Airport lighting, Civil Engineering

Assignment Help:

Airport Lighting:

Lighting of Approach to Runway

A good system of identification of the runway when landing is to provide six transverse cross-bars of lights placed at right angles to the centre line of the runway, spaced at 150 m, extending to 900 m from the runway end. A visual approach slope indicator (VASI) facilitates the pilot to approach at the correct height.

Runway Lighting

The centre line and edges of the runway are provided with lights. The spacing is 15 m for the centre line and 60 m for the edge lines.

Lighting of Taxiways

The taxiways are lighted similar to runways.

Apron Lighting

Apron lighting is provided by means of high masts.


Related Discussions:- Airport lighting

Millennium miles, Construction planning millennium miles

Construction planning millennium miles

Simple bending, In case of simple bending after simply supported beam, deri...

In case of simple bending after simply supported beam, derive that M/I = s /y = E/R.

Fluid mechanics, How a water bound macadam road is maintained

How a water bound macadam road is maintained

Full bore flow in drainage design, Q. Full bore flow in drainage design? ...

Q. Full bore flow in drainage design? In the design of gravity drainage pipes, full bore flow capacity is usually adopted to check against design runoff. Though one should note

Determine the ultimate bearing capacity of a square footing, Determine the ...

Determine the ultimate bearing capacity of a square footing, 1 m × 1 m, resting on saturated clay of unconfined compression strength of 180 kN/m 3 and a bulk density of 18 kN/m 3

Measure the cohesion of internal friction of the soil, A cylindrical specim...

A cylindrical specimen of a saturated soil fails under an axial stress 150 kN/m 2 in an unconfined compression test. The failure plane makes an angle of 52° with the horizontal.

Define construction damage - underwater inspection of bridge, Define Constr...

Define Construction damage - underwater inspection of bridge? Construction damage can result from improper procedures during the construction phase.  Some examples are: -  P

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd