Change order management, Other Management

Assignment Help:

Change Order Management

In previous section we learnt that incentives motivate and penalties keep a check for faults that occur in a project. In this section we will understand about a change order management.

A change order is order for work that is added to or deleted from the original  scope  of  work  in  a  contract,  which  alters  the  original  contract amount and/or completion date. A contractor?s claim for such an alteration due to a work perceived by him as additional work remains as a claim until the change order is resolved. A claim is a potential source of dispute. Hence resolution of change order situations knowledgably, fairly and promptly benefits both owner and contractor.

Change  order  is  a  component  of  the  change  management  process  in contract management. The change management process should enable implementation of changes in a system in a controlled manner by following a predefined framework/model. Change order management is hence a critical aspect of any construction job.

The rights of a contractor to a change order arise from the contract. If the contractor?s claim is not consistent with the contract, it will be denied, unless you admit it by oversight.

Project construction contracts always incorporate a Changes clause which provides allows you to order extra work without invalidating the contract or make changes to the existing work by altering, adding to or deducting from the work, with the contract sum.

The reasons this change clause is needed are:

  • Impossibility of perfect drawings and specifications: A fundamental truth in the construction industry is that no design can be made perfect.
  • Impractical risk allocations: The fundamental principle of risk allocation is to assign each risk to the party who is best able to control, manage or absorb that risk, which is the way to achieve maximum efficiency and economy. When contract for construction is taken up by a general contractor, his tendency will be to shift the risks to subcontractors and so on down the line leading to improper risk allocation.
  • Contractor-suggested changes: In many project contracts, value engineering proposals from contractor should be encouraged by owner.
  • Owner-suggested changes: You may discover obstacles or possible efficiencies that require them to deviate from the original plan.

Other than the above reasons, incorrectly estimated work or failure to meet commitments can lead to claims by contractor. Examples are:

  • Unforeseen adverse site conditions or actual site conditions being more adverse than what is mentioned in the contract.
  • Failure to make the site available at the time and in the condition required by the contract.
  • Failure to grant, or delay in granting, legitimate time extensions.
  • Unreasonable or mistaken inspection.

Although you can unilaterally order that changes be made, there is a commensurate duty on you, to make adjustments in the contract sum or contract time. Hence changes provisions in contract should typically provide methods for making these adjustments.

Changes in contract sum or contract time are made on the basis of negotiations between owner and contractor. The basis can be:

  • Unit prices for specific items of work.
  • Recognised mark-ups for contractor?s work and subcontractor?s work.

Related Discussions:- Change order management

Improve public sector performance, QUESTION 1 A core concept in implem...

QUESTION 1 A core concept in implementing TQM is Deming's 14 points, a set of management practices to help companies increase their quality and productivity. List 7 points and

Briefly describe two safety precautions fishermen operating, Question : ...

Question : (i) Give two reasons why fish could be aggregating around a floating object. (ii) What are the differences between (a) an anchored fish aggregating device; (b)

Benefits of b2b e-commerce in developing markets, Question: (a) What ...

Question: (a) What are the benefits of B2B E-Commerce in Developing Markets? (b) The B2B market has primary components: e-frastructure and e-markets, e_infrastructure is t

Quality management, . During the analysis of a process that was evaluated, ...

. During the analysis of a process that was evaluated, a situation arose where it was seen that the variability of the data points collected was non-random on several occasions, i.

Acquisition department, ACQUISITION DEPARTMENT: Libraries are organise...

ACQUISITION DEPARTMENT: Libraries are organised into units / departments / sections based on the functions that they are expected to perform. Acquisition Department (=AD) is o

Laws of library science, The study of the structure and development of the ...

The study of the structure and development of the UoS by the information professional can be shown to be a necessary implication of the five laws of library science. Law 1 And I

What are the traditional measures of development, Question 1: a. What a...

Question 1: a. What are the traditional measures of development? b. What are the basic characteristics of the least developing nations? c. According to Denis Goulet, what

Environmental assessment and management, Environmental Assessment and Manag...

Environmental Assessment and Management: 1. Using a case study area of your choice, explain and demonstrate different understandings of nature, environment and / or landscape

Sampling error and sampling bias, SAMPLING ERROR AND SAMPLING BIAS: Sa...

SAMPLING ERROR AND SAMPLING BIAS: Sampling error may  be  deiined  as the difference between  data obtained  from random sample and data  obtained  from  entire population.  E

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd