Change order management, Other Management

Assignment Help:

Change Order Management

In previous section we learnt that incentives motivate and penalties keep a check for faults that occur in a project. In this section we will understand about a change order management.

A change order is order for work that is added to or deleted from the original  scope  of  work  in  a  contract,  which  alters  the  original  contract amount and/or completion date. A contractor?s claim for such an alteration due to a work perceived by him as additional work remains as a claim until the change order is resolved. A claim is a potential source of dispute. Hence resolution of change order situations knowledgably, fairly and promptly benefits both owner and contractor.

Change  order  is  a  component  of  the  change  management  process  in contract management. The change management process should enable implementation of changes in a system in a controlled manner by following a predefined framework/model. Change order management is hence a critical aspect of any construction job.

The rights of a contractor to a change order arise from the contract. If the contractor?s claim is not consistent with the contract, it will be denied, unless you admit it by oversight.

Project construction contracts always incorporate a Changes clause which provides allows you to order extra work without invalidating the contract or make changes to the existing work by altering, adding to or deducting from the work, with the contract sum.

The reasons this change clause is needed are:

  • Impossibility of perfect drawings and specifications: A fundamental truth in the construction industry is that no design can be made perfect.
  • Impractical risk allocations: The fundamental principle of risk allocation is to assign each risk to the party who is best able to control, manage or absorb that risk, which is the way to achieve maximum efficiency and economy. When contract for construction is taken up by a general contractor, his tendency will be to shift the risks to subcontractors and so on down the line leading to improper risk allocation.
  • Contractor-suggested changes: In many project contracts, value engineering proposals from contractor should be encouraged by owner.
  • Owner-suggested changes: You may discover obstacles or possible efficiencies that require them to deviate from the original plan.

Other than the above reasons, incorrectly estimated work or failure to meet commitments can lead to claims by contractor. Examples are:

  • Unforeseen adverse site conditions or actual site conditions being more adverse than what is mentioned in the contract.
  • Failure to make the site available at the time and in the condition required by the contract.
  • Failure to grant, or delay in granting, legitimate time extensions.
  • Unreasonable or mistaken inspection.

Although you can unilaterally order that changes be made, there is a commensurate duty on you, to make adjustments in the contract sum or contract time. Hence changes provisions in contract should typically provide methods for making these adjustments.

Changes in contract sum or contract time are made on the basis of negotiations between owner and contractor. The basis can be:

  • Unit prices for specific items of work.
  • Recognised mark-ups for contractor?s work and subcontractor?s work.

Related Discussions:- Change order management

Main activities during the construction of the factory, Question 1: Rea...

Question 1: Read the following and answer the questions below. You are the Health and Safety Officer of a big industrial group which is constructing a new factory in which o

Information sources, Information Sources, Resources and Services: The ...

Information Sources, Resources and Services: The term 'Information sources' has two connotations. One is that of the stores or locations in which information kept Therefore, a

Environment and natural resource management, discuss merits and demerits of...

discuss merits and demerits of common property regimes and open access property regimes

Non conventional indexing and filing equipment , Non Conventional Indexing ...

Non Conventional Indexing and Filing Equipment -libraray equipment-libraray management Use of mechanical devices for sorting information recorded on special kinds of cards lik

Types of sampling, TYPES OF SAMPLING: Sampling plans can be  grouped u...

TYPES OF SAMPLING: Sampling plans can be  grouped under two categories-probability  sampling and non-probability sampling. Probability sampling uses a technique by which the r

Information transfer processes, Information Transfer Processes: This s...

Information Transfer Processes: This section is intended to take note of (a) the information transfer process among the users of information on the subject; (b) the informatio

Information demand , Information Demand  Information services are need...

Information Demand  Information services are needed to provide information not only on demand but also in anticipation of its use. Often it will be necessary to repackage the

Facilitating centres/services, Facilitating Centres/Services  Traditio...

Facilitating Centres/Services  Traditionally, only libraries functioned as facilitators, but over a period of time, several other specialized facilitating services have come i

Library equipment in physical planning of library , LIBRARY EQUIPMENT IN PH...

LIBRARY EQUIPMENT IN PHYSICAL PLANNING OF LIBRARY IN LIBRARY MANAGEMENT Most of the equipment used in the library is standard office equipment, sometimes adapted library use.

Factors that influence the level of market interest rate, Question 1 Suppo...

Question 1 Supposing you are the CEO of MS Bank Corporation. Your bank is facing interest rate risk, which has affected its operation significantly. Deliberate the factors that i

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd