Difference between compaction and consolidation of soil, Civil Engineering

Assignment Help:

Briefly explain the difference between compaction and consolidation of soil. What is the effect of compaction on soil properties?

Ans.- Compaction -

The process of increasing the dry density of soil by artificial methods and packing the soil particles together into a dense mass to sustain a dynamic load, is termed as compaction.

Consolidation -

A gradual expulsion of water from the pores of a saturated clay by a continuous pressure due to the load of the structure takes place and thus the volume of soil mass decreases. On the other hand, compaction is a quick process for reducing the volume of soil mass by applying dynamic loads.

Effect of compaction on soil properties -

Compaction is resorted to get the following main effect on soil properties -

i. To increase the density as well as bearing capacity of soil.

ii. To increase the shearing strength of the soil.

iii. To decrease the changes of settlement under repeated loads and also to retard the permeability of soil.


Related Discussions:- Difference between compaction and consolidation of soil

Test leakage of constructed gravity pipelines, Question Have air test o...

Question Have air test or water tests be selected to test leakage of constructed gravity pipelines ? Answer For gravity pipes, air tests are carried out after completi

Calculate the square foot of contact area for the formwork, A concrete crew...

A concrete crew will use the available steel form panels measuring 2'-6" wide x 4'-0" high to construct a 40'-6" long by 3'-2" high by 1'-6" wide concrete knee wall. The square

coursework (commercial management), Ask que1. Identify the risks involved ...

Ask que1. Identify the risks involved in this project related to cost in the perspective of the customer and analyse the probability of acceptance of such a project by customers. 2

Mr Kamal Saxena, What is WBM road. How it is constructed?

What is WBM road. How it is constructed?

Calculate the initial height of the stockpile, On a 5-acre level terrain bu...

On a 5-acre level terrain building site, an earthwork contractor has instructed her crew to strip and grub the topsoil of a 60,000-ft 2 proposed building pad to a minus 2-ft sub-g

Non uniform flow in open channe, A rectangular channel is 3 m in width and ...

A rectangular channel is 3 m in width and draws water from a lake. The channel slope is 0.001 and the Manning’s n is 0.0013. What will be the discharge in the channel when the lake

Paint system to protect steelwork from corrosion, Q. Paint system to protec...

Q. Paint system to protect steelwork from corrosion? In a typical painting system, there are generally three main layers primer, undercoat and finishing coat. Primer acts as th

Timber, What is exogenous tree?

What is exogenous tree?

How the water table is lowered, The water table is lowered from a depth of ...

The water table is lowered from a depth of 3 m to a depth of 6 m in a deposit of silt. The silt remains saturated even after the water table is lowered. What would be the enhance i

Traverse, how to fill traverse computation sheet of opened traversig ..

how to fill traverse computation sheet of opened traversig ..

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd