Change order management, Other Management

Assignment Help:

Change Order Management

In previous section we learnt that incentives motivate and penalties keep a check for faults that occur in a project. In this section we will understand about a change order management.

A change order is order for work that is added to or deleted from the original  scope  of  work  in  a  contract,  which  alters  the  original  contract amount and/or completion date. A contractor?s claim for such an alteration due to a work perceived by him as additional work remains as a claim until the change order is resolved. A claim is a potential source of dispute. Hence resolution of change order situations knowledgably, fairly and promptly benefits both owner and contractor.

Change  order  is  a  component  of  the  change  management  process  in contract management. The change management process should enable implementation of changes in a system in a controlled manner by following a predefined framework/model. Change order management is hence a critical aspect of any construction job.

The rights of a contractor to a change order arise from the contract. If the contractor?s claim is not consistent with the contract, it will be denied, unless you admit it by oversight.

Project construction contracts always incorporate a Changes clause which provides allows you to order extra work without invalidating the contract or make changes to the existing work by altering, adding to or deducting from the work, with the contract sum.

The reasons this change clause is needed are:

  • Impossibility of perfect drawings and specifications: A fundamental truth in the construction industry is that no design can be made perfect.
  • Impractical risk allocations: The fundamental principle of risk allocation is to assign each risk to the party who is best able to control, manage or absorb that risk, which is the way to achieve maximum efficiency and economy. When contract for construction is taken up by a general contractor, his tendency will be to shift the risks to subcontractors and so on down the line leading to improper risk allocation.
  • Contractor-suggested changes: In many project contracts, value engineering proposals from contractor should be encouraged by owner.
  • Owner-suggested changes: You may discover obstacles or possible efficiencies that require them to deviate from the original plan.

Other than the above reasons, incorrectly estimated work or failure to meet commitments can lead to claims by contractor. Examples are:

  • Unforeseen adverse site conditions or actual site conditions being more adverse than what is mentioned in the contract.
  • Failure to make the site available at the time and in the condition required by the contract.
  • Failure to grant, or delay in granting, legitimate time extensions.
  • Unreasonable or mistaken inspection.

Although you can unilaterally order that changes be made, there is a commensurate duty on you, to make adjustments in the contract sum or contract time. Hence changes provisions in contract should typically provide methods for making these adjustments.

Changes in contract sum or contract time are made on the basis of negotiations between owner and contractor. The basis can be:

  • Unit prices for specific items of work.
  • Recognised mark-ups for contractor?s work and subcontractor?s work.

Related Discussions:- Change order management

Define learning organization, Question 1 What is change management? Explai...

Question 1 What is change management? Explain the importance of change management Question 2 Define Organisational Life Cycle. List and explain the stages in organizational L

Human resources planning development, Plan, design, deliver, and evaluate a...

Plan, design, deliver, and evaluate an original training or HRD development program that you might use in your organization or one that you are very familiar with.

Advantages of machine readable catalogue, Advantages The machine-reada...

Advantages The machine-readable catalogue performs, all the functions of a library catalogue with greater efficiency and speed than any other form. We shall spell out theseadva

Pros and cons of corporate social responsibility, Question : More and m...

Question : More and more hospitality managers are aiming towards sustainability. (a) As a future trend for management of hospitality organizations discuss what particular

Organisation of information services, ORGANISATION OF INFORMATION SERVICES:...

ORGANISATION OF INFORMATION SERVICES: Documentation and information services are activities that grew out of information needs of user communities engaged in research, industr

List 5 factors affecting productivity, QUESTION a) List 5 factors affec...

QUESTION a) List 5 factors affecting productivity b) List 3 factors affecting productivity which are controllable at company's or project level and 2 factors affecting produ

Explain security risk management process, Question: a) Describe why the...

Question: a) Describe why the following security measures are important for e-banking and how are they implemented? (i) Data Confidentiality (ii) Data Integrity (iii) Aud

What is tco (total cost ownership), Question 1 What is TCO (total cost own...

Question 1 What is TCO (total cost ownership)? List the common task in IT system management. Discuss each task in detail Question 2 Explain people process technology appro

Explain the bcg matrix, QUESTION 1 (a) Explain the BCG matrix (b) Yo...

QUESTION 1 (a) Explain the BCG matrix (b) You are required to discuss the limitations of the BCG matrix as a tool/technique used in formulating corporate strategy QUE

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd