Explain the purpose of embedding puddle flange, Civil Engineering

Assignment Help:

Purpose of embedding puddle flange inside the walls of closed valve chambers

When valves are closed to stop water flow in a pipeline, a thrust is produced along the direction of the pipeline. Henceforth, it is essential to restrain the valves at the time of closure to prevent it from moving in the thrust direction. If the closed valve is situated inside valve chambers, it is connected to a puddle flange embedded inside a wall of chamber. So the closed valves can be effectively restrained from the thrust action at the time of the closure of valves.


Related Discussions:- Explain the purpose of embedding puddle flange

Determine the weight of solids mixed in the suspension, In a hydrometer ana...

In a hydrometer analysis, the corrected hydrometer reading in a 1000 ml uniform soil suspension at the start of sedimentation was 28. After a lapse of 30 minutes, the corrected hyd

Determine the active thrust on the wall by culmann method, A retaining wall...

A retaining wall with its face inclined at 75° with horizontal is 10 m high and retains soil inclined at a uniform surcharge angle of 10°. If the angle of internal friction of the

Ranging, defference between direct and indirect ranging..

defference between direct and indirect ranging..

Unsymmetrical bending, An 8 kN.m moment is applied at the end of a block fi...

An 8 kN.m moment is applied at the end of a block fixed into the ground as illustrated in thefigure below. The moment vector (double arrow head representation) acts in line with th

Impact of possible energy, a) Take into consideration the boiler efficiency...

a) Take into consideration the boiler efficiency, and verify the cost of heating the building, during the heating season, using present oil and gas prices.  b) Investigate the i

Significance of tailwater level in culverts, Significance of tailwater leve...

Significance of tailwater level in culverts Headwater level and tailwater level of culverts are significant parameters in hydraulic design. Headwater level can't be set too la

Geometric design, calculating OVERTAKING SIGHT DISTANCE

calculating OVERTAKING SIGHT DISTANCE

SURVEYING II LAB, Explain Designation of bearings. Calculate included angle...

Explain Designation of bearings. Calculate included angle from bearings

Define major ions present in the water, Define Major Ions present in the wa...

Define Major Ions present in the water  Cations:  Calcium, Magnesium, sodium, potassium Anions: Bicorabonate, sulfate, chloride Other ions present: Iron. Manganese, Fluor

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd