Economic Order Quantity:

Assume an economic order quantity case where annual demand D = 500 units, economic order quantity Q = 100 units, the wanted probability of not stocking out P = 0.95, the standard deviation of demand during lead time σ L = 20 units, and Lead time L = 12 days. Discover the reorder point. Suppose that demand is over a 250 = workday year.

Solution

d' in above example is

 d = 500 /250 = 2   and lead time is 12 days.

 From the equation,

R = d'L + z σL  = 2 (12) + z (20)

Since, in this case z is 1.64. Substituting this value of z, we achieved

R = 2 (12) + 1.64 (20) = 24 + 32.8 = 56.8 units

This illustrated that when the stock on hand gets down to 56 units, order 100 more.


Related Discussions:- Economic order quantity

Mr, how is the theory of kinematics applied to secondary machining

how is the theory of kinematics applied to secondary machining

Hot working of metals, advantages and disadvantages of hot working of metal...

advantages and disadvantages of hot working of metals

What is the initial velocity of the ball, What is the initial velocity of t...

What is the initial velocity of the ball: A ball is horizontally thrown from the top of a building 60 m height, hits the horizontal ground 25 m from the base of the building a

Spot welding of different metals-stainless steel, Spot welding of different...

Spot welding of different metals-Stainless steel Stainless steel is having lower thermal conductivity compared to mild steel. Therefore, it requires less heat input. But, stain

First law for closed system undergoing cycle, First Law for closed system u...

First Law for closed system undergoing cycle: In accordance to first law, when a closed system undergoes thermodynamic cycle, the net heat transfer is equal to network transfe

Kinematic equations, A projectile is fired with a velocity u at the entranc...

A projectile is fired with a velocity u at the entrance A of a horizontal tunnel of length L and height H. Determine the minimum value of u and the corresponding angle \theta for w

Continuous and salt bath furnaces, Continuous Furnace: Parts to be tr...

Continuous Furnace: Parts to be treated are situated on several sort of conveyor that move into the furnaces as per to programmed heating cooling cycle. The time for unloadin

Materials requirements planning, Materials requirements planning: Mate...

Materials requirements planning: Materials requirements planning (MRP) is a set of process for converting forecasted demand for a manufactured product into a requirement sched

Torque equilibrium equation , Problem A cat walks along a uniform plan...

Problem A cat walks along a uniform plank that is 5.00 m long and has a mass of 9.00 kg.  The plank is supported by two sawhorses, one 0.500 m from the left end of the board a

Vacuum pressure and absolute pressure - thermodynamics, V acuu m (Or V...

V acuu m (Or Vacuum pressure) (P vacc ): It is pressure of fluid, which is always less than atmospheric pressure. Pressure in a steam condenser is one such examp

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd