Calculate the Total Area (acre) for Lot

A 30-ft wide parabolic shaped stream divides the property as shown.  The total area (acre) for Lot 6 is most nearly:

1384_Calculate the Total Area (acre) for Lot 1.png

Solution:  The Area for a parabola is provides.  

The total Area for Lot 6 is:

A = 2 (1000) (750) ÷ 3 = 500,000-ft2

500,000-ft2 ÷ 43,560-ft2/Ac = 11.48-Ac  

The total Area for Lot 7 is:

A = (1050) (800) ÷ 3 = 280,000-f2

280,000-ft2 ÷ 43,560-ft2/Ac = 6.43-Ac

1667_Calculate the Total Area (acre) for Lot 2.png


Related Discussions:- Calculate the total area (acre) for lot

Determine the diameter of the footing, A circular footing is resting on a s...

A circular footing is resting on a stiff saturated clay with qu = 250 kN/m 2 . The depth of foundation is 2 m. Verify the diameter of the footing if the column load is 600 kN. S

Use scattered lighting for underwater inspection of bridge, Define Use of s...

Define Use of scattered lighting for Underwater inspection of Bridge In this arrangement, a very high powered, tight beam spot light (beam angle less than 10°) is used. The lam

Pavement width - geometric design of roads, Pavement Width: The pavem...

Pavement Width: The pavement widths commonly adopted are : Single lane                 :           3.75 m Intermediate lane     :           5.5 m Two lane

Surveying, how to make plain scale

how to make plain scale

What is ceramic mosaic and chequered cement tiles, Q. What is Ceramic mosai...

Q. What is Ceramic mosaic and Chequered Cement tiles? Chequered Mosaic tiles - Repairs to steps of F O Bs should be done only with Chequered Mosaic tiles. Ceramic m

Survey, how to draw longitudinal profile

how to draw longitudinal profile

Determine the example of tendon splices, Determine the example of tendon s...

Determine the example of tendon splices Following are some examples of  tendon splices. (a) Torpedo splice (b) Clamp splice (c)  Screw connectors

Consolidated undrained or consolidated drained analysis, Question In de...

Question In determining effectual stress parameters of a soil sample, which test is good, consolidated undrained analysis or consolidated drained analysis? Answer Effec

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd