Construct the correct network for project, Civil Engineering

Assignment Help:

A project requires that activities A and B can be started independently and activities C and D are independent but can be started after A and B have been completed. Activity E can be started only when all activities A, B, C, and D have been completed. Construct the correct network for this project.

789_Construct the correct network for a project.png


Related Discussions:- Construct the correct network for project

State the net allowable bearing pressure, A footing, 2 m square, is founded...

A footing, 2 m square, is founded at a depth of 1.5 m in a sand deposit, for which the corrected value of N is 27. The water table is at a depth of 2 m from the surface. Verify the

Raking piles of bridge abutment placed under an embankment, Question It sho...

Question It should be necessary that raking piles of a bridge abutment be placed under an embankment ? Answer For a bridge abutment to be supported on raking piles with div

Factors that affect design facility of screw pumps, Question While sele...

Question While select screw pumps in polder scheme projects , what are factors that affect design facility of screw pumps? Answer Commonly used angles of inclination

Helical reinforcement designed instead of regular links, Question For colum...

Question For column reinforcements, why is helical reinforcement sometimes designed instead of regular links with reasons? Answer The utilization of links for column designi

Total maximum surface deflection of the pavement system, A stationary 40 kN...

A stationary 40 kN single axle load (applied on a circular contact area of radius = 152 mm = 6") is applied to each of the flexible pavement structures indicated below. Assuming li

How to design shape of guide bunds, Q. How to design Shape of guide bunds? ...

Q. How to design Shape of guide bunds? Alignment of guide bunds converging on the upstream was considered by Bell, Spring and Gales to allow for the waterway obstructed by pier

Survey, who to we calculate the RL at first point.

who to we calculate the RL at first point.

Co, compressive stenght assigments.

compressive stenght assigments.

Inadequate pile founding level, Reasons of common occurrence of "inadequate...

Reasons of common occurrence of "inadequate pile founding level" in piles of piers The most severe load on piers usually is the horizontal load owing to berthing and mooring o

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd