What is total delay for cycle for the saturation flow rate

Assignment Help Civil Engineering
Reference no: EM13307005

A signal approach has 20 seconds of displayed green, 4 seconds of yellow, and 3 seconds of all red (assume typical start-up, lost time, and clearance time). The cycle length is 60 seconds. At the beginning of an effective red there are no vehicles in queue and vehicles arrive at three-quarters of the saturation flow rate for 30 seconds. Then there is zero flow for 10 seconds, and then one-half of the saturation rate from 40 seconds until the end of the cycle. What is the total delay for this cycle if the saturation flow rate is 1400 veh/h (in veh-s)? Assume D/D/1 queuing.

Reference no: EM13307005

Questions Cloud

Calculate the energy needed to accelerate a spaceship : Calculate the energy needed to accelerate a spaceship with a mass m = 25 × 103 kg toa speed of 0.40c. Compare this number with the approximate annual energy usage ofEarth, 1021 J
Find how much existing highway must be reconstructed : The overpass structure is to be level, centered 26 feet above the railroad, and 180 feet long. How much existing highway (in feet) must be reconstructed to provide appropriate vertical alignment
The crate is sliding down the ramp : 1)A crate of potatoes of mass 19.0 kg is on a ramp with angle of incline 30° to the horizontal. The coefficients of friction are μs = 0.82 and μk = 0.29. Find the frictional force (magnitude and direction) on the crate if the crate is sliding d..
Find how much time passes before the ice starts to melt : An open container holds ice of mass 0.595kg at a temperature of -13.5 celcius . The mass of the container can be ignored. How much time passes before the ice starts to melt
What is total delay for cycle for the saturation flow rate : A signal approach has 20 seconds of displayed green, 4 seconds of yellow, and 3 seconds of all red (assume typical start-up, lost time, and clearance time). The cycle length is 60 seconds.
The crate is sliding up the ramp : A crate of potatoes of mass 8.0 kg is on a ramp with angle of incline 30° to the horizontal. The coefficients of friction are μs = 0.72 and μk = 0.43. Find the frictional force (magnitude and direction) on the crate if the crate is sliding up t..
What is maximum acceleration from rest for car with engine : The car weights 2450 lb, the mechanical efficiency of the drivetrain is 90%, and the wheel radius is 14 inches. The base engine develops 200 ft-lb of torque, and a modified version of the engine develops 240 ft-lb of torque.
Compute the thickness of the glass : A very thin sheet of glass (n=1.5) floats on the surface of water (n=1.33). When illuminated with white light at normal incidence, What is the thickness of the glass
What is the speed of the combined masses after collision : An iron bar of mass, 0.55 kg, slides down a frictionless incline 0.41 m high. What is the speed of the combined masses after collision

Reviews

Write a Review

Civil Engineering Questions & Answers

  How many days will fish hatchery have to contain river water

If the initial concentration of parathion in the runoff from the agricultural field is 3 ppb, the velocity of the river is 2.3 miles/day, how many days will the fish hatchery have to contain river water in holding tanks until the parathion concent..

  Horizontal motion of plunger and shaft

The horizontal motion of plunger and shaft is arrested by resistance of the attached disk which moves through the oil bath. If the velocity of plunger is v.

  What was the drivers associated reaction time in seconds

The driver strikes the sign at a speed of 25 mi/h. If the student was traveling at 55 mi/h when the sign was spotted, what was the drivers associated reaction time in seconds

  Find si value of absolute pressure corresponding to vaccum

What is the SI value of absolute pressure corresponding to a vacuum pressure of -10 inches of water. Assume the location is Moscow, Idaho. What is the SI value of gage pressure corresponding to a pressure 14 psia. Assume the location is Denver, Colo..

  What is lowest grade possible for the constant-grade section

A tangent section of highway has a -1.0% grade and ends at station 0+1450and elevation 25m. It must be connected to another section of highway that has a -1% grade and that begins at station 1+345 and elevation 40m.

  What amount of water use is exceeded with the probability

Suppose the summer daily demand for water use in Phoenix is normally distributed with a mean of 310 million gallons/day and a standard deviation of 45 million gallons/day. Also suppose the city has reservoirs whose combined storage is 350 million ..

  What sample size is necessary for the confident interval

A state legislator wishes to survey residents of her district tosee what proportion of the electorate is aware of her position on using state funds to pay for abortions. a)What sample size is necessary if the 95% Confident Interval

  Partial wavelength for electromagnetic energy

What is the length of the partial wavelength for electromagnetic energy with a frequency of 15 MHz and a phase shift of 263 degrees (in meters)?

  Define mechanical engineering dynamics

Important information about Mechanical engineering dynamics, A 3000 lb car rests on a horizontal street out of gas with its brakes locked.

  Estimating annual erosion

Using the USLE, estimate the annual erosion from a 100 ha. forested watershed assuming the following: R =112 tonnes/ha/year. The forest is in fair condition with 40% cover; Average slope is 3%; The soils are clay loam in hydrologic group C.

  Explain how to compute the disclosure and elevation of a

Reciprocal leveling gives the following readings in feet from a setup near A: on A, 2.071; on B, 8.254, 8.259 and 8.257. At the setup near B: on B, 9.112; on A, 2.926, 2.930 and 2.927. The elevation of B is 1099.600. Compute the disclosure and ele..

  How much was the initial investment at an interest rate

A company that manufactures regenerative thermal oxidizers made an investment 10 years ago that is now worth $1,300,000. How much was the initial investment at an interest rate of 15% per year (a) simple interest and (b) compound interest?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd