Evaluate the length of guide bund, Civil Engineering

Assignment Help:

Q. Evaluate the Length of guide bund?

For encouraging axial flow through the bridge, upstream length of guide bund may be kept 1.0 to 1.5 times the bridge length and downstream length 0.25 to 0.40 times the bridge length. Length necessary for keeping worst possible embayment behind the guide bund sufficiently away from the approach bank is also required to be ascertained by fitting of sharpest loop as indicated in Figure 5.2 in Chapter 5. If field data of acute bends in river when cut offs occurred is not available, It may be assumed that radius of such a bend can be equal to 0.4 times the radius of average bends if maximum river discharge is up to 5660 m3/s and equal to 0.5 times the radius of average bends if the maximum discharge is more than 5660 m3/s. In case of braided rivers, the length determined on basis of both the considerations of axial flow through bridge and keeping away the worst loop may be found to be insufficient for protection of long approaches. Additional protection works like spurs, revetments etc. may then become necessary.

1833_Evaluate the Length of guide bund.png


Related Discussions:- Evaluate the length of guide bund

Dissimilarity in methods of compaction, Question Are there any dissimil...

Question Are there any dissimilarity in methods of compaction between clayey soil material and sandy material ? Answer The three key actions of compaction are static

Mr Kamal Saxena, What is WBM road. How it is constructed?

What is WBM road. How it is constructed?

Railway drawings, section of railway tracks in india ,all dimensions in met...

section of railway tracks in india ,all dimensions in meters

Heating season duration , Change the model to take into account the variati...

Change the model to take into account the variation in outdoor temperature for a "typical" day in the heating season based on the heat loss by the fabric and the heating of incomin

Rebound hammer.., rebound hammer working mechanism with detailed specificat...

rebound hammer working mechanism with detailed specifications of the images

Terminology of earthquake, TERMINOLOGY 1. Focus: The point on the fau...

TERMINOLOGY 1. Focus: The point on the fault where slip begins is the focus. It is also called as hypocentre 2. Epicentre: The point vertically above the focus on the su

Disparities between regular precast and pipe jacking, Question What are...

Question What are main disparities in design between regular precast concrete pipes and pipes used for pipe jacking ? Answer For pipes used for pipe jacking, they h

Construction Planning, A contractor has both a 3-cy and a 5-cy shovel in th...

A contractor has both a 3-cy and a 5-cy shovel in the equipment fleet. Select the minimum size shovel that will excavate 450,000 bcy of common earth in a minimum of 120 working day

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd