Calculate the total labor cost per cubic yard, Civil Engineering

Assignment Help:

A contractor will place 90-cubic yards of concrete for a housekeeping pad on the rooftop of a 36-ft tall building. Site conditions dictate that the safest and best method of placement is to use a crane and a 2-cubic-yard bucket. To perform the task efficiently, five Union laborers are needed - one at the concrete truck, three at the point of placement, and one on the portable internal vibrator. The wage rate for laborers is $22.00/hr (Union overtime rate is 1.5 times the wage rate after 8-hour day). Time needed for the operation is: Setup: 15-min; Cycle time consists of Load = 3-min., plus Swing, dump and return = 6-min. which allows a total cycle time = 9-min; Demobilize operation, 10-min. Supervision is done by the superintendent. Allow a 10% factor for inefficiencies during the cycle time. Crane rental cost is $1,800 per 8-hr day. The total labor cost per cubic yard for the concrete crane placement of the 90 cubic yards is most nearly:

Solution:

Identify (by underlining) relevant cost items and calculate summary quantities.

No. of cycles 90-CY/2-CY/Bucket = 45 cycles

Total cycle time 45-cycles x 9-min/cycle = 405 min

Inefficiency(labor,delays,etc.)10%of cycle time = 41-min

Setup and demobilize: Sub-total = 25 min

Total operation time: 405 + 41 + 25 = 471-min or 7.85-hrs

Amount of time needed (adjusted to workday) = 8 hr Laborers - five for 8 hours at $22.00/hr = $880.00

Total labor cost per 90-yd3 = $880.00

Cost per cubic yard $880/90-yd3 = $9.78/yd3


Related Discussions:- Calculate the total labor cost per cubic yard

Report, report on lintels and arches

report on lintels and arches

Determine the water-cement ratio, A concrete batch plant provided the Desig...

A concrete batch plant provided the Design Strength for the engineer's mix design to match the project's specification requirement for a 4000 psi Tremie pump mix.  The Water-cement

Process of lubrication of girder bearing, Q. Process of Lubrication of Gird...

Q. Process of Lubrication of Girder Bearing? Oiling and greasing of bearings is done to ensure that the bearings are well lubricated and working freely to permit expansion and

Dissimilarity b/w air chamber and surge tank, Question What is dissimil...

Question What is dissimilarity between air chamber and surge tank ? Answer Air chambers and surge tanks are usually set up in watermain to ease stress on schem

R.c.c square overhead tank, problems in estimating especially in reinforcem...

problems in estimating especially in reinforcement works

Concrete mix design, Concrete Mix Design: Concrete mix design is done...

Concrete Mix Design: Concrete mix design is done in a laboratory to achieve the desired strength and workability. The mix design is done to achieve strength slightly higher t

KNIFE EDGE LOADING, How does the knife edge load simulate the existing cond...

How does the knife edge load simulate the existing condition of the bridge structure?

What to do to improve the reliability of the test results, Explain clearly ...

Explain clearly with a neat sketch how you will verify the coefficient of permeability of a clay sample in the laboratory and derive the expression used to compute the permeability

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd