Change order management, Other Management

Assignment Help:

Change Order Management

In previous section we learnt that incentives motivate and penalties keep a check for faults that occur in a project. In this section we will understand about a change order management.

A change order is order for work that is added to or deleted from the original  scope  of  work  in  a  contract,  which  alters  the  original  contract amount and/or completion date. A contractor?s claim for such an alteration due to a work perceived by him as additional work remains as a claim until the change order is resolved. A claim is a potential source of dispute. Hence resolution of change order situations knowledgably, fairly and promptly benefits both owner and contractor.

Change  order  is  a  component  of  the  change  management  process  in contract management. The change management process should enable implementation of changes in a system in a controlled manner by following a predefined framework/model. Change order management is hence a critical aspect of any construction job.

The rights of a contractor to a change order arise from the contract. If the contractor?s claim is not consistent with the contract, it will be denied, unless you admit it by oversight.

Project construction contracts always incorporate a Changes clause which provides allows you to order extra work without invalidating the contract or make changes to the existing work by altering, adding to or deducting from the work, with the contract sum.

The reasons this change clause is needed are:

  • Impossibility of perfect drawings and specifications: A fundamental truth in the construction industry is that no design can be made perfect.
  • Impractical risk allocations: The fundamental principle of risk allocation is to assign each risk to the party who is best able to control, manage or absorb that risk, which is the way to achieve maximum efficiency and economy. When contract for construction is taken up by a general contractor, his tendency will be to shift the risks to subcontractors and so on down the line leading to improper risk allocation.
  • Contractor-suggested changes: In many project contracts, value engineering proposals from contractor should be encouraged by owner.
  • Owner-suggested changes: You may discover obstacles or possible efficiencies that require them to deviate from the original plan.

Other than the above reasons, incorrectly estimated work or failure to meet commitments can lead to claims by contractor. Examples are:

  • Unforeseen adverse site conditions or actual site conditions being more adverse than what is mentioned in the contract.
  • Failure to make the site available at the time and in the condition required by the contract.
  • Failure to grant, or delay in granting, legitimate time extensions.
  • Unreasonable or mistaken inspection.

Although you can unilaterally order that changes be made, there is a commensurate duty on you, to make adjustments in the contract sum or contract time. Hence changes provisions in contract should typically provide methods for making these adjustments.

Changes in contract sum or contract time are made on the basis of negotiations between owner and contractor. The basis can be:

  • Unit prices for specific items of work.
  • Recognised mark-ups for contractor?s work and subcontractor?s work.

Related Discussions:- Change order management

Market testing and commercialization, Question: A company faces a decis...

Question: A company faces a decision with respect to a product (code named M997) developed by one of its research laboratories. It has to decide whether to proceed to test mark

Improve distance learning programmes, Question: "Web-based training is ...

Question: "Web-based training is part of the biggest change in the way our species conducts training since the invention of the chalkboard or perhaps the alphabet. The developm

Library journal - library management system, Library Journal: Publish...

Library Journal: Publishes quarterly lists  of scientific,  technical and medical books announced for publication by publishers.  The third category of review  sources is d

Physical mobilisation, The areas to be considered while monitoring and cont...

The areas to be considered while monitoring and controlling a contract are wide spread. They are: P h y sical mobilisation: In this stage, the contractor gathers people, m

Dealer library plan and standing order, Dealer Library Plan (DLP): Und...

Dealer Library Plan (DLP): Under this plan, as agreement is reached between the library and the publishers or a group of publishers whereby the publishers send books as soon a

Explain the concept behind electronic check, Question: a) List and des...

Question: a) List and describe the role of the different parties involved in any e-payment system. b) Outline five factors (characteristics) that determine the acceptance

Documentary sources - source of data, Documentary Sources: Those  info...

Documentary Sources: Those  information which are contained  in  the published and unpublished documents, reports, statistics, manuscripts, letters, diaries  and so on, are gr

Acquisition motives, A c quisition Motives In the previous unit you l...

A c quisition Motives In the previous unit you learnt about the history of M and A. All the companies do not always have acquisition strategies, and not all companies that ha

Line balancing, what is line balancing. what happens if balance doesn''t ex...

what is line balancing. what happens if balance doesn''t exist

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd