Question - At the beginning of 2013, the Wizards received a contract to build a new arena for $25 million. The project is estimated to take three years to complete. According to the contract, the Wizards will bill the buyer in installments over the construction period according to a prearranged schedule. The Wizards use the percentage of completion method to account for long-term contracts. Information related to the contract is as follows:
2013
2014
2015
Costs to Date
$7,500,000
$12,500,000
$20,500,000
Estimated Costs to Complete
$11,250,000
$-
Billings during the year
$6,000,000
$10,000,000
$9,000,000
Cash collection during the year
$5,000,000
$7,000,000
$13,000,000
Record the entry for the costs of construction, progress billings, and collections in 2013.
Record the entry to recognize revenue, expense, and gross profit for 2014.
What is the entry to record the completion of the contract in 2015?
What is the total gross profit earned on this project?
Hubbard argues that the Fed can control the Fed funds rate, but the interest rate that is important for the economy is a longer-term real rate of interest. How much control does the Fed have over this longer real rate?
Coures:- Fundamental Accounting Principles: - Explain the goals and uses of special journals.
Accounting problems, Draw a detailed timeline incorporating the dividends, calculate the exact Payback Period b) the discounted Payback Period. the IRR, the NPV, the Profitability Index.
Term Structure of Interest Rates
Write a report on Internal Controls
Prepare the bank reconciliation for company.
Create a cost-benefit analysis to evaluate the project
Theory of Interest: NPV, IRR, Nominal and Real, Amortization, Sinking Fund, TWRR, DWRR
Distinguish between liquidity and profitability.
Your Corp, Inc. has a corporate tax rate of 35%. Please calculate their after tax cost of debt expressed as a percentage. Your Corp, Inc. has several outstanding bond issues all of which require semiannual interest payments.
Simple Interest, Compound interest, discount rate, force of interest, AV, PV
CAPM and Venture Capital
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd