Construct the correct network for project, Civil Engineering

Assignment Help:

A project requires that activities A and B can be started independently and activities C and D are independent but can be started after A and B have been completed. Activity E can be started only when all activities A, B, C, and D have been completed. Construct the correct network for this project.

789_Construct the correct network for a project.png


Related Discussions:- Construct the correct network for project

Earth work in high embankments, Q. Earth work in high embankments? (a) ...

Q. Earth work in high embankments? (a) Borrow pits must not be dug close to telegraph poles, electric poles, level crossings, bridges a culverts, or within 800 meters of the bo

Determine the limit states of collapse, Determine the Limit States of Colla...

Determine the Limit States of Collapse Those limit states which point out the failure or collapse of a structure based on certain critical conditions are known as limit states

Utilisation of buoyancy effect, Q. Utilisation of Buoyancy Effect? Subm...

Q. Utilisation of Buoyancy Effect? Submerged part of the substructure will be subjected to buoyancy effect. The uplift pressure from the ground water can be utilised by constru

Surveying, what do you understand by the term local attraction

what do you understand by the term local attraction

Surveying, tracing paper method for solving three point problem?

tracing paper method for solving three point problem?

Distance between concrete columns in 5 story building, distance between con...

distance between concrete columns in 5 story building and if there is distance 15 feet than what should be the column size and how many bars and diameter of each bar ?

Road pavement, whatis difference between premix asphalt carpeting and aspha...

whatis difference between premix asphalt carpeting and asphalt concrete pavement

Explain the design discharge for bridge waterway, Q. Explain the Design dis...

Q. Explain the Design discharge for bridge waterway? Design discharge for bridge waterway should be a flood of 50 year frequency. For very large bridges damage to which is like

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd