Briefly explain the difference between compaction and consolidation of soil. What is the effect of compaction on soil properties?
Ans.- Compaction -
The process of increasing the dry density of soil by artificial methods and packing the soil particles together into a dense mass to sustain a dynamic load, is termed as compaction.
Consolidation -
A gradual expulsion of water from the pores of a saturated clay by a continuous pressure due to the load of the structure takes place and thus the volume of soil mass decreases. On the other hand, compaction is a quick process for reducing the volume of soil mass by applying dynamic loads.
Effect of compaction on soil properties -
Compaction is resorted to get the following main effect on soil properties -
i. To increase the density as well as bearing capacity of soil.
ii. To increase the shearing strength of the soil.
iii. To decrease the changes of settlement under repeated loads and also to retard the permeability of soil.
This assessment will test Learning Outcomes 3 and 4 as well as the component of Learning Outcome 1 as it refers to waste disposal for the Plumbing Technology. The student is expect
Explain what is Stationing - Transportation 1) Stationing concept is used along horizontal alignments for referencing purpose 2) 1 station = 100 feet 3) How do you repres
Explain the Strength Design (LRFD) 1. γ Factors are applied to loads and φ factors applied to resistance. 2. Unfactored service loads receive a load factor γ > 1.0
Explain the Limitations of Rebound Hammer? The following characteristics of concrete can affect the correlation of the rebound number with the actual surface hardness and shoul
what is barometric leveling
mechanical monometer
Defnition of obstruction
Question What are thought in determining whether casings have to be left in for mini-piles ? Answer Contrary to most of pile design, design of min-piles is controlled
natural phenomenon affecting the designs of harbours
The local survey crew measures a distance of 1,135 ft of new drainage pipe that is required for the new road construction. The beginning point for the drainage is located at statio
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd