Calculate the Volume of Excavation

Using the information given in Figure, the volume of excavation in yd3 is most nearly:

 

287_Calculate the Volume of Excavation.png

Solution: Use the average end area method:

Volume (yd3) = [(A1 + A2) ÷ (2)] x [(L ÷ 27)]

Volume (yd3) = [725 + 544) ÷ (2)] x [(100 ÷ 27)]

Volume (yd3) = 2,350-yd3


Related Discussions:- Calculate the volume of excavation

Hydrolic, how can i caculate volicity and tank capacity ?

how can i caculate volicity and tank capacity ?

Define the term - permanent load, Define the term - permanent load Wher...

Define the term - permanent load Where the permanent load is less than or equal to 25% of the design imposed load, deflections may be calculated using any elastic method. When

Cost of utilities and taxes, The cost of utilities, taxes and maintenance o...

The cost of utilities, taxes and maintenance on a home is $3,000 per year.  The amount of money that would have to be invested now at 8% to cover these expenses for the next 5 year

Explain terzaghi theory of bearing capacity, a) Explain Terzaghi's theory o...

a) Explain Terzaghi's theory of bearing capacity of shallow strip foundations. Determine the three bearing capacity factors and give their values for  Φ  = 0' case. (b) Descreib

Simple stresses and strains, Simple stresses and strains: In this simp...

Simple stresses and strains: In this simple stresses and strains you have learnt the concepts of stress, strain, elastic modulus and the primary concepts in application to ana

Indirect tensile strength in water-retaining structures, Q. Indirect tensil...

Q. Indirect tensile strength in water-retaining structures ? Crack width formation is dependent on the early tensile strength of concrete. Principle of critical steel ratio als

Road materials, Road Materials Earthwork and pavements constitute a si...

Road Materials Earthwork and pavements constitute a significant part of the cost of a road. Hence it is desirable that thorough investigations be done about the availability o

Geotechnical Design, I need this to be done perfectly . It is a civil engin...

I need this to be done perfectly . It is a civil engineering assignment. Please let me know if you can solve this perfectly within no more than 40 hours. Thanks.

Abrasion test - tests on stones, Abrasion Test:   This test is carri...

Abrasion Test:   This test is carried out on stones used as aggregates for road construction. The test result shows the suitability of stones against   the grinding action u

Describe about the prestressed concrete, Describe about the Prestressed con...

Describe about the Prestressed concrete Civil engineering structures, such as buildings, bridges, dams, towers etc. and their structural components such as beams, columns, slab

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd