Evaluate the length of guide bund, Civil Engineering

Assignment Help:

Q. Evaluate the Length of guide bund?

For encouraging axial flow through the bridge, upstream length of guide bund may be kept 1.0 to 1.5 times the bridge length and downstream length 0.25 to 0.40 times the bridge length. Length necessary for keeping worst possible embayment behind the guide bund sufficiently away from the approach bank is also required to be ascertained by fitting of sharpest loop as indicated in Figure 5.2 in Chapter 5. If field data of acute bends in river when cut offs occurred is not available, It may be assumed that radius of such a bend can be equal to 0.4 times the radius of average bends if maximum river discharge is up to 5660 m3/s and equal to 0.5 times the radius of average bends if the maximum discharge is more than 5660 m3/s. In case of braided rivers, the length determined on basis of both the considerations of axial flow through bridge and keeping away the worst loop may be found to be insufficient for protection of long approaches. Additional protection works like spurs, revetments etc. may then become necessary.

1833_Evaluate the Length of guide bund.png


Related Discussions:- Evaluate the length of guide bund

Explain the difference in elevation between bm and tp2, Based on the inform...

Based on the information provided in Figure, the difference in elevation between BM and TP 2 is most nearly: Solution: Set up a Table as shown below and insert the kno

Back fill behind the abutments of bridges, Q. Back fill behind the abutment...

Q. Back fill behind the abutments of bridges? Dry Rubble - At the bank of all bridge abutments and wing walls, the space next to the masonry is to be filled in by a hand-pack

Shear lag in typical box-girder bridge, Shear lag in typical box-girder bri...

Shear lag in typical box-girder bridge For multiple-cell box girders, there are normally two arrangements. First one is that independent cells are connected by their top flang

Bond breaker for joint sealant, Joint sealant must be designed and construc...

Joint sealant must be designed and constructed to allow free extension and compression during the opening and closure of joints. In case joint sealants are attached to joint filler

Determine the uses of prestressed concrete poles, Determine the uses of Pre...

Determine the uses of Prestressed concrete poles Prestressed concrete poles are commonly mass produced and are used in most countries for power transmission, antenna masts etc

Determine the total stopping sight distance in feet, Determine the total St...

Determine the total Stopping Sight Distance in feet A motorist is travelling down a 6% grade at 65 mph and needs to stop because of a crash scene.  Assuming a 2.0 sec PRT and 1

Timber, defects in timber?

defects in timber?

What is partial prestressing, What is Partial Prestressing It is a form...

What is Partial Prestressing It is a form of prestressing in which tensile stresses are permitted, upto a limited extent, in concrete under working loads. As the permitted tens

Explain critical factor in design of shock transmission unit, Explain Criti...

Explain Critical factor in Design of shock transmission unit? (a) STUs are unidirectional devices for load transmission. If out of plane forces will be acting on the STU, the a

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd