Evaluate the length of guide bund, Civil Engineering

Assignment Help:

Q. Evaluate the Length of guide bund?

For encouraging axial flow through the bridge, upstream length of guide bund may be kept 1.0 to 1.5 times the bridge length and downstream length 0.25 to 0.40 times the bridge length. Length necessary for keeping worst possible embayment behind the guide bund sufficiently away from the approach bank is also required to be ascertained by fitting of sharpest loop as indicated in Figure 5.2 in Chapter 5. If field data of acute bends in river when cut offs occurred is not available, It may be assumed that radius of such a bend can be equal to 0.4 times the radius of average bends if maximum river discharge is up to 5660 m3/s and equal to 0.5 times the radius of average bends if the maximum discharge is more than 5660 m3/s. In case of braided rivers, the length determined on basis of both the considerations of axial flow through bridge and keeping away the worst loop may be found to be insufficient for protection of long approaches. Additional protection works like spurs, revetments etc. may then become necessary.

1833_Evaluate the Length of guide bund.png


Related Discussions:- Evaluate the length of guide bund

BRIDGES, WHAT ARE THE DIFFERENT TYPES OF BRIDGES

WHAT ARE THE DIFFERENT TYPES OF BRIDGES

Show the direction of gunning in shotcreting, Q. Show the Direction of gunn...

Q. Show the Direction of gunning in shotcreting? At the time of the construction of shotcrete, it is intended at gunning the full thickness in one single operation and this hel

Calculate the number of trucks for fleet working, A contractor was awarded ...

A contractor was awarded a Contract to excavate and haul 200,000-yds 3 of silty clay (USCS classification ML) with a bulking factor of 30%.  The contractor's fleet of dump trucks

Explain flocculation, Explain Flocculation Most important factor ef...

Explain Flocculation Most important factor effecting particle removal efficiency objective - to bring particles into contact so that they will collide, stick together

Calculate the invert elevation of the sewer pipe, 1. The center line elevat...

1. The center line elevation of the proposed roadway at station is 345+25.50 is 327.36-ft.   The existing ground top of cut elevation (ft) is most nearly: 2. A design engineer c

Assignment , A cantilever beam is loaded with a concentrated. Force of 5kN ...

A cantilever beam is loaded with a concentrated. Force of 5kN at the free end. The length of the cantilever beam is 1m having cross section of 50×50mm. determine the equation for b

Beam to column connection, what are the characteristics of the beam to colu...

what are the characteristics of the beam to column connection?

Determine the cubic yard in the ground, An earthwork contractor encountered...

An earthwork contractor encountered a location within the borrow area where the geological conditions changed.  Instead of encountering 100 cubic yards of wet clay, the contractor

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd