#quBloomsday Outfitters produces T-shirts for road races. They need to acquire some new stamping
machines to produce 30,000 good T-shirts per month. Their plant operates 200 hours per month, but
the new machines will be used for T-shirts only 60 percent of the time and the output usually includes
5 percent that are "seconds" and unusable. The stamping operation takes 1 minute per T-shirt, and the
stamping machines are expected to have 90 percent efficiency considering adjustments, changeover of
patterns, and unavoidable downtime. How many stamping machines are required?estion..

Related Discussions:- Case Study

Explain car lots wants to enforce the contract, Wally and Beaver were gener...

Wally and Beaver were general partners in a car dealership. Using the partnership name, Wally entered into a contract to purchase 30 used cars from Car Lots. Car Lots was not aware

Advantages and disadvantages of the parallel sourcing, What are the advanta...

What are the advantages and disadvantages of the parallel sourcing? Advantages of parallel sourcing: Best of both worlds for example, have your cake and eat this too for

Explain what is my alternative hypothesis, In preparing a survey to be admi...

In preparing a survey to be administer to my university peers, it is necessary to tabulate these data once collected. How should the data be tabulated and what statistical methods

Case an American Tragedy: How a Good Company Died?, Do you think that inade...

Do you think that inadequate strategic planning was a factor that resulted in the company''s asking for trade protection?

Make a performance appraisal form for a position, Design a performance appr...

Design a performance appraisal form for a position or targeted job for which you have some first-hand knowledge. First: be clear about the purpose of the assessment process: i.e.,

Explain what was the labor productivity, Natalie Attired runs a small job s...

Natalie Attired runs a small job shop where garments are made. The job shop employees 8 workers. Each work is paid $10 per hour. During the first week of March, each worker worked

Compute demand for a product, Historical demand for a product is:January DE...

Historical demand for a product is:January DEMAND 12 / February DEMAND 11/March DEMAND15/ April DEMAND 12/ May DEMAND 16 /June DEMAND 15 a. Using a weighted moving average with

Determine the appropriate sample size, Determine the Appropriate Sample Siz...

Determine the Appropriate Sample Size The following work sampling data was collected from observing a retail assistant:  Activity

Travel chart, #questionI want some project of travel chart ..

#questionI want some project of travel chart ..

Explain which one minimizes their cost, A swim club is designing a new pool...

A swim club is designing a new pool to replace its old pool. The new pool would need to last for 10 years since the club is planning on relocating after 10 years. A concrete shell

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd