Question

If n a number of codes, they boundary ratio of weight of hammer to weight of pile for pile driving. What will be the key reason for this?


Answer

As a hammer with first motion collides with a stationary pile, transfer of energy is mainly efficient when two masses are analogous. That is cause why some codes limit ratio of weight of hammer to weight of pile to be additional than 0.5. If weight of hammer is besides low, as a rule of energy during hammer driving is distributed to hammer and this grounds tension induced in hammer and marks in unproductive transfer of energy.

 


Related Discussions:- Boundary ratio of weight of hammer to weight of pile

Durability requirements for concrete, Durability requirements for Concrete ...

Durability requirements for Concrete Even though the alkaline environment of concrete protects steel, carbonation of hydrated cement may decrease the effective protection. The

Explain the coefficient of permeability, A sand deposit of 12 m thick overl...

A sand deposit of 12 m thick overlies a clay layer. The water table is 3 m below the ground surface. In a field permeability pump-out test, the water is pumped out at a rate of 540

Define the hazardous waste, Define the Hazardous Waste 1. Any waste or ...

Define the Hazardous Waste 1. Any waste or combination of waste that poses a substantial danger now or future to humans, plants, and animals without special precautions. 2.

Explain template jig, Explain Template Jig? 1) Template jig is the simp...

Explain Template Jig? 1) Template jig is the simplest type of jig, employed for accuracy than speed. 2) This jig fits over, on, or, into the work and is not generally clampe

Project management, planking and strutting for shallow excavation

planking and strutting for shallow excavation

Parabola, how to draw a parabola

how to draw a parabola

Stone soling - road pavements, Stone Soling: One of the early practic...

Stone Soling: One of the early practices in road construction was to provide a stone soling 150-225 mm in thickness. The stones are laid by manual labour, and stone spalls ar

Settlement due to deterioration, Q. Settlement due to Deterioration? Th...

Q. Settlement due to Deterioration? The deterioration of foundation concrete will result in the vicinity of sulphates, chlorides and chemically contaminated soils. Due to deter

Necessity of pile tip cover for rock-socketed H-piles, Q. Necessity of pile...

Q. Necessity of pile tip cover for rock-socketed H-piles? In current practice concrete cover is generally provided at the pile tips of pre-bored H-piles socketed in rock. The o

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd