Construct the correct network for project, Civil Engineering

Assignment Help:

A project requires that activities A and B can be started independently and activities C and D are independent but can be started after A and B have been completed. Activity E can be started only when all activities A, B, C, and D have been completed. Construct the correct network for this project.

789_Construct the correct network for a project.png


Related Discussions:- Construct the correct network for project

#titl, Two readings ie 1.64m and 0.73m were taken during leveling procedure...

Two readings ie 1.64m and 0.73m were taken during leveling procedure to define the slope of a centerline of a bridge at points A and B. If distance AB=50 m, find the slope of line

How can designer cater for stability of minor slips, Question Soil nail...

Question Soil nails are mostly designed for stabilization of key slips . How can designer cater for stability of minor slips? Answer There are many methods to treat mi

Edge piles take up more loads than central piles, Edge piles take up more l...

Edge piles take up more loads than central piles in rigid cap Because of the effect of interaction of individual piles, central piles tend to settle more than the edge piles w

Calculate the initial height of the stockpile, On a 5-acre level terrain bu...

On a 5-acre level terrain building site, an earthwork contractor has instructed her crew to strip and grub the topsoil of a 60,000-ft 2 proposed building pad to a minus 2-ft sub-g

Building classification, Why I is the missing after h and J is written in t...

Why I is the missing after h and J is written in the classification of building

Define overloading - deterioration in steel, Define Overloading - Deteriora...

Define Overloading - Deterioration in Steel? Steel structural elements are sensitive to impact damage from moving vessels and other types of accidental overloading. Impact or c

Explain the well drawdown equations - ground water, Explain the Well Drawdo...

Explain the Well Drawdown Equations Watch the units, especially if you use log 10 or ln.    h 1 = aquifer thickness minus the drawdown (ft)  r 1 = distance from well (ft

Strength of materials, #questionwhat is the shear force and bending moment....

#questionwhat is the shear force and bending moment..

Effect of concrete placing temperature, Effect of concrete placing temperat...

Effect of concrete placing temperature on early thermal movement Rate of hydration of cement paste is related to placing temperature of concrete. Rate of heat production is giv

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd