Estimate the net present worth - construction management, Civil Engineering

Assignment Help:

Three alternatives are being considered for improving a street intersection.The annual dollar savings on account of the improvement is shown below.  Assume that the intersection will last for 25 years and the interest rate is 5%.  Each of the three improvements is mutually exclusive but provides similar benefits. The alternative that is the most economical is: 

Alternative                         Total cost         Annual Benefit

A                                       $10,000           $  800

B                                       $12,000           1,000

C                                       $19,000           1,400

Solution:

Estimate the Net Present Worth (NPW) for each alternative and identify the most economical alternative for construction. 

Net Present Worth (NPW) = PW of benefits - PW of costs

Use the present worth factor for uniform series: 

  (P/A, i =5%, 25 yrs) = 14.094 (from the Factor Tables)

  NPW(A)  = ($800 x 14.094) - $10,000     = $1,275.20

  NPW(B)  = ($1000 x 14.094) - $12,000   = $2,094.00   

  NPW(C)  = ($1400 x 14.094) - $19,000   =   $731.60

Therefore, select Alternate B because it has the highest net present worth.


Related Discussions:- Estimate the net present worth - construction management

Strenght of meterials 2, Difference between direct and bending stress diagr...

Difference between direct and bending stress diagrams

Theory on the horizontal reactions of portal frames, Determine the horizont...

Determine the horizontal abutment reaction of a rectangular portal frame under increasing central concentrated load

Surveying, what are tie lines? explain in detail

what are tie lines? explain in detail

Calculate the amount of import or export, Calculate the Amount of Import or...

Calculate the Amount of Import or Export For the project site shown in Figure, the amount of import or export to bring the entire site to elevation 90-ft is most nearly:

Surveying, What is the least count of prismatic and surveyor compass

What is the least count of prismatic and surveyor compass

Acsr aluminium conductor steel reinforced are utilized as , Q. ACSR (Alumi...

Q. ACSR (Aluminium Conductor Steel Reinforced) are utilized as (A) over head transmission lines.            (B) super conductors. (C) fuse

Is codes for building design, IS CODES FOR BUILDING DESIGN The codes w...

IS CODES FOR BUILDING DESIGN The codes which help engineers to design buildings are following: 1. IS 456-2000. For the design of plain and reinforced concrete it is code

Define the arrow diagramming method, Define the Arrow Diagramming Method ...

Define the Arrow Diagramming Method Activity-on-Arrow (Branch) with nodes as dependencies Uses finish-to-start precedence only. The solution method for an activity on

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd