a. Activity C can be started only after the completion of activities A and B

b. Activity D can be started only activity B is completed

c. Activity E can be started only when activities A, B, C and D have been completed

 


Related Discussions:- Determine condition of activity in the network flow diagram

Approach span to its neighbouring inner spans, Question-Why is span length...

Question-Why is span length ratio of end span, approach span to its neighbouring inner spans typically about 0.75?   Answer-From aesthetic point of view, odd number of span

Water absorption test - tests on stones, Water Absorption Test: In t...

Water Absorption Test: In this test cube specimen weighing approximate 50 grams are prepared and the test is carried out in the steps following: 1.    Note down the weigh

Survey, How to find included angle during partical

How to find included angle during partical

Define masonry substructure- underwater inspection of bridge, Define Masonr...

Define Masonry substructure- underwater inspection of bridge? In early days, masonry, particularly stone masonry was extensively used for bridge piers and abutments. Typically,

Disparities b/w epoxy grout cement grout and cement mortar, Question What a...

Question What are the key disparities between epoxy grout cement grout and cement mortar ? Answer Epoxy grout contains of epoxy resin, epoxy hardener and sand or aggregates.

What is main purpose of swabbing, Question After construction of waterm...

Question After construction of watermain, earlier to hydrostatic pressure test , swabbing is approved out. What is main purpose of swabbing ? Answer Pipelines ha

Calculate the energy loss in the piping system, The head (energy) loss in t...

The head (energy) loss in the piping system between points 1 and 7 is the most nearly. Solution: 3 ft. The difference between point 1 and point 7 = 10 ƒt - 7 ƒt = 3 ƒt

Joints in box culverts and channels, Joints in box culverts and channels - ...

Joints in box culverts and channels - necessity of water tightness The joints for box culverts and channels must be capable of accommodating movements arising from moisture an

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd