Construct the correct network for project, Civil Engineering

Assignment Help:

A project requires that activities A and B can be started independently and activities C and D are independent but can be started after A and B have been completed. Activity E can be started only when all activities A, B, C, and D have been completed. Construct the correct network for this project.

789_Construct the correct network for a project.png


Related Discussions:- Construct the correct network for project

Explain the terms void ratio, (a) Distinguish among Black cotton soil and L...

(a) Distinguish among Black cotton soil and Laterite from an engineering point of view. (b) Explain the terms 'Void ratio', 'Degree of saturation' and 'Water content', define th

Distomat, short note about characteristics of distomat

short note about characteristics of distomat

Calculate load distribution factor, Load Distribution Factor: The form...

Load Distribution Factor: The formula for deriving at the number of repetitions of the standard axle load during a design period of n years is: N =365 × A × VDF × F [(1 + r

Concrete cover to enhance fire resistance, Q. Concrete cover to enhance fir...

Q. Concrete cover to enhance fire resistance? In the event of exposing concrete structures to a fire, a temperature gradient is established across the cross section of concrete

Bitumen, limitation in using with bitumen as watertight material

limitation in using with bitumen as watertight material

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd