Calculate the total labor cost per cubic yard, Civil Engineering

Assignment Help:

A contractor will place 90-cubic yards of concrete for a housekeeping pad on the rooftop of a 36-ft tall building. Site conditions dictate that the safest and best method of placement is to use a crane and a 2-cubic-yard bucket. To perform the task efficiently, five Union laborers are needed - one at the concrete truck, three at the point of placement, and one on the portable internal vibrator. The wage rate for laborers is $22.00/hr (Union overtime rate is 1.5 times the wage rate after 8-hour day). Time needed for the operation is: Setup: 15-min; Cycle time consists of Load = 3-min., plus Swing, dump and return = 6-min. which allows a total cycle time = 9-min; Demobilize operation, 10-min. Supervision is done by the superintendent. Allow a 10% factor for inefficiencies during the cycle time. Crane rental cost is $1,800 per 8-hr day. The total labor cost per cubic yard for the concrete crane placement of the 90 cubic yards is most nearly:

Solution:

Identify (by underlining) relevant cost items and calculate summary quantities.

No. of cycles 90-CY/2-CY/Bucket = 45 cycles

Total cycle time 45-cycles x 9-min/cycle = 405 min

Inefficiency(labor,delays,etc.)10%of cycle time = 41-min

Setup and demobilize: Sub-total = 25 min

Total operation time: 405 + 41 + 25 = 471-min or 7.85-hrs

Amount of time needed (adjusted to workday) = 8 hr Laborers - five for 8 hours at $22.00/hr = $880.00

Total labor cost per 90-yd3 = $880.00

Cost per cubic yard $880/90-yd3 = $9.78/yd3


Related Discussions:- Calculate the total labor cost per cubic yard

Material engineering assignment, select three materials metal and non meala...

select three materials metal and non mealat at least one of the selected materials shold change its property

Determine about the prestressed concrete, Determine about the Prestressed c...

Determine about the Prestressed concrete Prestressed concrete is a special type of concrete in which internal stresses of a suitable nature, magnitude and distribution are int

Concrete technology, chemical compositions of Rapid Hardening Cement

chemical compositions of Rapid Hardening Cement

State the coulomb wedge theory, A retaining wall is battered away from the ...

A retaining wall is battered away from the fill from bottom to top at an angle of 15° with the vertical. Height of the wall is 6 m. The fill slopes upwards at an angle 15° away fro

Single flemish bond, advantages and disadvantages in single flemish bond

advantages and disadvantages in single flemish bond

What is the sludge volume index, What is the Sludge Volume Index? Two 1...

What is the Sludge Volume Index? Two 1 L samples of mixed liquor are taken from a lagoon. After settling for 30 min in a graduated cylinder, 250 mL of solids have settled out i

Upper floor, We need all types of Upper floor

We need all types of Upper floor

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd