Corrosion of steel reinforcement inside a concrete structure is undesirable in the subsequent ways:
(i) Presence of rust impairs the bond strength of deformed reinforcement since corrosion takes place at the raised ribs and fills the gap between ribs so evening out the original deformed shape. Basically the bond between concrete and deformed bars originates from the mechanical lock between raised ribs and concrete. Reduction of mechanical locks by corrosion results in the decline in bond strength with concrete.
(ii) Presence of corrosion decreases the effective cross sectional area of steel reinforcement. Therefore the available tensile capacity of steel reinforcement is reduced by a considerable reduction in the cross sectional area.
(iii) Corrosion products occupy about 3 times the original volume of steel from that it is formed. Such radical increase in volume generates significant bursting forces in vicinity of steel reinforcement. Subsequently cracks are formed along steel reinforcement when tensile strength of concrete is exceeded.
Demonstrate the Design of Prestressed concrete poles Prestressed concrete poles are generally designed as members with uniform prestress since they are subjected to bending mo
Cross-sectional area of flow (ft 2 ) (A) For rectangular channels = (w)(d). For trapezoidal channels, divide the flow area into two side triangles and one center rectangle, so
Q- What are loads and forces taken into account for designing a pile and what is load carrying capacity of a pile. Ans. For designing a pile the following loads and force ar
Addition of water to bored piles In water bearing ground, some water head (about 1 m) above the existing ground water table is sustained to stabilize the bore at the time of e
Q. Explain about Overhauling of Level xing? Each level crossing except those laid with PSC sleepers must be opened out and the condition of sleepers and fittings, rails and fas
for calculating the bending moment in which the loading and the length of continuous beam is taken from the user
Solved examples on linear programming partB
after formation of the soil under raft some area around the lift pit for example will be on tipping shape and some column placed in the same area the question how we place the col
Q. Settlement due to Lowering of Water Table? Water table is encountered with, whenever any excavations are made for foundations. The water is to be out for working conditions.
How to convert uniformly varying load to point load
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd