Explain synchronisation and parallel operation, Electrical Engineering

Assignment Help:

Explain Synchronisation and Parallel Operation

Generation, transmission and distribution of electric power have to be conducted in an efficient and reliable way at a reasonable cost with the least amount of interruptions. Consequently, in a large power system many synchronous generators are connected in parallel to a common line known as an infinite bus of fixed voltage and frequency, and pre-determined phase sequence. A number of safety requirements need to be satisfied prior to connecting a generator to the infinite bus (this is called a synchronising procedure):

2448_Explain Synchronisation and Parallel Operation.png

(1) The operating frequency,

(2) The line voltage and

(3) The phase sequence must all be the same as those for an infinite bus.

To meet an increased load demand, let us, for instance, bring a second generator into service as shown in Figure. The necessary synchronisation procedure consists of the following major steps. The speed of the incoming generator is adjusted to obtain the frequency of the induced voltage equal to that of the infinite bus. Now that the frequency match is achieved the field current can be raised to a level at which the induced voltage of the second generator is identical to the bus voltage. In order to verify the phase sequence, three lamps are connected asymmetrically as illustrated in the figure. When the phase sequence is correct, the lamp LI will be dark, while the other two lamps will glow brightly. If the phase sequence is not proper, all the lamps will glow or become dark simultaneously. When all the above conditions are met, the second generator can be safely connected to the infinite bus by closing the appropriate circuit breaker.

In addition to the lamps to check the conditions for synchronism, an electronic device (often computer controlled) called a synchroscope is also used to perform a precise switching when the above criteria are fulfilled. It provides the information on the incoming generator as to whether it is running at a lower or higher speed. At a proper speed and a correct phase sequence, the synchroscope indicates zero when the synchronising switch must be closed to connect the second generator on line. At this moment, it is neither receiving nor delivering any power. This is referred to as the floating stage of the generator. If we now increase the field current, the second generator will produce reactive power and help improve voltage regulation. Else, if an attempt is made to increase the rotor speed, the torque developed will increase and the second generator will begin to supply active power to the load.


Related Discussions:- Explain synchronisation and parallel operation

Critical rate of rise of voltage - thyristor , Critical Rate of Rise of Vol...

Critical Rate of Rise of Voltage It  depends on  the junction temperature higher  the junction  temperature lower  the critical rate of  rise of  voltage. It is also known  as

Microcontroller interfacing, The winch uses a 415 Volt 50 Hz AC motor, so b...

The winch uses a 415 Volt 50 Hz AC motor, so both the up/down and run/stop controls actually operate +24V relays, whose contacts switch the 415Vac to the winch. The relays also pro

Determine the value of sr flip-flop, The inputs to an SRFF are shown in Fig...

The inputs to an SRFF are shown in Figure. Determine the value of Q at times t 1 , t 2 , and t 3 .

Calculate the voltage regulation, The per-phase synchronous reactance of a ...

The per-phase synchronous reactance of a three-phase, wye-connected, 2.5-MVA, 6.6-kV, 60-Hz turboalternator is 10. Neglect the armature resistance and saturation. Calculate the vo

Compare with register, Compare with Register The contents  of the re...

Compare with Register The contents  of the register  are compared with  the contents  of the accumulator  here  register  may be  any one  of the  A, B, C, D E, H, or L  reg

Role of electricity regulatory commission in kpi, Role of Electricity Regul...

Role of Electricity Regulatory Commission in KPI The new Electricity Act, 2003, has empowered Electricity Regulatory Commission (ERC) to play an extremely decisive role in all

Explain the synchronous up-down counters, Explain the Synchronous Up-Down C...

Explain the Synchronous Up-Down Counters? The circuit of a 3-bit synchronous up-down counter and a table of its sequence are shown below.  Alike to an asynchronous up-down count

Metering techniques, Metering Techniques The techniques of metering co...

Metering Techniques The techniques of metering could be categorized depending upon the voltage at which consumers are fed as: 1. LT (Low Tension) Metering, and 2. HT (Hi

Transformer, how back emf is produced in transformer?

how back emf is produced in transformer?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd