Determine the total head and total pressure of water, Civil Engineering

Assignment Help:

Determine the total head and total pressure of water flowing at  in a pipe which has the following data:

Flow= 2,500 gpm; Elevation = 30 ft; Pressure = 40 psi; Pipe Diameter = 12 inch; velocity = 7 ft/sec; ??water = 62.4 lb/ft3.  

Solutions: Ep = (40 psi)(2.31 ft/psi) = 92.4 ƒt

Ev = (V2/2g ):= (7)2 / (2)(32.2) = 0.76 ƒt

Ez = 30 ƒt

H = Total Head = Ep + Ev + Ez = 92.4 ƒt + 0.76 ƒt + 30 ƒt = 123.2 ƒt

P = Total Pressure = γH = (62.4 lb / ƒt3)(123.2 ƒt) = 7,688 lb/ ƒt2 = 53.3 psi


Related Discussions:- Determine the total head and total pressure of water

Surveying, WCB from included angle

WCB from included angle

Back fill behind the abutments of bridges, Q. Back fill behind the abutment...

Q. Back fill behind the abutments of bridges? Dry Rubble - At the bank of all bridge abutments and wing walls, the space next to the masonry is to be filled in by a hand-pack

Determine the strain compatibility method, Determine the Strain Compatibili...

Determine the Strain Compatibility method For estimating the ultimate strength of prestressed concrete members in flexure, 'Strain Compatibility method' may be used. For calcul

Calculate the diameter of the stockpile, 1. On a 5-acre level terrain build...

1. On a 5-acre level terrain building site, an earthwork contractor has instructed her crew to strip and grub the topsoil of a 60,000-ft 2 proposed building pad to a minus 2-ft su

What is contact pressure, What is 'contact pressure'? How does it depend on...

What is 'contact pressure'? How does it depend on the type of structure and type of soil? What is 'active zone' in soil? Define it with reference to the pressure bulb concept.

Calculate surface loading rate for each clarifier, A wastewater plant is op...

A wastewater plant is operating at 10MGD with a suspended solids concentration of 200mg/L. It has 6 clarifiers operating in parallel. Each clarifier is 40 foot in diameter and 10 f

Estimating movement for movement joints, Question Should reversible moi...

Question Should reversible moisture movement be taken into account in estimating movement for movement joints ? Answer Size of concrete is affected by changes in dist

Water-bound macadam road construction for unpaved roads, how can I come up ...

how can I come up with the research on the water bound macadam road construction

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd