Calculate the deposited amount - construction management, Civil Engineering

Assignment Help:

An engineer deposits an "X" amount every 6 months for 3 years so that she'll have $10,000 at the end of this period. The interest rate is 5% per year which is rebalanced every 6-month.  The amount deposited is most nearly:

Solution:  Determine the components and apply the equation:

n = 6 deposits     i = 2.5% per 6-month period 

F = $10,000(A/F, 2.5%, 6) = 0.15655 A = $1,565.50


Related Discussions:- Calculate the deposited amount - construction management

..zero energy building, this is our final year project .please help me to g...

this is our final year project .please help me to guide about it

Grouting in segmental linings in tunnels, Q. Grouting in segmental linings ...

Q. Grouting in segmental linings in tunnels? Grouting is typically carried out under pressure in segmental linings at the time of tunnel construction due to the below reasons:

Geological classification of stones, Geological Classification Based on...

Geological Classification Based on their beginning of formation stones are classified into 3 main groups-Igneous, sedimentary and metamorphic rocks. Igneous Rocks: Thes

Earth fill dams, Ask question #Minimum 100E. The regulations and specificat...

Ask question #Minimum 100E. The regulations and specifications that followed for compaction works for earth dam in Oman words accepted#

Explain working of ultrasonic system for concrete elements, Explain the wor...

Explain the working of Ultrasonic System for Concrete Elements? Ultrasonic methods can be used underwater for overall assessment of the strength of concrete based on sound velo

Comparison of pre and post-tensioning, Comparison of pre and post-tensionin...

Comparison of pre and post-tensioning A comparison between pre-tensioned and post-tensioned concrete members can be made on the basis of the following considerations. (a) T

Inspection of girder bridge, Q. As an AEN in charge, what inspection will...

Q. As an AEN in charge, what inspection will you under taken at the time of inspection of Girder Bridge 3 x 60 feet. Please explain the important items to be o

Street originate in the plumbing term street ell, How did street originate ...

How did street originate in the plumbing term street ell? Ans) A "street ell" may have gotten its name due to it describes a 90° fitting particularly useful in tight, street dit

Radial contour, how to calculate distance for radial contour

how to calculate distance for radial contour

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd