Q. What are rules for working of Dip lorries and their protection arrangements on a single line section explain with sketches?

Ans.-Rules for working of Dip lorries -

i. Subject to their being certificate comp lent the all inspectors of engineering and signal and tele communication departments are permitted to us Dip lorri.

ii. No Railway servant shall use a lorry unless he is in a possession of a permit.

iii. The permit will only be issued after examined and valid for a period of one year.

iv. Each Lorry must have marked on it the number designation and code initials of the HQ.

v. Whenever lorry be placed on P.F. for loading on a train it should be placed paralleld to the Track.

vi. Lorry shall always be pushed and not pulled.

vii. When ever a lorry has to work within station section the PWI will advise the station master in writing.

viii. A lorry may be worked with out block protection when the PWI before putting a lorry on the line has as certained from the station master on duty.

ix. When the PWI intents to place the lorry on the line in mid section he shall issue a message on field telephone to the Station Master.


Related Discussions:- What are rules for working of dip lorries

science and materials, the behaviour of structural materials using compara...

the behaviour of structural materials using comparative statement when they are formed into structural member

Problems in turbid water - underwater inspection of bridge, Define Problems...

Define Problems in turbid water - underwater inspection of bridge? There are three main problems, which limit the viewing performance of an underwater camera. These are: -

Raised check rails for obtuse crossing, Raised Check Rails for obtuse cross...

Raised Check Rails for obtuse crossing In order to provide guided path way in throat portion of 1 in 8 1/2 BG obtuse diamond crossing, the check rails are raised by welding of

Consolidated undrained or consolidated drained analysis, Question In de...

Question In determining effectual stress parameters of a soil sample, which test is good, consolidated undrained analysis or consolidated drained analysis? Answer Effec

Define the void ratio and specific gravity of particles, Derive the formula...

Derive the formula among soil moisture content (w), degree of saturation (S), specific gravity (G), and void ratio (e). Saturated clay has a water content of 40% and bulk specif

Levelling, the cooke''s reversible level

the cooke''s reversible level

Som, Maximum thermal stress in circular tapering section is

Maximum thermal stress in circular tapering section is

REport, CASTE DISCRIMANIMATION

CASTE DISCRIMANIMATION

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd