Estimating movement for movement joints, Civil Engineering

Assignment Help:

Question

Should reversible moisture movement be taken into account in estimating movement for movement joints?


Answer

Size of concrete is affected by changes in distinctive humidity- moisture reasons growth although drying causes shrinkage. Such humidity movement is reversible. This is entirely different from aeration shrinkage in which concrete slowly loses humidity during hardening, thus causing irreparable reduction.

In fact, variation of humidity and estimated reversible moisture movement is not significant (about 30 percent) and so, its contribution to group does not validate for group joints .

 


Related Discussions:- Estimating movement for movement joints

What is contact pressure, What is 'contact pressure'? How does it depend on...

What is 'contact pressure'? How does it depend on the type of structure and type of soil? What is 'active zone' in soil? Define it with reference to the pressure bulb concept.

Estimation specification and costing, Estimate the single room of size 3m x...

Estimate the single room of size 3m x 4m x height 3m using individual wall method?

Explain the spiral curves - transportation, Explain the Spiral Curves - Tra...

Explain the Spiral Curves - Transportation A spiral is a curve of continuously changing radius. It varies from 0 degree of curvature (infinite radius) at its TS (Tangent to Spi

State about the pre-tensioned concrete beam, State about the pre-tensioned ...

State about the pre-tensioned concrete beam A pre-tensioned concrete beam, 200 mm wide and 300 mm deep, is prestressed by straight wires carrying an initial force of 150 kN at

Remedial measures for problems in turbid water - reflection, Remedial measu...

Remedial measures for Problems in Turbid Water - Reflection? The problem of reflection can be minimised by carefully placing the flash away from the axis of the camera and at a

Explain detention or retention ponds - hydrology, Explain Detention or Rete...

Explain Detention or Retention Ponds Detention/Retention Ponds: Designed to reduce and contain the peak runoff from developed areas (more impervious). Attempt to limit the runo

Cost-volume relationship, Cost-volume relationship: Cost-volume relati...

Cost-volume relationship: Cost-volume relationship is illustrated through a simple example dealing with the cost of operating an automobile. To perform the analysis following

Arches, construction of arches

construction of arches

Graphics, 1. Draw the projections of a line AB that is 50 mm long and is pa...

1. Draw the projections of a line AB that is 50 mm long and is parallel to both the HP and the VP. The line is 40 mm above the HP and 25 mm in front of the VP. 2. A line AB, 50 mm

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd