Determine the expected extension at the jack, Civil Engineering

Assignment Help:

A cylindrical concrete tank, 30 m external diameter, is to be prestressed circumferentially by means of  high-strength steel wire (E, = 2 x  105  N/mm2)  jacked  at 4 points, 900 apart. If  the minimum stress  in the wire immediately after tensioning is to be 450 N/mm2  and coefficient of friction is 0.5, calculate :

(a) The maximum stress to be applied to the wires at the  jack, and

(b) The expected extension at  the jack.

 


Related Discussions:- Determine the expected extension at the jack

High Sulfate Soils, How do you treat High Sulfate soils, Gypsum? Is it good...

How do you treat High Sulfate soils, Gypsum? Is it good practice to build on it?

Equipments required for under water inspection of bridge, Define Equipments...

Define Equipments and tools required for under water Inspection of Bridge? Since the underwater inspection of stone masonry substructures involve only a cursory inspection of t

Define the alternate depths - hydrologic system, Define the Alternate Depth...

Define the Alternate Depths In open channels, two alternate depths of flow have the same energy for the same flow rate. As shown in the figure, the hyperbolic plot of energy (x

Water quality analysis, Water quality analysis: This water quality ana...

Water quality analysis: This water quality analysis presents an overview of physical characteristics of water, chemical substances that are normally present in water and vario

Grillage foundation, what are the advantages of grillage foundation and why...

what are the advantages of grillage foundation and why people prefers that?

Determine the allowable bearing pressure of the sand, Two load tests were c...

Two load tests were conducted at a site-one with a 0.5 m square test plate and the other with a 1.0 m square test plate. For a settlement of 25 mm, the loads were found to be 60 kN

CBR of soil, Why IRC 37-2012 has taken 90th percentile for pavement design ...

Why IRC 37-2012 has taken 90th percentile for pavement design of expressway or NH while they hav taken 80th percentile for state highway design ????????

Geodesy, what is the difference between geodesy and plane survey

what is the difference between geodesy and plane survey

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd