Calculate the total labor cost per cubic yard, Civil Engineering

Assignment Help:

A contractor will place 90-cubic yards of concrete for a housekeeping pad on the rooftop of a 36-ft tall building. Site conditions dictate that the safest and best method of placement is to use a crane and a 2-cubic-yard bucket. To perform the task efficiently, five Union laborers are needed - one at the concrete truck, three at the point of placement, and one on the portable internal vibrator. The wage rate for laborers is $22.00/hr (Union overtime rate is 1.5 times the wage rate after 8-hour day). Time needed for the operation is: Setup: 15-min; Cycle time consists of Load = 3-min., plus Swing, dump and return = 6-min. which allows a total cycle time = 9-min; Demobilize operation, 10-min. Supervision is done by the superintendent. Allow a 10% factor for inefficiencies during the cycle time. Crane rental cost is $1,800 per 8-hr day. The total labor cost per cubic yard for the concrete crane placement of the 90 cubic yards is most nearly:

Solution:

Identify (by underlining) relevant cost items and calculate summary quantities.

No. of cycles 90-CY/2-CY/Bucket = 45 cycles

Total cycle time 45-cycles x 9-min/cycle = 405 min

Inefficiency(labor,delays,etc.)10%of cycle time = 41-min

Setup and demobilize: Sub-total = 25 min

Total operation time: 405 + 41 + 25 = 471-min or 7.85-hrs

Amount of time needed (adjusted to workday) = 8 hr Laborers - five for 8 hours at $22.00/hr = $880.00

Total labor cost per 90-yd3 = $880.00

Cost per cubic yard $880/90-yd3 = $9.78/yd3


Related Discussions:- Calculate the total labor cost per cubic yard

Estimate the activity durations - construction management, Estimate the Act...

Estimate the Activity Durations The total labor cost for emergency bridge rehabilitation on an interstate highway is $5,716,440.  The average crew-hour cost is $15,879 for this

Design a 10 unit rapid sand filter system, Design a 10 unit rapid sand filt...

Design a 10 unit rapid sand filter system for a flow of 6.3 MGD with a filtration rate of 2 gpm/sq ft. and an L: W ratio of 1.3.   Design flow (Q) = 6.3 MGD = 6.3x106 gpd =

What is objective method of assessment, Q. What is objective method of asse...

Q. What is objective method of assessment? Track recording consists of objective method of assessment of the quality of track with the help of sophisticated equipments. A conti

Define resultant force on a given area of a horizontal plane, Resultant For...

Resultant Force on a Given Area of a Horizontal Plane By equation, the total vertical force applied to an area A on the plane is: Resultant Force R = ΡA = (lb/ft 2 )(ft 2 )

Dressing of stones.., what is dressing of stones and its various types

what is dressing of stones and its various types

Soil compaction, Soil Compaction: Soils used in road construction nee...

Soil Compaction: Soils used in road construction need to be thoroughly rolled and compacted. Compaction of soil is needed for the following reasons. (a) A well compacted s

Design the 2-span continuous center, Design the 2-span continuous center T-...

Design the 2-span continuous center T-beam, B2, for the floor syetem shown below. The girders that the beam frames into are all 24" wide. Using fc'= 5 ksi, and fy = 60 ksi. The ser

Soil mechanics, Hi, i really need help to done my assignment i have done so...

Hi, i really need help to done my assignment i have done some part but in that case i need professional advice to finish my task. could you please let me know if you can help me. t

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd