direct run off volume of a unit depth of 1 cm over the entire catchment area.

Hydrograph method consists of constructing a unit hydrograph or distribution graph for the catchment and then by use of given rainfall data, the hydro graph runoff is calculated.


Related Discussions:- Explain the unit hydrograph method

Determine the variation of safe bearing capacity of soi, State the algebrai...

State the algebraic equations showing the variation of safe bearing capacity of soil (for clay and sand to be given separately) in shallow foundation with: (i) depth of foundati

Normal stress, how does wrong calculations in normal stress cause partial o...

how does wrong calculations in normal stress cause partial or total collapse of a building?

Work, Grouted or Penetration Macadam:

Grouted or Penetration Macadam:

Construction management, i would like to get a project done. I have some pl...

i would like to get a project done. I have some plans and I need a cost estimate on how much it will cost to get it constructed.

Concrete cracking, Attached information shows construction details of a wat...

Attached information shows construction details of a water tank. The slab was poured in one pour and the walls (incl. Baffles) were poured in two even sections. Forms were stripped

A concrete compression machine, Question In a concrete compression test , ...

Question In a concrete compression test , usually 150mmx150mmx150mm concrete cube examples are used for testing. Why isn't 100mmx100mmx100mm concrete cube samples used in test in

Define the term - prestressing force, Define the term - prestressing force ...

Define the term - prestressing force It should be realized that the maximum amount of prestressing force which can be  transferred from tendons to concrete depends on the bond

Explain the angle of wall friction, A retaining wall 4.5 m high with vertic...

A retaining wall 4.5 m high with vertical back supports a backfill with horizontal surface. The unit weight of the fill is 18 kN/m 3 and the angle of internal friction is 36°. The

Project management, Project Management: This unit starts with the gene...

Project Management: This unit starts with the general definition of Project management. Several phases involved in project management are also desribed. Further, the technique

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd