Concrete compaction in piling works, Civil Engineering

Assignment Help:

Question

What is the reason that vibrators not used in concrete compaction in piling works?


Answer

Concrete for piles must be a high-slump self-compacting mix that is capable of flowing between reinforcement cages with simplicity. As concrete is designed to be self-compacting, vibrators are not used for given that additional compaction. Furthermore, concrete in piles is compacted by power derived from free falling. Though, if vibrators are used, vibrated concrete can be compacted to sides of concrete casings and hinders lifting up of casings.

 


Related Discussions:- Concrete compaction in piling works

Explain the aashto classification system, Explain the AASHTO Classification...

Explain the AASHTO Classification System   1.  Identify the percent passing the No.10, No. 40, and No. 200 sieves. Identify the LL and PI of the fraction passing the No. 40 sie

Determine the magnitude of application of the active thrust, A retaining wa...

A retaining wall 9 m high retains cohesion less soil, with an angle of internal friction 33°. The surface is level with the top of the wall. The unit weight of the top 3 m of the f

Survying, what aare the parts and function of steel tape ?

what aare the parts and function of steel tape ?

Piling wall, explain about forces acting on a piling wall

explain about forces acting on a piling wall

Impact of possible energy, a) Take into consideration the boiler efficiency...

a) Take into consideration the boiler efficiency, and verify the cost of heating the building, during the heating season, using present oil and gas prices.  b) Investigate the i

Problems in turbid water - underwater inspection of bridge, Define Problems...

Define Problems in turbid water - underwater inspection of bridge? There are three main problems, which limit the viewing performance of an underwater camera. These are: -

Soil in road construction, Soil in Road Construction: Road Embankme...

Soil in Road Construction: Road Embankment and Sub-grade Soil is mainly used as the material for constructing a road embankment. The road embankment supports the road

Explain the equalization basins - hydraulic system, Equalization Basins - H...

Equalization Basins - Hydraulic System For influent flow to publicly owned treatment works (POTWs), flow rates may be excessive for short or long durations, especially in combi

Define advantages and disadvantage black & white fathometer, Define Advanta...

Define Advantages and disadvantages Black & White Fathometer? Advantages of the black & white Fathometer are: - Inexpensive - Effective Disadvantages include the follo

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd