Determine the station number - transportation, Civil Engineering

Assignment Help:

The local survey crew measures a distance of 1,135 ft of new drainage pipe that is required for the new road construction. The beginning point for the drainage is located at station 8+77. What is the station number of the ending point?


Related Discussions:- Determine the station number - transportation

Define Carbonate hardness (ch) - water softening, Carbonate Hardness (CH) -...

Carbonate Hardness (CH) - Water Softening Ca +2 , Mg +2 combining with alkalinity (OH - , CO 3 -2 , HCO 3 - ). If alkalinity is present in water the CH wil

Important parts of road pavements, Important parts of road pavements: ...

Important parts of road pavements: Prime Coat : Application of a low viscosity bituminous binder over a granular base to fill up the voids. Tack Coat : Application of b

Cutbacks and emulsions, Cutbacks And Emulsions: Cutbacks A cu...

Cutbacks And Emulsions: Cutbacks A cutback is a bitumen whose viscosity has been reduced by adding a diluent such as naphtha or kerosene. The use of cut-back is not f

Aluminium sliding window detail drawings, what are the details of aluminium...

what are the details of aluminium sections and how are they connected for making a door or window

Main advantages of using rubber dams, Question In assortment of dams in...

Question In assortment of dams in drainage channels, what are the main advantages of using rubber dams instead of steel-gate dams ? Answer Key Advantages of rubber d

Wmm, what is material of wmm plant

what is material of wmm plant

Surveying, how to solve the problems of cross sectional surveying and profi...

how to solve the problems of cross sectional surveying and profil questions

Explain subcritical flow and supercritical flow, Explain Subcritical flow a...

Explain Subcritical flow and Supercritical flow Subcritical flow: The depth of flow is greater than critical depth and the velocity of the fluid is slow. Also termed "tranquil"

Total volume of soil that excavated from the borrow area, Project specifica...

Project specifications require a relative compaction of 95% (modified Proctor).  Construction of a highway embankment requires 10,000-yd 3 of fill.  The borrow soil has an in-situ

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd