Change order management, Other Management

Assignment Help:

Change Order Management

In previous section we learnt that incentives motivate and penalties keep a check for faults that occur in a project. In this section we will understand about a change order management.

A change order is order for work that is added to or deleted from the original  scope  of  work  in  a  contract,  which  alters  the  original  contract amount and/or completion date. A contractor?s claim for such an alteration due to a work perceived by him as additional work remains as a claim until the change order is resolved. A claim is a potential source of dispute. Hence resolution of change order situations knowledgably, fairly and promptly benefits both owner and contractor.

Change  order  is  a  component  of  the  change  management  process  in contract management. The change management process should enable implementation of changes in a system in a controlled manner by following a predefined framework/model. Change order management is hence a critical aspect of any construction job.

The rights of a contractor to a change order arise from the contract. If the contractor?s claim is not consistent with the contract, it will be denied, unless you admit it by oversight.

Project construction contracts always incorporate a Changes clause which provides allows you to order extra work without invalidating the contract or make changes to the existing work by altering, adding to or deducting from the work, with the contract sum.

The reasons this change clause is needed are:

  • Impossibility of perfect drawings and specifications: A fundamental truth in the construction industry is that no design can be made perfect.
  • Impractical risk allocations: The fundamental principle of risk allocation is to assign each risk to the party who is best able to control, manage or absorb that risk, which is the way to achieve maximum efficiency and economy. When contract for construction is taken up by a general contractor, his tendency will be to shift the risks to subcontractors and so on down the line leading to improper risk allocation.
  • Contractor-suggested changes: In many project contracts, value engineering proposals from contractor should be encouraged by owner.
  • Owner-suggested changes: You may discover obstacles or possible efficiencies that require them to deviate from the original plan.

Other than the above reasons, incorrectly estimated work or failure to meet commitments can lead to claims by contractor. Examples are:

  • Unforeseen adverse site conditions or actual site conditions being more adverse than what is mentioned in the contract.
  • Failure to make the site available at the time and in the condition required by the contract.
  • Failure to grant, or delay in granting, legitimate time extensions.
  • Unreasonable or mistaken inspection.

Although you can unilaterally order that changes be made, there is a commensurate duty on you, to make adjustments in the contract sum or contract time. Hence changes provisions in contract should typically provide methods for making these adjustments.

Changes in contract sum or contract time are made on the basis of negotiations between owner and contractor. The basis can be:

  • Unit prices for specific items of work.
  • Recognised mark-ups for contractor?s work and subcontractor?s work.

Related Discussions:- Change order management

Construction procedure , Construction Procedure: Parts of a Questbnnai...

Construction Procedure: Parts of a Questbnnaire or Interview Schedule A  questionnaire or  an  interview  schedule contain the following parts:  a)  Introduction and Instr

Cumulative index work and loose issue shelving work, Cumulative Index Work:...

Cumulative Index Work: As the name suggests, it pertains to noting by entering down the announcement of cumulative index followed by entering  the receipt of cumulative index

Resource sharing library network, Resource Sharing Library Network Res...

Resource Sharing Library Network Resource sharing is the focal point of library networking and cooperation. The tested technological advances in this field have tremendously i

What are the main characteristics of an erp system, Question (a) (i) W...

Question (a) (i) What are the main characteristics of an ERP system? (ii) List FIVE benefits and FIVE disadvantages of implementing an ERP system. (b) Assume you are

Problems of dds and role of internation organisation, PROBLEMS OF DDS AND R...

PROBLEMS OF DDS AND ROLE OF INTERNATION ORGANISATION: Copyright issues, non-availability of publications and restrictions imposed on the storage and delivery of documents elec

Introduction of syringe management, The project ‘Syringe Management Plan' i...

The project ‘Syringe Management Plan' is created to protect the community against misplace of syringe that causes accidental needle injury. This project is introduce as there is no

Visual aids, Visual Aids These are the tools for gaining and sustaining...

Visual Aids These are the tools for gaining and sustaining audience attention when presenting oral representation. Visual aids provide concrete support for your ideas and keep

Subject headings and catalogue entries - coordinating work, Subject Heading...

Subject Headings: The coordinator must ensure correctness and consistency  in the subject headings used. The subject headings for the  document as a whole and for Cross Refer

Basic terminology - library management, BASIC TERMINOLOGY - Library managem...

BASIC TERMINOLOGY - Library management: A term may be defined as a standardised name for a. given entity or concept which is precise. Terminology, in its turn, is defined as a

Stacking systems - library management, STACKING SYSTEMS: The main cons...

STACKING SYSTEMS: The main consideration in stacking is to achieve economy of space while ensuring ease of accessibility for the readers to the contents of the shelves. Space

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd