Change order management, Other Management

Assignment Help:

Change Order Management

In previous section we learnt that incentives motivate and penalties keep a check for faults that occur in a project. In this section we will understand about a change order management.

A change order is order for work that is added to or deleted from the original  scope  of  work  in  a  contract,  which  alters  the  original  contract amount and/or completion date. A contractor?s claim for such an alteration due to a work perceived by him as additional work remains as a claim until the change order is resolved. A claim is a potential source of dispute. Hence resolution of change order situations knowledgably, fairly and promptly benefits both owner and contractor.

Change  order  is  a  component  of  the  change  management  process  in contract management. The change management process should enable implementation of changes in a system in a controlled manner by following a predefined framework/model. Change order management is hence a critical aspect of any construction job.

The rights of a contractor to a change order arise from the contract. If the contractor?s claim is not consistent with the contract, it will be denied, unless you admit it by oversight.

Project construction contracts always incorporate a Changes clause which provides allows you to order extra work without invalidating the contract or make changes to the existing work by altering, adding to or deducting from the work, with the contract sum.

The reasons this change clause is needed are:

  • Impossibility of perfect drawings and specifications: A fundamental truth in the construction industry is that no design can be made perfect.
  • Impractical risk allocations: The fundamental principle of risk allocation is to assign each risk to the party who is best able to control, manage or absorb that risk, which is the way to achieve maximum efficiency and economy. When contract for construction is taken up by a general contractor, his tendency will be to shift the risks to subcontractors and so on down the line leading to improper risk allocation.
  • Contractor-suggested changes: In many project contracts, value engineering proposals from contractor should be encouraged by owner.
  • Owner-suggested changes: You may discover obstacles or possible efficiencies that require them to deviate from the original plan.

Other than the above reasons, incorrectly estimated work or failure to meet commitments can lead to claims by contractor. Examples are:

  • Unforeseen adverse site conditions or actual site conditions being more adverse than what is mentioned in the contract.
  • Failure to make the site available at the time and in the condition required by the contract.
  • Failure to grant, or delay in granting, legitimate time extensions.
  • Unreasonable or mistaken inspection.

Although you can unilaterally order that changes be made, there is a commensurate duty on you, to make adjustments in the contract sum or contract time. Hence changes provisions in contract should typically provide methods for making these adjustments.

Changes in contract sum or contract time are made on the basis of negotiations between owner and contractor. The basis can be:

  • Unit prices for specific items of work.
  • Recognised mark-ups for contractor?s work and subcontractor?s work.

Related Discussions:- Change order management

Agreement - requirements of resource sharing library network, Agreements ...

Agreements The first agreement, obviously is the agreement to share currently owned materials (that is, to permit access to the holdings among partners), with protocols, limit

Public documentation/information centres, Public documentation/information ...

Public documentation/information centres: Established from public funds, these may not be self- supporting financially. In developing countries, documentation and information

Implementation of enterprise project management, I mplementation of EPM ...

I mplementation of EPM It is not a minor matter to espouse the EPM strategy and implement it in an organisation. A fresh organisational structure and new practices have to be

Change order management, Change Order Management In previous section we...

Change Order Management In previous section we learnt that incentives motivate and penalties keep a check for faults that occur in a project. In this section we will understand

Basic terminology - library management, BASIC TERMINOLOGY - Library managem...

BASIC TERMINOLOGY - Library management: A term may be defined as a standardised name for a. given entity or concept which is precise. Terminology, in its turn, is defined as a

Organizational behavior, what type of errors would you be prone to make whi...

what type of errors would you be prone to make while making these judgement towards goofing employees?

Developing a project management culture, Developing a Project Management Cu...

Developing a Project Management Culture Moving the organisation to embrace a "project management culture" takes time and patience. The initial step an organisation can take is

How do you do this project, managing construction to build 15,000 sq meters...

managing construction to build 15,000 sq meters office you budget is $10 per sq meter timeline is to construct 3,000 sq meters per day you finish 7,000 sq meters of parking lot yo

Location site -preliminary considerations -library building, Location Site ...

Location Site -Preliminary Considerations of Library building-library managment Location is  important for homogeneous  services, site  selection and choice of community,  reg

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd