Concrete compaction in piling works, Civil Engineering

Assignment Help:

Question

What is the reason that vibrators not used in concrete compaction in piling works?


Answer

Concrete for piles must be a high-slump self-compacting mix that is capable of flowing between reinforcement cages with simplicity. As concrete is designed to be self-compacting, vibrators are not used for given that additional compaction. Furthermore, concrete in piles is compacted by power derived from free falling. Though, if vibrators are used, vibrated concrete can be compacted to sides of concrete casings and hinders lifting up of casings.

 


Related Discussions:- Concrete compaction in piling works

Shear moment diagram, how to draw shear moment diagram for cantileaver beam...

how to draw shear moment diagram for cantileaver beam

Bridge engineering, long span bridge or continuous bridge which is more pre...

long span bridge or continuous bridge which is more preferable and why ??? what is the major problem in continuous bridge and what would be its effect if there is any differential

Steel report, Are you capable to do me 6 pages steel report in 48 H ?

Are you capable to do me 6 pages steel report in 48 H ?

., WHAT IS PILE CORROSION

WHAT IS PILE CORROSION

Find the maximum stress, Find the maximum stress: A circular bar rigid...

Find the maximum stress: A circular bar rigidly fixed at both ends is 1 m long and tapers uniformly from 20 cm diameter at one end to 10 cm diameter at the other end. Find the

Define underwater magnetic particle testing, Define Underwater Magnetic Par...

Define Underwater Magnetic Particle Testing? Underwater magnetic particle testing (UWMT) is a non-destructive testing suited for detection of surface cracks or discontinuities

BRIDGES, WHAT ARE THE DIFFERENT TYPES OF BRIDGES

WHAT ARE THE DIFFERENT TYPES OF BRIDGES

Explain the installation of shock transmission unit, Explain the Installati...

Explain the Installation of Shock Transmission Unit? It is not always necessary to install STUs while a structure is under construction but the holding down anchor bolts and th

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd