If n a number of codes, they boundary ratio of weight of hammer to weight of pile for pile driving. What will be the key reason for this?
Answer
As a hammer with first motion collides with a stationary pile, transfer of energy is mainly efficient when two masses are analogous. That is cause why some codes limit ratio of weight of hammer to weight of pile to be additional than 0.5. If weight of hammer is besides low, as a rule of energy during hammer driving is distributed to hammer and this grounds tension induced in hammer and marks in unproductive transfer of energy.
systems approach to diagnose and solve the chronic water crisis in the city.
Q. What is Imp rest Stores? Material obtained not for specific works but as a standing advance for the purpose of material urgent requirements as and when they arise should wit
I want to know the necessary material list during replacement of Expansion Joint
Question In a concrete compression test , usually 150mmx150mmx150mm concrete cube examples are used for testing. Why isn't 100mmx100mmx100mm concrete cube samples used in test in
built in truss
In reclamation involving large volumes of fill and tight programme, shall engineers use marine fill or mud extracted from land borrow area as filling material? There are two
Q. Explain Gap Survey and adjustment of Gap? Gap survey and rectification of gaps is to be carried out, in stretches where track develops excessive creep jammed joints, sun kin
what is the trignomerty leveling
Q. Method of observation by satellite? The difference between a photographs and imageries needs to be understood first. A photograph covers a specific area within its view and
Explain the "Standard Penetration Test" used in soil exploration. List the information that can be obtained by the test when made in (a) clay, (b) sand. Comment on the correctio
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd