Change order management, Other Management

Assignment Help:

Change Order Management

In previous section we learnt that incentives motivate and penalties keep a check for faults that occur in a project. In this section we will understand about a change order management.

A change order is order for work that is added to or deleted from the original  scope  of  work  in  a  contract,  which  alters  the  original  contract amount and/or completion date. A contractor?s claim for such an alteration due to a work perceived by him as additional work remains as a claim until the change order is resolved. A claim is a potential source of dispute. Hence resolution of change order situations knowledgably, fairly and promptly benefits both owner and contractor.

Change  order  is  a  component  of  the  change  management  process  in contract management. The change management process should enable implementation of changes in a system in a controlled manner by following a predefined framework/model. Change order management is hence a critical aspect of any construction job.

The rights of a contractor to a change order arise from the contract. If the contractor?s claim is not consistent with the contract, it will be denied, unless you admit it by oversight.

Project construction contracts always incorporate a Changes clause which provides allows you to order extra work without invalidating the contract or make changes to the existing work by altering, adding to or deducting from the work, with the contract sum.

The reasons this change clause is needed are:

  • Impossibility of perfect drawings and specifications: A fundamental truth in the construction industry is that no design can be made perfect.
  • Impractical risk allocations: The fundamental principle of risk allocation is to assign each risk to the party who is best able to control, manage or absorb that risk, which is the way to achieve maximum efficiency and economy. When contract for construction is taken up by a general contractor, his tendency will be to shift the risks to subcontractors and so on down the line leading to improper risk allocation.
  • Contractor-suggested changes: In many project contracts, value engineering proposals from contractor should be encouraged by owner.
  • Owner-suggested changes: You may discover obstacles or possible efficiencies that require them to deviate from the original plan.

Other than the above reasons, incorrectly estimated work or failure to meet commitments can lead to claims by contractor. Examples are:

  • Unforeseen adverse site conditions or actual site conditions being more adverse than what is mentioned in the contract.
  • Failure to make the site available at the time and in the condition required by the contract.
  • Failure to grant, or delay in granting, legitimate time extensions.
  • Unreasonable or mistaken inspection.

Although you can unilaterally order that changes be made, there is a commensurate duty on you, to make adjustments in the contract sum or contract time. Hence changes provisions in contract should typically provide methods for making these adjustments.

Changes in contract sum or contract time are made on the basis of negotiations between owner and contractor. The basis can be:

  • Unit prices for specific items of work.
  • Recognised mark-ups for contractor?s work and subcontractor?s work.

Related Discussions:- Change order management

Sescribe the principles of bureaucratic management, Question 1: (a) Des...

Question 1: (a) Describe the five principles of bureaucratic management put forward by Max Weber. (b) Elaborate on the advantages and disadvantages of bureaucratic manageme

Objectives of resource sharing, Objectives of Resource Sharing   The ob...

Objectives of Resource Sharing   The objectives implied in resource sharing activity are very idealistic in nature. They are mainly aimed at providing convenient access to info

Outline kolb''s learning styles model, QUESTION Read the extract below ...

QUESTION Read the extract below and answer the questions that follow There is general consensus among educators that all learners are not the same. However, a single school

Business Improvement Strategies, Hi there i need help in case study assignm...

Hi there i need help in case study assignment. Thanks

British museum cataloguing rules - library catalogue code, British Museum C...

British Museum Cataloguing Rules: British Museum, Department of Printed Books. Rules for compiling books, maps and music in the British Museum. - Rev. ed. - London: British Mu

Developmental stages of customer acquisition and management, Question: ...

Question: CEOs admit that more money, time, and organisational changes will be required to make the needed transition from product or channel driven structures and tactics to a

Physical processing work - procedures, Physical Processing Work: Cutt...

Physical Processing Work: Cutting : It is often found that books are received with partially uncut sections. If these are left unnoticed, readers may carelessly open up the p

Change order management, Change Order Management In previous section we...

Change Order Management In previous section we learnt that incentives motivate and penalties keep a check for faults that occur in a project. In this section we will understand

Features for the best physical form of library catalogue, FEATURES FOR THE ...

FEATURES FOR THE BEST PHYSICAL FORM OF LIBRARY CATALOGUE: Despite the widespread use of the computer for cataloguing, a great many catalogues in the conventional format, such

Entrepreneurship, #question. I want detailed information about entrepreneur...

#question. I want detailed information about entrepreneurship.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd