Determine the water-cement ratio, Civil Engineering

Assignment Help:

A concrete batch plant provided the Design Strength for the engineer's mix design to match the project's specification requirement for a 4000 psi Tremie pump mix.  The Water-cement ratio is most nearly:

1096_Determine the water-cement ratio.png

Solution:

From the given information: 

Cement + Flyash = 658-lbs

Water = 30.0-gal x 8.345-lbs/gal = 250.35-lbs

w/c = 250.35 / 658 = .38


Related Discussions:- Determine the water-cement ratio

Trigonometry, #question a pilot entering a bay on course 60.3 degrees at sp...

#question a pilot entering a bay on course 60.3 degrees at speed 12 miles per hour sees a light bearing 37.3 true and 20 minutes later he sees it bearing 20.0 degrees true. if he k

Maintenance of drainage and shoulders, Maintenance of Drainage: Maint...

Maintenance of Drainage: Maintenance of drainage will ensure that the run-off is taken away from the runway efficiently. The side ditches and buried pipes should be cleaned r

Management of engineering stores general, Charged of stores - The follo...

Charged of stores - The following types of stores come under this category: - i. Consumable stores, such as kerosene oil, paints, varnishes, cotton waste and grease, etc, is

Explain is vadose zone - ground water, Explain is Vadose Zone - Ground wate...

Explain is Vadose Zone - Ground water In an unconfined aquifer, it is the area located above the water table and aquifer, where the soil and rock are not saturated with water.

Calculate the percent grade of line, 1. The topography of a local valley is...

1. The topography of a local valley is shown. The horizontal distance between point P and Q is 11,456-ft. The percent grade (%) of line P-Q .     2. Based on the info

Role of rebate in typical construction joint, Question What is role of reba...

Question What is role of rebate in typical construction joint ? Answer Construction joints are formed on sites to facilitate construction procedure. Though, if improperly constr

Define deferred maintenance- underwater inspection of bridge, Define Deferr...

Define Deferred maintenance - underwater inspection of bridge? Many problems of the substructure can be traced to lack of any maintenance in time, which again can be due to lac

Surveying, why we perform survey work from whole to the part?

why we perform survey work from whole to the part?

Continuous flow systems, Continuous Flow Systems: Transport by road, r...

Continuous Flow Systems: Transport by road, rail, air or ships takes place in vehicles which move along a path at intervals. As against this, continuous flow systems are those

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd