Estimate the net present worth - construction management, Civil Engineering

Assignment Help:

Three alternatives are being considered for improving a street intersection.The annual dollar savings on account of the improvement is shown below.  Assume that the intersection will last for 25 years and the interest rate is 5%.  Each of the three improvements is mutually exclusive but provides similar benefits. The alternative that is the most economical is: 

Alternative                         Total cost         Annual Benefit

A                                       $10,000           $  800

B                                       $12,000           1,000

C                                       $19,000           1,400

Solution:

Estimate the Net Present Worth (NPW) for each alternative and identify the most economical alternative for construction. 

Net Present Worth (NPW) = PW of benefits - PW of costs

Use the present worth factor for uniform series: 

  (P/A, i =5%, 25 yrs) = 14.094 (from the Factor Tables)

  NPW(A)  = ($800 x 14.094) - $10,000     = $1,275.20

  NPW(B)  = ($1000 x 14.094) - $12,000   = $2,094.00   

  NPW(C)  = ($1400 x 14.094) - $19,000   =   $731.60

Therefore, select Alternate B because it has the highest net present worth.


Related Discussions:- Estimate the net present worth - construction management

Deflection, solving problems with their answer

solving problems with their answer

Univariate normal distribution, Univariate normal distribution: Let X ...

Univariate normal distribution: Let X = (X I , X 2 , ..., X n ,) has the multivariate normal distribution (5.26) of Section 5.4. Show that Y = a X ' follows a univariate norma

Mechanism of formation of soil plugs, Question What is main mechanism o...

Question What is main mechanism of formation of soil plugs in marine driven steel piles with reinforced concrete infill? Answer Throughout initial driving process, ope

Water-bound macadam road construction for unpaved roads, how can I come up ...

how can I come up with the research on the water bound macadam road construction

Hydraulics and Hydrology , A flow rate of 200 gpm of oil with u=1.5 x 10-3 ...

A flow rate of 200 gpm of oil with u=1.5 x 10-3 lb-sec/ft2 and p=1.7 slug/ft3 occurs in a 4-in pipe. Determine the Reynolds number. Classify the flow as laminar or turbulent. What

Earth dam, earth dam design and its force

earth dam design and its force

Estimate the activity durations - construction management, Estimate the Act...

Estimate the Activity Durations The total labor cost for emergency bridge rehabilitation on an interstate highway is $5,716,440.  The average crew-hour cost is $15,879 for this

Application of levelling, how do I draw sections(longitudinal and cross sec...

how do I draw sections(longitudinal and cross sections)?

Define construction damage - underwater inspection of bridge, Define Constr...

Define Construction damage - underwater inspection of bridge? Construction damage can result from improper procedures during the construction phase.  Some examples are: -  P

Trigo, a pilot entering a bay on course

a pilot entering a bay on course

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd