Define Truss analysis-stability  

  • Identify whether a truss is determinate or indeterminate.
  • Identify if the truss is stable or unstable

 

m = number of members

r = number of reaction components

j = number of joints

m + r < 2*j -> Unstable

m + r = 2*j -> Statically determinate

m + r > 2*j -> Statically indeterminate

If m + r ≥ 2*j -> Check stability visually


Related Discussions:- Define truss analysis-stability

Energy absorbed in heeling during vessel berthing, Q. Energy absorbed in he...

Q. Energy absorbed in heeling during vessel berthing? When a vessel   berths on a fender system at a pier, point of contact of berthing ship can be below or above the centre of

State the term - transverse force on concrete, State the term - transverse ...

State the term - transverse force on concrete We know that in pre-stressed concrete, tendons are placed in a stretched condition and they always would try to regain their origi

Postensioning in raft foundation, how can we post tension a raft foundation...

how can we post tension a raft foundation? what design procedure should we follow to post tension raft foundation in order to decrease the concrete and steel volume and increase th

Bitumen tests, discussion of each bitumen test, its significance and import...

discussion of each bitumen test, its significance and importance in understanding and working with bitumen

BOLTED CONNECTIONS, compare riveted joints with welded joints

compare riveted joints with welded joints

Construction of concrete carriageway, Question If construction of conc...

Question If construction of concrete carriageway is carried out in summer, be capable of expansion joints be omitted? Answer If construction of concrete carriageway

Levelling, important terms used in levelling

important terms used in levelling

Define project schedule financial analysis, The 6 monthly payment applicati...

The 6 monthly payment application for the construction of a $70,000,000 University dormitory is analyzed and the summary accounting show: the budgeted cost of work performed is $14

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd