Designing of watermain, Civil Engineering

Assignment Help:

Question

In designing of watermain, regular practice is to use supple iron for pipe size less than 600mm and to use steel for pipe size additional than 600mm. Give some specific and main reasons?


Answer


For watermain pipe size less than 600mm, ductile iron is usually used since internal welding for steel pipes below 600mm is difficult to be carried out. Furthermore, it requires only simple jointing details that allow for faster rate of structure. For watermain pipe size higher than 600mm, steel pipes are recommended as steel pipes are lighter as compare to ductile iron pipes for same material strength and so cost of steel pipes is less than that of ductile iron pipes. In adding, in areas of difficult contact lighter mild steel pipes pose benefit over ductile iron pipes for simple handling.

 

 


Related Discussions:- Designing of watermain

What is partial prestressing, What is Partial Prestressing It is a form...

What is Partial Prestressing It is a form of prestressing in which tensile stresses are permitted, upto a limited extent, in concrete under working loads. As the permitted tens

Reinforcement in thrust blocks, Reinforcement in thrust blocks In gene...

Reinforcement in thrust blocks In general situation, reinforcement isn't essential for thrust blocks in pressurized pipelines. Though certain amount of reinforcement hasto be

Maintenance of drainage and shoulders, Maintenance of Drainage: Maint...

Maintenance of Drainage: Maintenance of drainage will ensure that the run-off is taken away from the runway efficiently. The side ditches and buried pipes should be cleaned r

Mechanics problem, i am facing some problem in solving the problem of elong...

i am facing some problem in solving the problem of elongation due to self weight suspended from fixed support in the conical bar

Define the predominant factor in atmospheric corrosion, Define the Predomin...

Define the Predominant factor in atmospheric corrosion? The predominant factor in atmospheric corrosion in areas located above splash zone is moisture as there is an excess ava

Design volume of the aeration basin - sewer construction, Design volume of ...

Design volume of the aeration basin - sewer construction: Problem: What is the design volume of the aeration basin? Solution Assuming that 30% of the plant influe

Mensuration, My team has to construct a swimming pool at the back of the ho...

My team has to construct a swimming pool at the back of the house. It’s interior dimensions are 10M x 3M and 1M at the shallow end and 2.5M at the deep end. The walls and the bas

Full bore flow in drainage design, Q. Full bore flow in drainage design? ...

Q. Full bore flow in drainage design? In the design of gravity drainage pipes, full bore flow capacity is usually adopted to check against design runoff. Though one should note

Determine the example of tendon splices, Determine the example of tendon s...

Determine the example of tendon splices Following are some examples of  tendon splices. (a) Torpedo splice (b) Clamp splice (c)  Screw connectors

Define facilities that discharge wastewater to a potw, Facilities that disc...

Facilities that discharge wastewater to a publicly owned treatment works? Facilities that discharge wastewater to a POTW (publicly owned treatment works) are known as subject t

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd