Change order management, Other Management

Assignment Help:

Change Order Management

In previous section we learnt that incentives motivate and penalties keep a check for faults that occur in a project. In this section we will understand about a change order management.

A change order is order for work that is added to or deleted from the original  scope  of  work  in  a  contract,  which  alters  the  original  contract amount and/or completion date. A contractor?s claim for such an alteration due to a work perceived by him as additional work remains as a claim until the change order is resolved. A claim is a potential source of dispute. Hence resolution of change order situations knowledgably, fairly and promptly benefits both owner and contractor.

Change  order  is  a  component  of  the  change  management  process  in contract management. The change management process should enable implementation of changes in a system in a controlled manner by following a predefined framework/model. Change order management is hence a critical aspect of any construction job.

The rights of a contractor to a change order arise from the contract. If the contractor?s claim is not consistent with the contract, it will be denied, unless you admit it by oversight.

Project construction contracts always incorporate a Changes clause which provides allows you to order extra work without invalidating the contract or make changes to the existing work by altering, adding to or deducting from the work, with the contract sum.

The reasons this change clause is needed are:

  • Impossibility of perfect drawings and specifications: A fundamental truth in the construction industry is that no design can be made perfect.
  • Impractical risk allocations: The fundamental principle of risk allocation is to assign each risk to the party who is best able to control, manage or absorb that risk, which is the way to achieve maximum efficiency and economy. When contract for construction is taken up by a general contractor, his tendency will be to shift the risks to subcontractors and so on down the line leading to improper risk allocation.
  • Contractor-suggested changes: In many project contracts, value engineering proposals from contractor should be encouraged by owner.
  • Owner-suggested changes: You may discover obstacles or possible efficiencies that require them to deviate from the original plan.

Other than the above reasons, incorrectly estimated work or failure to meet commitments can lead to claims by contractor. Examples are:

  • Unforeseen adverse site conditions or actual site conditions being more adverse than what is mentioned in the contract.
  • Failure to make the site available at the time and in the condition required by the contract.
  • Failure to grant, or delay in granting, legitimate time extensions.
  • Unreasonable or mistaken inspection.

Although you can unilaterally order that changes be made, there is a commensurate duty on you, to make adjustments in the contract sum or contract time. Hence changes provisions in contract should typically provide methods for making these adjustments.

Changes in contract sum or contract time are made on the basis of negotiations between owner and contractor. The basis can be:

  • Unit prices for specific items of work.
  • Recognised mark-ups for contractor?s work and subcontractor?s work.

Related Discussions:- Change order management

Managerial economics, what is prisoner''s dilemma'',of non cooperative game...

what is prisoner''s dilemma'',of non cooperative game?

Basic terminology - library management, BASIC TERMINOLOGY - Library managem...

BASIC TERMINOLOGY - Library management: A term may be defined as a standardised name for a. given entity or concept which is precise. Terminology, in its turn, is defined as a

Change owner, T he change owner The change owner is the person assigne...

T he change owner The change owner is the person assigned to essentially arrange and then make the approved changes to the system. The change owner is consulted about the foll

Discuss the sq3r technique of reading, Question 1 What do you mean by b...

Question 1 What do you mean by barriers of communication? Explain different types of barriers to communication 2 Explain the different types of listening 3 Discuss the SQ

Planning for negotiations , Planning for negotiations  A complex negoti...

Planning for negotiations  A complex negotiation requires specific planning to be successful. Without planning, a negotiator cannot possibly have the information required to ef

List and explain the risks, QUESTION a) Define risk as per the Public P...

QUESTION a) Define risk as per the Public Private Partnership Guidance Manual b) What are the primary objectives of transferring risks from a contracting authority to a priv

Literature search, LITERATURE SEARCH: The ultimate objective of any do...

LITERATURE SEARCH: The ultimate objective of any documentation or information activity is to provide the user with the information he needs, to the extent he requires, within

Nature of terms - library management, Nature of Terms: In an analysis ...

Nature of Terms: In an analysis of classification terminology, Prasad (1986) had identified three types of terms - normative, fundamental and associative. Normative terms are

Skills in literature search, Skills in Literature Search: Expertise in...

Skills in Literature Search: Expertise in literature search can be gained only by experience. Some attitudes or traits conducive to a good literature search are: imagination,

Describe carefully the forms of organizational culture, QUESTION 1 (a) ...

QUESTION 1 (a) What is an organization? (b) What is management? (c) Describe carefully the functions of managers in organizations QUESTION 2 Organisations are com

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd