Base of concrete retaining walls, Civil Engineering

Assignment Help:

Q. Granular fill or rock fill essential at the base of concrete retaining walls?

It isn't uncommon that rock fill layers and granular fill layers are placed beneath the bottom of concrete retaining walls. Purpose of such provision is to spread the loading in view of insufficient bearing capacity of foundation material to maintain the loads of retaining walls.

Upon placing of rockfill layers and granular fill layers, same imposed loads are supported by a larger area of founding material and therefore stress exerted by loads is decreased accordingly.

Layers of rockfill and granular fill materials aren't standard details of concrete retaining wall. If we are fully satisfied that founding material could support the loads arising from retaining walls, it isn't essential to provide these layers of rockfill and granular fill materials.


Related Discussions:- Base of concrete retaining walls

Fluid mechanism, tell me something about velocity profile?

tell me something about velocity profile?

Compass surveying, Compass Surveying: You have studied about the compa...

Compass Surveying: You have studied about the compass and its use for bearings of measuring survey lines. The angular measurements are carried out with prismatic compass that

What is multiple-cell box girder, Q. What is Multiple-cell box girder? ...

Q. What is Multiple-cell box girder? Multiple-cell box girder: cells connected by top flanges vs. cells connected both by top and bottom flanges When the depth of a box gi

Syphon, what is the design of syphon

what is the design of syphon

SHEARING STRESS IN CIRCULAR SECTION, SHEAR STRESS DISTRIBUTION INTO CIRCULA...

SHEAR STRESS DISTRIBUTION INTO CIRCULAR SECTION DERIVATION

Compute the maximum allowable concentrated live load, Given for the section...

Given for the section shown in Figure, M * = 250 kNm, f sy = 500 MPa and f c ′ = 25 MPa. Compute A st and (if necessary) A sc . You may assume that eac

Hydraulics, A tank with vertical sides contain 3m of water in the bottom, o...

A tank with vertical sides contain 3m of water in the bottom, overlain by 4m of oil with no intermixing. Draw pressure diagram due to the oil and water on one of the tank sides and

Calculate the amount of cubic yards of soil, A proposed building site requi...

A proposed building site requires 135,000-ft 3 of imported fill.  A borrow site is located 5-miles Northeast of the project site where the soil has a shrinkage of 16%.  The amount

Air pollution, chlorosis in plants is caused by

chlorosis in plants is caused by

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd