Determine the condition of each activity in the network flow diagram shown below

 

898_Determine the condition of each activity in the network flow diagram.png

Ans:

a. Activity C can be started only after the completion of activities A and B

b. Activity D can be started only activity B is completed

c. Activity E can be started only when activities A, B, C and D have been completed

 


Related Discussions:- Determine condition of activity in the network flow diagram

Unsymmetrical bending, An 8 kN.m moment is applied at the end of a block fi...

An 8 kN.m moment is applied at the end of a block fixed into the ground as illustrated in thefigure below. The moment vector (double arrow head representation) acts in line with th

One layered spatial structures, Classification of the damage according to t...

Classification of the damage according to the type of structures The level of damage in spatial trusses has also been classified into three different levels based on th

Concrete, what is the allwoable combined aggregates Fineness Modulus

what is the allwoable combined aggregates Fineness Modulus

Dam, tupes of dam

tupes of dam

Vectors application, how does vectors apply mathamatical in civil engineeri...

how does vectors apply mathamatical in civil engineering

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd