Define the cost per square foot of contact area, Civil Engineering

Assignment Help:

Define the Cost per Square Foot of Contact Area

The cost of concrete formwork is influenced by three factors:

1. Initial cost or fabrication cost that contains the cost of transportation, materials, assembly, and erection.

2. Potential reuse which decreases the final total cost per square foot of contact area. The data in Table indicates that the maximum economy can be achieved by maximizing the number of reuses.

588_Define the Cost per Square Foot of Contact Area.png

3. Stripping costs, this also includes the cost of cleaning and repair. This item tends to stay constant for each reuse up to a fixed point at which the total cost of repairing and cleaning start rising rapidly.

In deciding to use a specific formwork system, the initial cost should be evaluated versus the available budget for formwork cost. Some formwork systems tend to have a high initial cost, but through repetitive reuse, they become economical.

For example, slip forms have a high initial cost, but the average potential reuse (usually over 100 times) reduces the final cost per square foot of contact area for the type of formwork. In the case of rented formwork systems, the period of time the formwork is in use has a great effect on the cost of the formwork.


Related Discussions:- Define the cost per square foot of contact area

Determine the bar sizes and spacing, Referring to problem 1, in order to me...

Referring to problem 1, in order to meet a 1-hour fire code rating the slab thickness must be at least 4.00. Based on the information given in problem 1 and with a slab thickness o

Differences between open shield and closed shield, Q. Differences between o...

Q. Differences between open shield and closed shield? Open shield type TBM refers to those providing lateral support only. They can be further classified into single shield and

Determine the water-cement ratio, A concrete batch plant provided the Desig...

A concrete batch plant provided the Design Strength for the engineer's mix design to match the project's specification requirement for a 4000 psi Tremie pump mix.  The Water-cement

Determine the loss in post-tensioned members, Determine the Loss in post-te...

Determine the Loss in post-tensioned members This loss occurs only in post-tensioned members. There always exists a certain amount of friction in the jacking and anchoring syst

Define categories of scaling-underwater inspection of bridge, Define the Ca...

Define the Categories of Scaling? Scaling is classified into following three categories: i. Light scale - loss of surface mortar up to 5 mm deep, with surface exposure of co

Single flemish bond, advantages and disadvantages in single flemish bond

advantages and disadvantages in single flemish bond

CONCRETE BATCHING, DOES A GAUGE BOX OF THE SIZE LIKE 50,40,30 MM EXISTS?

DOES A GAUGE BOX OF THE SIZE LIKE 50,40,30 MM EXISTS?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd