Determine the expected extension at the jack, Civil Engineering

Assignment Help:

A cylindrical concrete tank, 30 m external diameter, is to be prestressed circumferentially by means of  high-strength steel wire (E, = 2 x  105  N/mm2)  jacked  at 4 points, 900 apart. If  the minimum stress  in the wire immediately after tensioning is to be 450 N/mm2  and coefficient of friction is 0.5, calculate :

(a) The maximum stress to be applied to the wires at the  jack, and

(b) The expected extension at  the jack.

 


Related Discussions:- Determine the expected extension at the jack

3 wire leveling, can you give me some examples and problems in 3-wire level...

can you give me some examples and problems in 3-wire leveling?

Methods of contouring by grid points, the elevations of grid points for an ...

the elevations of grid points for an area as follows: 1 2 3 4 5 6 7 8 F 690 709 726 732 735 740 743 747 E 696 715 729 736 740 737 739 740 D 702 723 733 742 737 737 745 747 C 707 72

Define seismic isolation bearings - bridge bearing, Define Seismic Isolati...

Define Seismic Isolation Bearings  - Bridge Bearing? Many bridges had been built before the proper seismic design specifications were known to us. These bridges require strengt

Depth of boring for multi-storeyed building, Depth of Boring  for Multi-st...

Depth of Boring  for Multi-storeyed Building Peck has recommended that first drill hole is to be made up to depth at which the presence of a thick layer of soft clay with a hig

Beneficial points of sliding bearings over roller bearings, What are key be...

What are key beneficial points of sliding bearings over roller bearings ? In roller bearing for a given movement a roller bearing exhibit modify in pressure centre from its un

Estimate the jam density in one lane of trucks, At a large port facility ne...

At a large port facility near New York City tractor-trailer trucks are lined-up in long queues as their drivers wait to have their containers inspected and documents processed.  As

.Chemestry, How desalination of water can be acheived by reverse osmosis an...

How desalination of water can be acheived by reverse osmosis and electrodialysis process?

Importance of racking load for a pre-stressed concrete beam, Importance of ...

Importance of racking load for a pre-stressed concrete beam Evaluation of cracking load for a pre-stressed concrete beam member is important for the following cases/reasons.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd