Cleaning and greasing of steel sliding bearings :
Following equipments are required for greasing of steel sliding bearings:
1. Jacks (50 ton capacity) - 2 nos.
2. Hard wooden packing below and above jack
3. Grease graphite Grade 3 conforming to IS:508
4. Kerosene or released black oil for cleaning
5. 6 mm thick steel scrapers
6. Mortar pan
7. Cotton waste
Greasing of sliding bearings can be undertaken under traffic with issue of caution order and line protection for temporary works as per provision of IRPWM.
Lifting of girder should be restricted to 8 to 10 mm only, ensuring that the bearing strip does not get lifted over locking strip and guide strip to avoid creep of girder in logitudinal and lateral direction. For lifting, it is not necessary to break the track. Only loosening of fish bolts and dog spikes over a small length on both sides of the pier is sufficient. Only one end of the girder should be lifted at a time and steel scraper inserted between bearing strip and base plate to remove old grease dust and dirt. The contact surface is cleaned with oil and grease applied. Girder is then lowered back over the base plate. Time required for all these activities is approximately 15 to 20 minutes.
Define Investigation Scour for Underwater Inspection of Bridge? Investigation Scour is probably the most critical item to be aware of when performing an underwater inspection o
1. The topography of a local valley is shown. The horizontal distance between point P and Q is 11,456-ft. The percent grade (%) of line P-Q . 2. Based on the info
Pre-tensioned concrete elements It is the act of transferring the stress in prestressing tendons to the concrete member. In the case of pre-tensioned concrete elements, this st
staircase
Effect of concrete placing temperature on early thermal movement Rate of hydration of cement paste is related to placing temperature of concrete. Rate of heat production is giv
stress and there types
Define Unit Hydrograph UNIT HYDROGRAPH: The hydrograph developed for a drainage basin (watershed) from the runoff of a 1 in or 1 cm storm. It is the base hydrograph from which
classification and characterstics of lintels
Explain term - losses of prestress We know that with time, tendons lose some of their initial prestress (at the time of transfer of prestress). This is termed as 'losses of pre
A nearly horizontal, 12 ft wide rectangular channel carries 60 cfs at a depth of 3.0 ft. The width of the channel is smoothly contracted to 6 ft at the downstream section. (a) Dete
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd