What is activated sludge process, Civil Engineering

Assignment Help:

Q. What is Activated Sludge process?

The term Activated Sludge is used to indicate the sludge which is obtained by settling sewage in presence of abundant oxygen. The Activated Sludge is biologically active and it contains a large number of aerobic bacteria and other micro organisms which have got an unusual property to oxidise organic matter.

Activated Sludge is mixed with raw or partially treated sewage. When Activated Sludge is mixed properly with sewage containing ample or sufficient quantity of oxygen, micro organisms present in Activated Sludge multiply rapidly as result of this.

a) Organic solids present in sewage are rapidly oxidised.

b) Suspended and colloidal matters coagulate and they from a readily settleable precipitate.

After such precipitate settles down the effluent which is obtained is clear and sparking. The effluent contains very low amount of organic matter. A portion of settled sludge is sent for recirculation and the remaining part is sent to sludge digestion tanks. The digested sludge is harmless.


Related Discussions:- What is activated sludge process

Dynamics, A vehicle for landing on the moon has a mass of 4500kg. The dampe...

A vehicle for landing on the moon has a mass of 4500kg. The damped spring undercarriage system of the vehicle has a stiffness of 450kn/m and a damping ratio of 0.2. The rocket lift

Construction mesurment, Measurement quantity of excavation, concrete, formw...

Measurement quantity of excavation, concrete, formwork as my assignment brief.

Movement accommodation factor for joint sealant, Movement accommodation fac...

Movement accommodation factor is normally specified by manufacturers of joint sealants for designers to design dimension of joints. It is stated as the total movement that a joint

Explain template jig, Explain Template Jig? 1) Template jig is the simp...

Explain Template Jig? 1) Template jig is the simplest type of jig, employed for accuracy than speed. 2) This jig fits over, on, or, into the work and is not generally clampe

Estimation of loading carrying capacity, Question While designing mini...

Question While designing mini-piles , should strength of grout be disused during estimation of loading carrying capacity? Answer While designing min-piles, there will

Sieve analysis - soil mechanics and foundations, Sieve Analysis - Soil Mech...

Sieve Analysis - Soil Mechanics and Foundations a. Sieve Analysis used to obtain the grain size distribution of coarse-grained soils (sands and gravels) larger than 0.075 mm (r

Static, Determine the moment of inertia with respect to the x axis for the ...

Determine the moment of inertia with respect to the x axis for the shaded area shown (Figure 2) . The dimension is a = 2.00m .

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd