Equations account for the loss of power, primarily due to mechanical friction as a result of rotating components in the pump and motor.

Pump efficiency = (whp/bhp) 100

Motor efficiency = (bhp/ehp) 100

Overall efficiency = (pump efficiency)(motor efficiency)  = (whp/ehp) 100


Related Discussions:- Define the pump and motor efficiencies - hydrolic system

Doors and windows, what are the actuall windows and door dimensions e.g AN ...

what are the actuall windows and door dimensions e.g AN ND4

Infrastructure railway design, The objective of this module is:- - For t...

The objective of this module is:- - For the student to identify the track design issues and there relationships that will need to be considered in the development of a feasibili

What are the parasitic forces for prestressing, Q. What are the Parasitic f...

Q. What are the Parasitic forces for prestressing? In statically determinate structures, prestressing forces will cause the concrete structures to end upwards. Therefore precam

Depth of boring for multi-storeyed building, Depth of Boring  for Multi-st...

Depth of Boring  for Multi-storeyed Building Peck has recommended that first drill hole is to be made up to depth at which the presence of a thick layer of soft clay with a hig

Plinth wall, is it necessary for to put plinth wall in buildings

is it necessary for to put plinth wall in buildings

Determine the total active thrust by rebhann''s method, A retaining wall 3....

A retaining wall 3.6 m high supports a dry cohesion less backfill with a plane ground surface sloping upwards at a surcharge angle of 20° from the top of the wall. The back of the

Method of construction of a bored cast-in-situ concrete pile, Q. Method of ...

Q. Method of construction of a bored cast-in-situ concrete pile? Ans. - Bored cast-in-situ concrete pile - A guide casing of 3 to 4 m length is provided on top of the bore hole

Levelling, how to go about the collimation method.

how to go about the collimation method.

Underwater problems in bridge construction, Q. Underwater problems in bridg...

Q. Underwater problems in bridge construction? The major bridge construction materials are steel and concrete. In the past, stone and brick masonry, with lime mortar as binding

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd