Construct the correct network for project, Civil Engineering

Assignment Help:

A project requires that activities A and B can be started independently and activities C and D are independent but can be started after A and B have been completed. Activity E can be started only when all activities A, B, C, and D have been completed. Construct the correct network for this project.

789_Construct the correct network for a project.png


Related Discussions:- Construct the correct network for project

Energy dissipation at outlets - typical drainage outlet, Q. Energy dissipat...

Q. Energy dissipation at outlets - typical drainage outlet? Flow velocity at outlets is generally high. Without proper control of this energy, subsequent bank erosion can resu

Continuous flow systems, Continuous Flow Systems: Transport by road, r...

Continuous Flow Systems: Transport by road, rail, air or ships takes place in vehicles which move along a path at intervals. As against this, continuous flow systems are those

Estimate prestress losses, Given: beam deminsions: flange width=22" FL...

Given: beam deminsions: flange width=22" FLANGE THICKNESS=7" WEB WIDTH=7" SECTION HEIGHT=40" f'c=5000psi f'ci=3500psi fpu=270ksi Ap=eighteen 1/2" diam strands superim

Calculates the energy required, Write a program called, A1Q1, that reads a ...

Write a program called, A1Q1, that reads a single letter.   It will then display the corresponding ASCII code of the letter and prints the next character and the character which is

Advantages of using top-down approach, Question What are major advantag...

Question What are major advantages of using top-down approach in basement construction? Answer The main advantages of top-down approach are listed below- (i) Stru

Plane table surveing, in plane table surveying which activity is done first...

in plane table surveying which activity is done first whether centering or levelling?

Determine the settlement of the foundation, The thiclcness of the normally...

The thiclcness of the normally consolidated soft clay layer is 6 m. The natural water content is 31 percent. The specific gravity of the soil being 2.68 with a liquid limit of 4

Necessity of pile tip cover for rock-socketed H-piles, Q. Necessity of pile...

Q. Necessity of pile tip cover for rock-socketed H-piles? In current practice concrete cover is generally provided at the pile tips of pre-bored H-piles socketed in rock. The o

Shear stress, difference between bending stress and shear stress

difference between bending stress and shear stress

Sulphate-resisting cement not used in marine concrete, Question Explain...

Question Explain the reason why is sulphate-resisting cement not used in marine concrete ? Answer Major components of Portland cement are tricalcium silicate, dicalciu

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd