Calculate the total labor cost per cubic yard, Civil Engineering

Assignment Help:

A contractor will place 90-cubic yards of concrete for a housekeeping pad on the rooftop of a 36-ft tall building. Site conditions dictate that the safest and best method of placement is to use a crane and a 2-cubic-yard bucket. To perform the task efficiently, five Union laborers are needed - one at the concrete truck, three at the point of placement, and one on the portable internal vibrator. The wage rate for laborers is $22.00/hr (Union overtime rate is 1.5 times the wage rate after 8-hour day). Time needed for the operation is: Setup: 15-min; Cycle time consists of Load = 3-min., plus Swing, dump and return = 6-min. which allows a total cycle time = 9-min; Demobilize operation, 10-min. Supervision is done by the superintendent. Allow a 10% factor for inefficiencies during the cycle time. Crane rental cost is $1,800 per 8-hr day. The total labor cost per cubic yard for the concrete crane placement of the 90 cubic yards is most nearly:

Solution:

Identify (by underlining) relevant cost items and calculate summary quantities.

No. of cycles 90-CY/2-CY/Bucket = 45 cycles

Total cycle time 45-cycles x 9-min/cycle = 405 min

Inefficiency(labor,delays,etc.)10%of cycle time = 41-min

Setup and demobilize: Sub-total = 25 min

Total operation time: 405 + 41 + 25 = 471-min or 7.85-hrs

Amount of time needed (adjusted to workday) = 8 hr Laborers - five for 8 hours at $22.00/hr = $880.00

Total labor cost per 90-yd3 = $880.00

Cost per cubic yard $880/90-yd3 = $9.78/yd3


Related Discussions:- Calculate the total labor cost per cubic yard

Fluid mechanism, tell me something about velocity profile?

tell me something about velocity profile?

Investigation scour for underwater inspection of bridge, Define Investigati...

Define Investigation Scour for Underwater Inspection of Bridge? Investigation Scour is probably the most critical item to be aware of when performing an underwater inspection o

Varigon theorem, Ask questio #Minimum 100 words accepted# what is varigon ...

Ask questio #Minimum 100 words accepted# what is varigon theorem and what are their application ? its examples

Paint, different types of paints?

different types of paints?

Water tretement, define scale and sludge and mention the scale and sludge f...

define scale and sludge and mention the scale and sludge forming substance and explain the prevention methods

Define the arrow diagramming method, Define the Arrow Diagramming Method ...

Define the Arrow Diagramming Method Activity-on-Arrow (Branch) with nodes as dependencies Uses finish-to-start precedence only. The solution method for an activity on

Estimation of loading carrying capacity, Question While designing mini...

Question While designing mini-piles , should strength of grout be disused during estimation of loading carrying capacity? Answer While designing min-piles, there will

Survey, how can I use reciprocal type of leveng method to level a ground, a...

how can I use reciprocal type of leveng method to level a ground, and a procedure

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd