Construct the correct network for project, Civil Engineering

Assignment Help:

A project requires that activities A and B can be started independently and activities C and D are independent but can be started after A and B have been completed. Activity E can be started only when all activities A, B, C, and D have been completed. Construct the correct network for this project.

789_Construct the correct network for a project.png


Related Discussions:- Construct the correct network for project

How to find back bearings?, Example: The following fore bearings were ...

Example: The following fore bearings were observed respectively for lines, AB, BC, CD, DE, EF and FG. Find out their back bearings: (i) 148°                          (ii

Bitumen, limitation in using with bitumen as watertight material

limitation in using with bitumen as watertight material

Non-distortional prestressing, Non-distortional Prestressing Concrete m...

Non-distortional Prestressing Concrete members deflect due to their own self weight. If prestressing force is applied in such a way that these deflections are eliminated due to

Earth work in high embankments, Q. Earth work in high embankments? (a) ...

Q. Earth work in high embankments? (a) Borrow pits must not be dug close to telegraph poles, electric poles, level crossings, bridges a culverts, or within 800 meters of the bo

What is ceramic mosaic and chequered cement tiles, Q. What is Ceramic mosai...

Q. What is Ceramic mosaic and Chequered Cement tiles? Chequered Mosaic tiles - Repairs to steps of F O Bs should be done only with Chequered Mosaic tiles. Ceramic m

Manhole covers finished of cast iron same as ductile iron, Question Why are...

Question Why are manhole covers finished of cast iron as same are through of ductile iron ? Answer Usually, manholes covers are made of cast iron. Though, in viewpoint of pipe

Loading and unloading cycles for soil nails, In carrying out pull-out tests...

In carrying out pull-out tests for soil nails, it generally requires the unloading and loading of soil nails of several cycles up to 80% of ultimate tensile strength of soil nails.

Calculate the number of trucks for fleet working, A contractor was awarded ...

A contractor was awarded a Contract to excavate and haul 200,000-yds 3 of silty clay (USCS classification ML) with a bulking factor of 30%.  The contractor's fleet of dump trucks

Closing and opening of expansion joints and contraction join, Question ...

Question In case of for unreinforced concrete carriageway, what will succession of closing and opening of expansion joints and contraction joints? Answer Take a case t

What is rapid sand filter, Q. What is Rapid Sand Filter? A Rapid Sand F...

Q. What is Rapid Sand Filter? A Rapid Sand Filter is a water treatment plant that includes provision for pre treating the water by coagulation and sedimentation for settlement

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd