Lubrication of rail joint, Civil Engineering

Assignment Help:

Lubrication of rail joints is one of the important items of permanent way works incidental to systematic track maintenance, the lubrication of joints is done for the following purpose -

i. To allow for free expansion of rails.

ii. To reduce wear and tear on the fishing planes of rails and fish plates.

The lubrication of rail joints also called oiling and greasing of fishplates is done once a year for all the joints during the moderate season which does not have extremes of weather (both hot & cold ). Rainy season is also excluded for this purpose. The lubricant used is a paste of workable consistency made of plumbago Kerosine oil and black oil in the following proportion -

Plumbago ( Dry Graphite ) = 5 kg.

Kerosine oil ( IInd Quality ) = 3.5 Liter.

Black or Reclaimed oil = 2.75 Liter.

For 100 joints of 52 kg / 90R or for 125 joints of 75 R / 60 R

Some items only plumbago and kerosin oil is used in the ratio of 3 : 2 for lubrication of fishplates the black oil is however used for oiling of fish bolts and nuts.


Related Discussions:- Lubrication of rail joint

Highway transportation, HIGHWAY TRANSPORTATION: Broadly, there are two...

HIGHWAY TRANSPORTATION: Broadly, there are two classes of roads: (a)        Urban, and (b)       Rural (Non-urban). Urban roads are those which are located within tow

Collapse mechanisms in unsymmetrical portal frames, How to find beam,sway a...

How to find beam,sway and combined mechanisms for unsymmetrical portal frames? Also how to find the critical mechanisms by using plotting method?

Calculate the monthly payment for home mortgage, Your home mortgage is $300...

Your home mortgage is $300,000 for 30 years with a nominal annual rate of 7%. The monthly payment is most nearly: Solution: n = 360 months interest = 7%-annual ÷ 12-months/year

Cement, List the ingredients of cement And their functions

List the ingredients of cement And their functions

Compute the ultimate settlement, A 2 m wide strip footing is to be constru...

A 2 m wide strip footing is to be constructed in a sandy stratum of 2 m thick. The depth of the footing is 1 m below ground surface. The sand layer is underlain by lm thick cla

Wall method of estimation, 1. Can you enumerate the benefits of individual ...

1. Can you enumerate the benefits of individual wall method of estimation? 2. Estimate the single room of size 3m x 4m x height 3m  using individual wall method? 3. Which met

Timber design, design of timber in flexural members in terms of extreme fib...

design of timber in flexural members in terms of extreme fibre stress in bending, maximum horizontal shear stress, deflection and bearing stress perpendicular to the grain. the ful

Optimum moisture content to grab maximum density, Question For compacti...

Question For compaction of free-draining sands or gravels, what is optimum moisture content to grab maximum density ? Answer Compaction curve of dirty materials is com

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd