Change order management, Other Management

Assignment Help:

Change Order Management

In previous section we learnt that incentives motivate and penalties keep a check for faults that occur in a project. In this section we will understand about a change order management.

A change order is order for work that is added to or deleted from the original  scope  of  work  in  a  contract,  which  alters  the  original  contract amount and/or completion date. A contractor?s claim for such an alteration due to a work perceived by him as additional work remains as a claim until the change order is resolved. A claim is a potential source of dispute. Hence resolution of change order situations knowledgably, fairly and promptly benefits both owner and contractor.

Change  order  is  a  component  of  the  change  management  process  in contract management. The change management process should enable implementation of changes in a system in a controlled manner by following a predefined framework/model. Change order management is hence a critical aspect of any construction job.

The rights of a contractor to a change order arise from the contract. If the contractor?s claim is not consistent with the contract, it will be denied, unless you admit it by oversight.

Project construction contracts always incorporate a Changes clause which provides allows you to order extra work without invalidating the contract or make changes to the existing work by altering, adding to or deducting from the work, with the contract sum.

The reasons this change clause is needed are:

  • Impossibility of perfect drawings and specifications: A fundamental truth in the construction industry is that no design can be made perfect.
  • Impractical risk allocations: The fundamental principle of risk allocation is to assign each risk to the party who is best able to control, manage or absorb that risk, which is the way to achieve maximum efficiency and economy. When contract for construction is taken up by a general contractor, his tendency will be to shift the risks to subcontractors and so on down the line leading to improper risk allocation.
  • Contractor-suggested changes: In many project contracts, value engineering proposals from contractor should be encouraged by owner.
  • Owner-suggested changes: You may discover obstacles or possible efficiencies that require them to deviate from the original plan.

Other than the above reasons, incorrectly estimated work or failure to meet commitments can lead to claims by contractor. Examples are:

  • Unforeseen adverse site conditions or actual site conditions being more adverse than what is mentioned in the contract.
  • Failure to make the site available at the time and in the condition required by the contract.
  • Failure to grant, or delay in granting, legitimate time extensions.
  • Unreasonable or mistaken inspection.

Although you can unilaterally order that changes be made, there is a commensurate duty on you, to make adjustments in the contract sum or contract time. Hence changes provisions in contract should typically provide methods for making these adjustments.

Changes in contract sum or contract time are made on the basis of negotiations between owner and contractor. The basis can be:

  • Unit prices for specific items of work.
  • Recognised mark-ups for contractor?s work and subcontractor?s work.

Related Discussions:- Change order management

Information for innovation , Information for Innovation  Innovation is...

Information for Innovation  Innovation is based on new ideas, and new combination of old ideas, the utility of which is tested with applications using different kinds of infor

What are planktons, Question 1: (a) What is the chemical composition of...

Question 1: (a) What is the chemical composition of water? (b) Name the 3 states of matter in which water can exist. (c) Explain, with the help of diagrams, the molecular str

Cobol, Write a COBOL program to accept three subject marks and to display t...

Write a COBOL program to accept three subject marks and to display the total of marks and percentage of marks.

Rules of thumb for a competitive negotiation, Rules of thumb for a competit...

Rules of thumb for a competitive negotiation:    Stick to your planned target and walk away points.    You are likely to get a better overall deal if you make a larger nu

Explain the philosophy behind quality management system, Question 1: (a...

Question 1: (a) Explain the basic philosophy behind quality management systems such as those specified in ISO 9000:2000 series. (b) Discuss how an effective quality manageme

Loose assemblage, Loose assemblage is assembling together of two or more of...

Loose assemblage is assembling together of two or more of: subjects (basic or compound) isolate ideas (in one and the same facet, or isolate ideas in one and the same array)

Context setting - value-added information services, Context Setting   '...

Context Setting   'Context setting' implies that the significance and inter-relatedness of individual dataitems be made explicit, and piece of information in the entire scheme

Request for quote , Request for Quote  Request for Quote (RFQ), is a st...

Request for Quote  Request for Quote (RFQ), is a standard business process to invite suppliers into a bidding process to bid on specific products or services through Invitation

Building the team, QUESTION Leadership is essential for the success of ...

QUESTION Leadership is essential for the success of any organization (i) Briefly explain the need for leadership for a manager to be successful (ii) Briefly describe the

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd