DG Company has made a significant investment in a project to develop a new client management IT system, which when implemented should help give the company a competitive edge. However, all is not well with the management of the project and B, the project sponsor, is particularly concerned about the progress.
There appear to have been a series of problems throughout the project which B feels she should have been alerted to. The result has been that the project manager she had appointed has now resigned, complaining that he was unclear on his role in the project, and that B was constantly interfering.
Explain how using a project management methodology, like as PRINCE2, could help minimise the problems that have occurred in the client management IT system project.
PRINCE2 is an acronym for Projects In Controlled Environments and is a structured approach to project management. Fundamentally it provides a project framework with a set of project tools, guidelines and standards. It contains bureaucratic controls on the planning and implementation so that any potential problems that may increases are identified and can be resolved early in the process. Whilst it could be argued that aspects of PRINCE2 could be considered to be just good project management, the dissimilarity is in the level of structure and documentation needed.
The key processes of PRINCE2 methodology offer a number of features that would help the client management IT system project, containing:
Differences between wbs and product breakdown structure, Project Management
Materials Management as an Operating Function : In small scale industries generally the function of materials management is considered subordinate to the production func
Scenario: You are a member of the Project Review team for CK Software Services. At the next meeting, the team will discuss the scheduling for the new automated teller machine (ATM)
o Does the project plan clearly identify a set of functional increments leading to project completion? o Is the sequence of objectives consistent with both the risk priority and
Question 1: Define deterministic model of inventory control. Explain inventory costs and relationships Description of deterministic model of inventory control Invento
Need to get critical analysis of the Document, Project Management Body of Knowledge 1996 by the Standard committee of the PMI 8 pages. how much would this cost?
What are the techniques used for a post completion review? Techniques used for a PC (post completion) review: a. End user satisfaction surveys regarding to the quality of th
what are the segments involved in project management structure?
GBF Group is a leading food and beverage manufacturer with an international presence in over 50 countries worldwide. The group has seven strategic business units (SBUs) and each ha
Influence of Organization culture on key dimensions of management
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd