Change order management, Other Management

Assignment Help:

Change Order Management

In previous section we learnt that incentives motivate and penalties keep a check for faults that occur in a project. In this section we will understand about a change order management.

A change order is order for work that is added to or deleted from the original  scope  of  work  in  a  contract,  which  alters  the  original  contract amount and/or completion date. A contractor?s claim for such an alteration due to a work perceived by him as additional work remains as a claim until the change order is resolved. A claim is a potential source of dispute. Hence resolution of change order situations knowledgably, fairly and promptly benefits both owner and contractor.

Change  order  is  a  component  of  the  change  management  process  in contract management. The change management process should enable implementation of changes in a system in a controlled manner by following a predefined framework/model. Change order management is hence a critical aspect of any construction job.

The rights of a contractor to a change order arise from the contract. If the contractor?s claim is not consistent with the contract, it will be denied, unless you admit it by oversight.

Project construction contracts always incorporate a Changes clause which provides allows you to order extra work without invalidating the contract or make changes to the existing work by altering, adding to or deducting from the work, with the contract sum.

The reasons this change clause is needed are:

  • Impossibility of perfect drawings and specifications: A fundamental truth in the construction industry is that no design can be made perfect.
  • Impractical risk allocations: The fundamental principle of risk allocation is to assign each risk to the party who is best able to control, manage or absorb that risk, which is the way to achieve maximum efficiency and economy. When contract for construction is taken up by a general contractor, his tendency will be to shift the risks to subcontractors and so on down the line leading to improper risk allocation.
  • Contractor-suggested changes: In many project contracts, value engineering proposals from contractor should be encouraged by owner.
  • Owner-suggested changes: You may discover obstacles or possible efficiencies that require them to deviate from the original plan.

Other than the above reasons, incorrectly estimated work or failure to meet commitments can lead to claims by contractor. Examples are:

  • Unforeseen adverse site conditions or actual site conditions being more adverse than what is mentioned in the contract.
  • Failure to make the site available at the time and in the condition required by the contract.
  • Failure to grant, or delay in granting, legitimate time extensions.
  • Unreasonable or mistaken inspection.

Although you can unilaterally order that changes be made, there is a commensurate duty on you, to make adjustments in the contract sum or contract time. Hence changes provisions in contract should typically provide methods for making these adjustments.

Changes in contract sum or contract time are made on the basis of negotiations between owner and contractor. The basis can be:

  • Unit prices for specific items of work.
  • Recognised mark-ups for contractor?s work and subcontractor?s work.

Related Discussions:- Change order management

Organizational Behaviour, Case let 1 M/s. ABC Ltd is a medium-sized enginee...

Case let 1 M/s. ABC Ltd is a medium-sized engineering company producing a large-range of product lines according to customer requirements. It has earned a good reputation as a quic

Answers Please, Question 1 of 16 4.0 Points Six (6) samples of size five ...

Question 1 of 16 4.0 Points Six (6) samples of size five (5) were used to collect the data presented below: sample number 1 2 3 4 5 6 sample mean (x-bar) 8.0 8.1

Describe the three steps model to change management, Question 1: (a) Th...

Question 1: (a) The planned change model as developed by Bullock and Batten (1985) proposed a four-phased model. Describe the different change phases and change processes asso

Questions and answers while going for a negotiation, Let us review some que...

Let us review some questions that as a negotiator you can face while conducting a negotiation and the considerations to find answers to these questions:  Framing the opening

Explain four different types of organizational structure, QUESTION 1 An...

QUESTION 1 An organization structure is the organization framework by which job tasks are divided grouped and coordinated (a) Explain the four different types of organizatio

Uses of maps and atlases, Uses Maps and atlases are used by common men...

Uses Maps and atlases are used by common men as well as specialists both for work and pleasure. Varied uses of maps and atlases depend on their types. We shall first describe

VALS, HOW DO I WRITE THE VALS

HOW DO I WRITE THE VALS

Maturity model in cobit 5, Maturity model in CobiT 5: CobiT 5 maturity ...

Maturity model in CobiT 5: CobiT 5 maturity model is based on the ISO/IEC 15504. This new model presents some differences (CobiT 5 2012). However, an important similarity betwe

Define some characteristics of technology forecasting, Question 1 Describe...

Question 1 Describe the term technology. Write a short note on progression and growth of technology Question 2 Define some characteristics of technology forecasting. Describe

Controlling risks, Controlling Risks Risk management is not just provid...

Controlling Risks Risk management is not just providing for uncertainties - it is management of risks considering the combination of the probability (extent to which the risk e

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd