Important items during level crossing inspection, Civil Engineering

Assignment Help:

Q.7.- Write the important items to be inspected during level Crossing inspection. How do you take census of traffic at level crossing.

Ans.-Important items to be inspected during level Crossing inspection -

i. Examination of Gate equipment and Gateman in Rules.

ii. Obstruction of view.

iii. Condition of sleepers and fittings, rails and fastenings inspected at least once a year or more frequently.

iv. The painting of gates and discs.

v. Whistle boards and 'STOP' boards provided on the approaches to level crossings.

vi. The Assistant Engineer should inspect the equipment at every manned level crossing on the sub-division every six months, and examine the Gateman in rules during his inspection.

vii. The Assistant Engineer should scrutinise the manuscript register of level crossing maintained by the Permanent Way Inspectors and inspect as many level crossings as possible, when they are completely opened out during the year.

viii. Visibility Requirements for unmanned Level Crossings.

ix. Provision of speed breakers on the approaches of level crossing.

x. Appointment of Gatemen , Rosters and Medical fitness Certificates.-

xi. Gate Lamps and Blinders.


Related Discussions:- Important items during level crossing inspection

Waterway, What is linear waterway?

What is linear waterway?

Describe the boussinesq theory, A raft of size 4 m-square carries a load of...

A raft of size 4 m-square carries a load of 200 kN/m 2 . Verify the vertical stress increment at a point 4 m below the centre of the loaded area using Boussinesq's theory. Compare

Aggregaters, What Aggregate''s class III

What Aggregate''s class III

Explain damage inspections - underwater inspection of bridge, Explain the D...

Explain the Damage inspections - underwater inspection of bridge? Sometimes referred to as post-event inspections, damage inspections are typically unscheduled inspections aime

Plane table surveing, in plane table surveying which activity is done first...

in plane table surveying which activity is done first whether centering or levelling?

Laplace transform, Using Laplace transfom, the following differential equat...

Using Laplace transfom, the following differential equation d y dy dt reduces to the algebraic equation of the form Resolve y(s) into partial fractions

Features of a stratigraphical survey phase, Features of a Stratigraphical S...

Features of a Stratigraphical Survey phase The principal features of a Stratigraphical Survey phase are: a)  Determination of depth of ground water, thickness, extent and ap

Harbours, natural phenomenon affecting the designs of harbours

natural phenomenon affecting the designs of harbours

Explain the bearing capacity failure, A continuous wall footing, 1 m wide,...

A continuous wall footing, 1 m wide, rests on sand, the water table lying at a great depth. The corrected N-value for the sand is 10. Verify the load which the footing can support

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd