Calculate benefit cost ratio for government project, Civil Engineering

Assignment Help:

Calculate the Benefit-Cost Ratio for Municipal Government Project

With interest at 10%, the benefit-cost ratio for this municipal government project is most nearly:

  Initial cost                                                                          $200,000

  Additional costs at end of years 1 & 2                                 $30,000/yr

  Benefits at end of years 1 & 2                                            $0

  Annual benefits from year's 3 to 10                                     $90,000/yr

Solution:

PW Cost   = $200,000 + $30,000 (P/A, 10%, 2)

    = $200,000 + $30,000 (1.736)

    = $252,080

486_Calculate Benefit Cost Ratio for Government Project.png

PW Benefits = $90,000 (P/A, 10%, 8) (P/F, 10%, 2)     

    = $90,000 (5.335) (0.8264)     

    = $396,800

B/C = $396,800/$252,080 = 1.574


Related Discussions:- Calculate benefit cost ratio for government project

Define the combustion of solid waste, Define the Combustion of Solid Waste?...

Define the Combustion of Solid Waste? A chemical reaction in which the elements in fuel oxidize in presence of excess oxygen C → CO 2 , H → H 2 O, S   → SO x , N → NO x

Lagrange''s mean value theorem, Write some appplications of lagrange''s mea...

Write some appplications of lagrange''s mean value thorem

Test on specially moulded test piece, Test on specially moulded test piece ...

Test on specially moulded test piece The test piece shall be moulded by the manufacturer with identical compound and under identical vulcanizing conditions as used in manufact

Write short notes on numerical rating of bridges, Q. Write short notes on N...

Q. Write short notes on Numerical rating of Bridges? In the numerical rating system, the condition of a bridge is represented by a number consisting eight digits. This eight di

Civil engineering drawing, Explain step by step procedure involved in the a...

Explain step by step procedure involved in the analysis and design of balanced cantilever bridge.

BUILDING CONSTRUCTION, GIVE IN DETAIL THE TREATMENT OF TOP SURFACE OF EARTH...

GIVE IN DETAIL THE TREATMENT OF TOP SURFACE OF EARTH FILLING..

Calculate the initial height of the stockpile, On a 5-acre level terrain bu...

On a 5-acre level terrain building site, an earthwork contractor has instructed her crew to strip and grub the topsoil of a 60,000-ft 2 proposed building pad to a minus 2-ft sub-g

Earth work in high embankments, Q. Earth work in high embankments? (a) ...

Q. Earth work in high embankments? (a) Borrow pits must not be dug close to telegraph poles, electric poles, level crossings, bridges a culverts, or within 800 meters of the bo

State the laws governing compaction of cohesion less soils, a) What are th...

a) What are the laws governing compaction of (i) cohesion less soils like sand and (ii) moderately cohesive soils like sandy clay ? b) To what compaction pressure does the

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd