Explain synchronisation and parallel operation, Electrical Engineering

Assignment Help:

Explain Synchronisation and Parallel Operation

Generation, transmission and distribution of electric power have to be conducted in an efficient and reliable way at a reasonable cost with the least amount of interruptions. Consequently, in a large power system many synchronous generators are connected in parallel to a common line known as an infinite bus of fixed voltage and frequency, and pre-determined phase sequence. A number of safety requirements need to be satisfied prior to connecting a generator to the infinite bus (this is called a synchronising procedure):

2448_Explain Synchronisation and Parallel Operation.png

(1) The operating frequency,

(2) The line voltage and

(3) The phase sequence must all be the same as those for an infinite bus.

To meet an increased load demand, let us, for instance, bring a second generator into service as shown in Figure. The necessary synchronisation procedure consists of the following major steps. The speed of the incoming generator is adjusted to obtain the frequency of the induced voltage equal to that of the infinite bus. Now that the frequency match is achieved the field current can be raised to a level at which the induced voltage of the second generator is identical to the bus voltage. In order to verify the phase sequence, three lamps are connected asymmetrically as illustrated in the figure. When the phase sequence is correct, the lamp LI will be dark, while the other two lamps will glow brightly. If the phase sequence is not proper, all the lamps will glow or become dark simultaneously. When all the above conditions are met, the second generator can be safely connected to the infinite bus by closing the appropriate circuit breaker.

In addition to the lamps to check the conditions for synchronism, an electronic device (often computer controlled) called a synchroscope is also used to perform a precise switching when the above criteria are fulfilled. It provides the information on the incoming generator as to whether it is running at a lower or higher speed. At a proper speed and a correct phase sequence, the synchroscope indicates zero when the synchronising switch must be closed to connect the second generator on line. At this moment, it is neither receiving nor delivering any power. This is referred to as the floating stage of the generator. If we now increase the field current, the second generator will produce reactive power and help improve voltage regulation. Else, if an attempt is made to increase the rotor speed, the torque developed will increase and the second generator will begin to supply active power to the load.


Related Discussions:- Explain synchronisation and parallel operation

What is the significance of source gate cutoff voltage, Q. What is the sign...

Q. What is the significance of source gate cutoff voltage? The source gate cutoff voltage is also called pinch off voltage. It is obtained when VDS increases and approaches a l

Ldax load accumulator indirect instruction , LDAX  Load Accumulator Indire...

LDAX  Load Accumulator Indirect Instruction This instruction is used to copy data  from memory  location pointed by register  pair only  BC or DE  to the accumulator  HL pair

Sign flag - sub subtract instruction , Sign flag Since D 7  bit in ...

Sign flag Since D 7  bit in the  results is 0sign flag is reset. This also  shown that the results is positive.

Binary codes, what are the types of binary codes

what are the types of binary codes

#titleElectromagnetic Induction, Hello, I have some questions pertaining t...

Hello, I have some questions pertaining to electromagnetic induction. Could you please give me a hand? Thanks. If we increase the speed of the bar magnet slowly from 0 to 8, and

Spectrum analyser, The spectrum analyser plots amplitude against frequency,...

The spectrum analyser plots amplitude against frequency, in other words it shows signals in the frequency domain. The spectrum analyser has the same trigger options as the oscillos

Collector-to-base bias, Collector-to-base bias: Figure: Collec...

Collector-to-base bias: Figure: Collector-to-base bias This configuration uses negative feedback to avoid thermal runaway and stabilize the operating point. In th

Explain synchronisation and parallel operation, Explain Synchronisation and...

Explain Synchronisation and Parallel Operation Generation, transmission and distribution of electric power have to be conducted in an efficient and reliable way at a reasonable

A, A microstrip antenna system operating at 915MHz must be designed using R...

A microstrip antenna system operating at 915MHz must be designed using Rogers RO3010 substrate with the thickness of 0.635mm.

Find the transfer function of a linear system, Q. The response y(t) of a li...

Q. The response y(t) of a linear system to an excitation x(t) = e -2t u(t) is y(t) = (t + 2)e -t u(t). Find the transfer function.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd