Change order management, Other Management

Assignment Help:

Change Order Management

In previous section we learnt that incentives motivate and penalties keep a check for faults that occur in a project. In this section we will understand about a change order management.

A change order is order for work that is added to or deleted from the original  scope  of  work  in  a  contract,  which  alters  the  original  contract amount and/or completion date. A contractor?s claim for such an alteration due to a work perceived by him as additional work remains as a claim until the change order is resolved. A claim is a potential source of dispute. Hence resolution of change order situations knowledgably, fairly and promptly benefits both owner and contractor.

Change  order  is  a  component  of  the  change  management  process  in contract management. The change management process should enable implementation of changes in a system in a controlled manner by following a predefined framework/model. Change order management is hence a critical aspect of any construction job.

The rights of a contractor to a change order arise from the contract. If the contractor?s claim is not consistent with the contract, it will be denied, unless you admit it by oversight.

Project construction contracts always incorporate a Changes clause which provides allows you to order extra work without invalidating the contract or make changes to the existing work by altering, adding to or deducting from the work, with the contract sum.

The reasons this change clause is needed are:

  • Impossibility of perfect drawings and specifications: A fundamental truth in the construction industry is that no design can be made perfect.
  • Impractical risk allocations: The fundamental principle of risk allocation is to assign each risk to the party who is best able to control, manage or absorb that risk, which is the way to achieve maximum efficiency and economy. When contract for construction is taken up by a general contractor, his tendency will be to shift the risks to subcontractors and so on down the line leading to improper risk allocation.
  • Contractor-suggested changes: In many project contracts, value engineering proposals from contractor should be encouraged by owner.
  • Owner-suggested changes: You may discover obstacles or possible efficiencies that require them to deviate from the original plan.

Other than the above reasons, incorrectly estimated work or failure to meet commitments can lead to claims by contractor. Examples are:

  • Unforeseen adverse site conditions or actual site conditions being more adverse than what is mentioned in the contract.
  • Failure to make the site available at the time and in the condition required by the contract.
  • Failure to grant, or delay in granting, legitimate time extensions.
  • Unreasonable or mistaken inspection.

Although you can unilaterally order that changes be made, there is a commensurate duty on you, to make adjustments in the contract sum or contract time. Hence changes provisions in contract should typically provide methods for making these adjustments.

Changes in contract sum or contract time are made on the basis of negotiations between owner and contractor. The basis can be:

  • Unit prices for specific items of work.
  • Recognised mark-ups for contractor?s work and subcontractor?s work.

Related Discussions:- Change order management

Binding and preservation work, BINDING AND PRESERVATION WORK: Preserva...

BINDING AND PRESERVATION WORK: Preservation and binding are those aspects of librarianship that have frequently been neglected. It is generally acknowledged that in the presen

Pest framework to analyse the business environment, QUESTION 1 Apply Po...

QUESTION 1 Apply Porter's Five Forces Model to UTM explaining how it can be used by the University to assess the attractiveness of the Tertiary Education Sector QUESTION 2

State and explain the capital asset pricing model, Question 1: (i) S...

Question 1: (i) State and explain the Capital Asset Pricing Model (CAPM). (ii) Discuss the resiliency of the model when the assumptions under which the CAPM is deri

Cataloguing-in-publication, Cataloguing-in-Publication (CIP): Centrali...

Cataloguing-in-Publication (CIP): Centralised cataloguing led to the logical step of publishing bibliographic entries of documents in the publication itself, on the reverse si

Referral centres, Referral Centres: A referral centre is some sort of ...

Referral Centres: A referral centre is some sort of "information desk" for the scientific and technical community which does not provide enquirers directly with the informatio

Library reinforced binding, Library Reinforced Binding: Reinforced bin...

Library Reinforced Binding: Reinforced binding means strengthening the book by adding some material. It could be strengthening of the hinge with cloth or the reinforcing a pal

In project management there are three primary variables, QUESTION In pr...

QUESTION In project management, there are three primary variables: the amount of work to be done; the amount of time available (calendar time, not person-years); and the amount

Need for project quality standards, N eed for project quality standards ...

N eed for project quality standards Project quality standard help the organisation in defining specific measurable objectives. The objective tells if the goals are being met a

Withdrawal - library management, Withdrawal - library management: A bo...

Withdrawal - library management: A book may be withdrawn from collection/from the stock register and shelf list if:  •  it is outdated  •  worn out beyond repair  •

Short-term decision-making problem, A company manufactures and sells a sing...

A company manufactures and sells a single product. The variable cost of the product is Rs 2.50 per unit and all production each month is sold at a price of Rs 3.70 per unit. A pote

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd