Define alum (aluminum sulfate) caogulation, Civil Engineering

Assignment Help:

Define Alum (aluminum sulfate) Caogulation

  • Purchased as dry or liquid alum { Al2(SO4)3,14 H2O}, MW 594 (other formulas with varying number of water molecules also used)
  • 48.8% alum and rest water
  • When alum is added to water containing alkalinity (pH 5.5 to 8.)

 

206_Define Alum (aluminum sulfate) Caogulation.png

  • Each mole of alum uses 6 moles of alkalinity (HCO-3) and produces 2 moles of aluminum hydroxide (solid precipitate) and 6 moles of CO2 which decreases the ph
  • However due to the presence of alkalinity pH won't lower drastically If there is not enough alkalinity, lime (either as CaO or Ca(OH)2 ) or soda ash (Na2CO3) can be added to prevent pH from lowering due to the coagulation reaction.

Related Discussions:- Define alum (aluminum sulfate) caogulation

Designing of service reservoirs, Question In designing of service res...

Question In designing of service reservoirs , straight reinforcement in walls of reservoirs is placed at external layer. Give some specific and main reasons?   Answer

Dissimilarity in methods of compaction, Question Are there any dissimil...

Question Are there any dissimilarity in methods of compaction between clayey soil material and sandy material ? Answer The three key actions of compaction are static

Determine the major and minor principal effective stresses, The stresses ac...

The stresses acting on the plane of maximum shearing stress by a given point in sand are as follows: total normal stress = 250 kN/m 2 ; pore-water pressure = 88.5 kN/ m 2 ; shearin

Major differences between sureties and security, Question What are majo...

Question What are major differences between sureties and security ? Answer During construction contracts, if a contractor fails to carry out works, employer would e

Centroid, use of centroid in civil engineering

use of centroid in civil engineering

Necessity for road drainage - road drainage, Necessity for Road Drainage: ...

Necessity for Road Drainage: Poor drainage can cause damage to the various components of a road in the following manner: (a) Water can enter the various pavement layers th

Calculate the total duration for the four activity project, Calculate the T...

Calculate the Total Duration for the Four Activity Project Solution:      Scheduling work activity has associated time duration. The durations shown in the Table were e

Show elastomeric bearings, 1. Elastomeric bearings must not be placed one b...

1. Elastomeric bearings must not be placed one behind the other along the longitudinal axis of the girder on a single line of support under any circumstances. 2. Bearings of dif

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd