Determine condition of activity in the network flow diagram, Civil Engineering

Assignment Help:

Determine the condition of each activity in the network flow diagram shown below

 

898_Determine the condition of each activity in the network flow diagram.png

Ans:

a. Activity C can be started only after the completion of activities A and B

b. Activity D can be started only activity B is completed

c. Activity E can be started only when activities A, B, C and D have been completed

 


Related Discussions:- Determine condition of activity in the network flow diagram

Road maintenance, find the details of road maintenance in our project work

find the details of road maintenance in our project work

Dimples in polytetrafluoroethylene, Dimples in Polytetrafluoroethylene (PTF...

Dimples in Polytetrafluoroethylene (PTFE) PTFE is a fluorocarbon polymer that possesses good chemical resistance and can function in a wide range of temperature. The most signi

HJJJJKKK, #questiRJTIEJITIUDUAIIGIIYHU7S7URURE78ITIT8Y88R6ET8Y86U895R7YRGLH...

#questiRJTIEJITIUDUAIIGIIYHU7S7URURE78ITIT8Y88R6ET8Y86U895R7YRGLHKGJFn..

Transition curves - geometric design of roads, Transition Curves: If ...

Transition Curves: If a vehicle travelling on a straight enters a horizontal curve abruptly, it will cause shock and sway. To avoid this, it is customary to provide a transit

What are the various impurities in water, Q. What are the various impuritie...

Q. What are the various impurities in water? Ans.- Impurities in water - The impurities in water are classified as - i. Suspended Impurities. ii. Colloidal Impuritie

Shear stress distribution on sections, is shear stress distribution on I an...

is shear stress distribution on I and T sections are same????

How double drainage occur, The loading period for a building extended from ...

The loading period for a building extended from Feb., 1957 to Feb., 1959. In Feb., 1962, the average measured settlement was found to be 117 mm. The ultimate settlement was expecte

Shallow bedrock condition adverse for open berth piers, Question What i...

Question What is the reason that shallow bedrock condition adverse for open berth piers? Answer Most severe load on piers generally is horizontal load due to berthing

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd