Explain synchronisation and parallel operation, Electrical Engineering

Assignment Help:

Explain Synchronisation and Parallel Operation

Generation, transmission and distribution of electric power have to be conducted in an efficient and reliable way at a reasonable cost with the least amount of interruptions. Consequently, in a large power system many synchronous generators are connected in parallel to a common line known as an infinite bus of fixed voltage and frequency, and pre-determined phase sequence. A number of safety requirements need to be satisfied prior to connecting a generator to the infinite bus (this is called a synchronising procedure):

2448_Explain Synchronisation and Parallel Operation.png

(1) The operating frequency,

(2) The line voltage and

(3) The phase sequence must all be the same as those for an infinite bus.

To meet an increased load demand, let us, for instance, bring a second generator into service as shown in Figure. The necessary synchronisation procedure consists of the following major steps. The speed of the incoming generator is adjusted to obtain the frequency of the induced voltage equal to that of the infinite bus. Now that the frequency match is achieved the field current can be raised to a level at which the induced voltage of the second generator is identical to the bus voltage. In order to verify the phase sequence, three lamps are connected asymmetrically as illustrated in the figure. When the phase sequence is correct, the lamp LI will be dark, while the other two lamps will glow brightly. If the phase sequence is not proper, all the lamps will glow or become dark simultaneously. When all the above conditions are met, the second generator can be safely connected to the infinite bus by closing the appropriate circuit breaker.

In addition to the lamps to check the conditions for synchronism, an electronic device (often computer controlled) called a synchroscope is also used to perform a precise switching when the above criteria are fulfilled. It provides the information on the incoming generator as to whether it is running at a lower or higher speed. At a proper speed and a correct phase sequence, the synchroscope indicates zero when the synchronising switch must be closed to connect the second generator on line. At this moment, it is neither receiving nor delivering any power. This is referred to as the floating stage of the generator. If we now increase the field current, the second generator will produce reactive power and help improve voltage regulation. Else, if an attempt is made to increase the rotor speed, the torque developed will increase and the second generator will begin to supply active power to the load.


Related Discussions:- Explain synchronisation and parallel operation

Detrmine when the current flowing in the conductor, A conductor 300 mm long...

A conductor 300 mm long moves at a uniform speed of 4 m/s at right-angles to a uniform magnetic field of flux density 1.25 T. Verify the current flowing in the conductor when  (

Show binary to octal conversion, Q. Show Binary to Octal Conversion? It...

Q. Show Binary to Octal Conversion? It is simple to convert from an integer binary number to octal. This is accomplished by: Break the binary number into 3-bit secti

Instability problem, We would like you to do an indepth study/research in t...

We would like you to do an indepth study/research in the tradeoff between the filtering of the QR and the QR performance So it will be about filtering but more of an indepth for

Define and explain numerical aperture, Define and explain Numerical apertur...

Define and explain Numerical aperture? Figure shown below shows an incident ray to the fibre, The light bends at two interfaces, one at the air- core interface and the

Explain protected mode addressing, Explain protected mode addressing. ...

Explain protected mode addressing. This addressing permits access to data and programs located as the first 1M byte of memory, with in the first 1M byte of memory. Addressing

Find an expression for the instantaneous force, Q. Let the solenoid carry a...

Q. Let the solenoid carry an alternating current of 10 A (rms) at 60 Hz instead of the direct current. Find an expression for the instantaneous force.

Transformer, Why we provide the short circuit and open circuit test in tran...

Why we provide the short circuit and open circuit test in transformer

Find the current in each resistor, For the network shown in Figure, find th...

For the network shown in Figure, find the current in each resistor by means of nodal analysis.

Find out the output if resistance, Q. The input to the differentiator circu...

Q. The input to the differentiator circuit is a sinusoidal voltage of peak value 5mv and frequency 1kHZ. find out the output if R=100K and C=10^-6F Solution. The equation

Case 2 a>b - program description, Case 2 ( A>B) Suppose XX = 05H ( stor...

Case 2 ( A>B) Suppose XX = 05H ( stored  in A ) And  YY = 02H ( stored  in B). Then carry  flag will  reset by CMP instruction, since  A> B in this  case JNC  will transfer the

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd