Define the finish to finish activity, Civil Engineering

Assignment Help:

A finish-to-finish activity is best described as:

  1. The "from" activity must finish before the "to" activity can finish
  2. The "from" activity must finish before the "to" activity can start
  3. The "from" activity must start before the "to" activity can start
  4. The "from" activity must start before the "to" activity can finish  

Solution: 1. The "from" activity appears first and the "to" activity appears second in the sequence.


Related Discussions:- Define the finish to finish activity

Define types of seismic isolation bearing - rubber bearings, Define Types o...

Define Types of Seismic Isolation Bearing - Rubber Bearings? Seismic isolation is obtained by two types of isolation bearings. a) Rubber bearings b) Friction pendulum bea

Amount of borrow needed to bring area to elevation of 90-ft, Surveyed eleva...

Surveyed elevations are shown in Figure for a 50' x 50' grid at a proposed parking lot location. The amount of borrow needed to bring the area to an elevation of 90-ft is most near

Determine the load which a square footing, Two load tests were performed at...

Two load tests were performed at a site-one with a 50 cm square plate and the other with a 75 cm square plate. For a settlement of 15 mm, the loads were recorded as 50 kN and 90 kN

Delay of bituminous laying on top of sub-base, Question In case if ther...

Question In case if there is a delay of bituminous laying on top of sub-base, have to tack coat be applied on the top surface of sub-base? Answer When there is a d

Building classification, Why I is the missing after h and J is written in t...

Why I is the missing after h and J is written in the classification of building

Reduced levelling, what is the theary of reduced levelling

what is the theary of reduced levelling

Structures, Derivation of Moment-Area Method

Derivation of Moment-Area Method

How to design marginal embankments, Q. How to design Marginal Embankments? ...

Q. How to design Marginal Embankments? Design aspects of marginal embankments are similar to those of approach banks. The aspects needing special attention are dealt with below

STRENTH OF MATERIAL, WHY WE ARE USING MAMENT OF INERTIA IN STRAIN ENERGY ST...

WHY WE ARE USING MAMENT OF INERTIA IN STRAIN ENERGY STRUCTURE

Construct the correct network for project, A project requires that activiti...

A project requires that activities A and B can be started independently and activities C and D are independent but can be started after A and B have been completed. Activity E can

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd