Construct the correct network for project, Civil Engineering

Assignment Help:

A project requires that activities A and B can be started independently and activities C and D are independent but can be started after A and B have been completed. Activity E can be started only when all activities A, B, C, and D have been completed. Construct the correct network for this project.

789_Construct the correct network for a project.png


Related Discussions:- Construct the correct network for project

Inspection and quality control certificate, Q. Inspection and Quality Contr...

Q. Inspection and Quality Control Certificate : A 'lot' under inspection should be accepted by the inspector when no defect is found in the acceptance level tests and so certif

Show the earth pressure on abutment, Q. Show the Earth pressure on abutment...

Q. Show the Earth pressure on abutment? The magnitude of earth pressure coefficient in calculating the earth pressure on bridge abutment reliesconsiderably on the degree of res

Unsealed contraction joints in concrete pavement, Unsealed contraction join...

Unsealed contraction joints in concrete pavement For unreinforced concrete pavement, contraction joint is an approximately 3mm wide groove with a depth of about one-third to o

Estimate prestress losses, Given: beam deminsions: flange width=22" FL...

Given: beam deminsions: flange width=22" FLANGE THICKNESS=7" WEB WIDTH=7" SECTION HEIGHT=40" f'c=5000psi f'ci=3500psi fpu=270ksi Ap=eighteen 1/2" diam strands superim

Meaning of driving succession of driven piles, Question What is meaning...

Question What is meaning of driving succession of driven piles? Answer In Basement construction, if piles are driven from centre to perimeter, there is a propensity o

Lintel, Ask question #classfication of lintel Minimum 100 words accepted#

Ask question #classfication of lintel Minimum 100 words accepted#

Determine the uses of full prestressing, Determine the uses of Full Prestre...

Determine the uses of Full Prestressing A prestressed concrete structural member is said to be fully prestressed if sufficient prestresses are introduced so that  tensile stres

Reasons for blockage in pumping concrete, Q. Reasons for blockage in pumpin...

Q. Reasons for blockage in pumping concrete ? Concrete pumping is normally adopted in highly elevated locations for which access for concrete trucks is difficult. Construction

Cement testing, explain the importance of following standard procedure

explain the importance of following standard procedure

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd