Already have an account? Get multiple benefits of using own account!
Login in your account..!
Remember me
Don't have an account? Create your account in less than a minutes,
Forgot password? how can I recover my password now!
Enter right registered email to receive password!
Q. Evaluate the Length of guide bund?
For encouraging axial flow through the bridge, upstream length of guide bund may be kept 1.0 to 1.5 times the bridge length and downstream length 0.25 to 0.40 times the bridge length. Length necessary for keeping worst possible embayment behind the guide bund sufficiently away from the approach bank is also required to be ascertained by fitting of sharpest loop as indicated in Figure 5.2 in Chapter 5. If field data of acute bends in river when cut offs occurred is not available, It may be assumed that radius of such a bend can be equal to 0.4 times the radius of average bends if maximum river discharge is up to 5660 m3/s and equal to 0.5 times the radius of average bends if the maximum discharge is more than 5660 m3/s. In case of braided rivers, the length determined on basis of both the considerations of axial flow through bridge and keeping away the worst loop may be found to be insufficient for protection of long approaches. Additional protection works like spurs, revetments etc. may then become necessary.
Write definition of the following - (i) Afflux. ( ii ) Free Board. ( iii ) Clearance. ( iv ) Via duct. ( v ) Skew Bridge ( vi ) Cause Way. ( vii ) Clear Span. ( v
Major bridge - Major bridge is one of which has a total linear waterway of 18 m or more for multiple span and total linear water way of 12 m or more for single span. Important b
Question Is it true that there is no essential to design nominal reinforcement to piles. Answer In BS8110 and BS5400 Pt.4, they need provision of nominal reinforce
how surface water can be controlled in road pavement
what is coursed rubble masonry
Q. What are the Parasitic forces for prestressing? In statically determinate structures, prestressing forces will cause the concrete structures to end upwards. Therefore precam
by estimation
A finish-to-finish activity is best described as: The "from" activity must finish before the "to" activity can finish The "from" activity must finish before the "to" acti
Q. Show the Overlays on concrete bridge deck? After years of servicing, some overlays can be applied on the top surface of bridges. Overlays on concrete bridge decks achieve th
chaining on level surface
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd