Calculate the total labor cost per cubic yard, Civil Engineering

Assignment Help:

A contractor will place 90-cubic yards of concrete for a housekeeping pad on the rooftop of a 36-ft tall building. Site conditions dictate that the safest and best method of placement is to use a crane and a 2-cubic-yard bucket. To perform the task efficiently, five Union laborers are needed - one at the concrete truck, three at the point of placement, and one on the portable internal vibrator. The wage rate for laborers is $22.00/hr (Union overtime rate is 1.5 times the wage rate after 8-hour day). Time needed for the operation is: Setup: 15-min; Cycle time consists of Load = 3-min., plus Swing, dump and return = 6-min. which allows a total cycle time = 9-min; Demobilize operation, 10-min. Supervision is done by the superintendent. Allow a 10% factor for inefficiencies during the cycle time. Crane rental cost is $1,800 per 8-hr day. The total labor cost per cubic yard for the concrete crane placement of the 90 cubic yards is most nearly:

Solution:

Identify (by underlining) relevant cost items and calculate summary quantities.

No. of cycles 90-CY/2-CY/Bucket = 45 cycles

Total cycle time 45-cycles x 9-min/cycle = 405 min

Inefficiency(labor,delays,etc.)10%of cycle time = 41-min

Setup and demobilize: Sub-total = 25 min

Total operation time: 405 + 41 + 25 = 471-min or 7.85-hrs

Amount of time needed (adjusted to workday) = 8 hr Laborers - five for 8 hours at $22.00/hr = $880.00

Total labor cost per 90-yd3 = $880.00

Cost per cubic yard $880/90-yd3 = $9.78/yd3


Related Discussions:- Calculate the total labor cost per cubic yard

Masonry, Sketches for English bond, Stretcher bond, Header bond, Flemish bo...

Sketches for English bond, Stretcher bond, Header bond, Flemish bond in first & second layer plan, elevation and 3 dimensional view of brick bond.

Determine the expected extension at the jack, A cylindrical concrete tank,...

A cylindrical concrete tank, 30 m external diameter, is to be prestressed circumferentially by means of  high-strength steel wire (E, = 2 x  10 5   N/mm 2 )  jacked  at 4 points, 9

Explain term - losses of prestress, Explain term - losses of prestress ...

Explain term - losses of prestress We know that with time, tendons lose some of their initial prestress (at the time of transfer of prestress). This is termed as 'losses of pre

Maintenance of steel bearings, Q. Maintenance of steel bearings? Cleani...

Q. Maintenance of steel bearings? Cleaning and greasing of bearings is one of the important maintenance works to avoid premature failure of bearings and reduce recurring heavy

Determining the amount of pre-camber, 1. Domes - You are a construction man...

1. Domes - You are a construction manager in the UAE in charge of a project that involves constructing domes.  Discuss briefly, giving examples, a range of different types of dome

Survying, what aare the parts and function of steel tape ?

what aare the parts and function of steel tape ?

Explain the shrink factor of soil, Explain the Shrink Factor of Soil In...

Explain the Shrink Factor of Soil In addition to the swell factor and its associated load factor, soil also has a shrink factor. While the first two relate the volume of an equ

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd