A project to remodel a garage has the following activities. (Hint: You will need to build an AIB/AON diagram, perform a forward pass, and perform a backward pass to answer this question.)
Activity Duration Predecessors
A4 months---
B3 months---
C3 months---
D5 monthsC
E3 monthsA, B
F3 monthsB, C
G3 monthsE, F
H4 monthsD, F
I5 monthsG
J2 monthsH
What are the critical path activities?
What is the project's scheduled completion time?
What is the slack or float for Activity C? Show your calculations.
What is the slack or float for Activity D? Show your calculations.
What is the slack or float for Activity F? Show your calculations.
Consider a 3 firm supply chain consisting of a retailer, manufacturer, and a supplier. The retailers demand over an 8 week period was 100 units each of the first 2 weeks, 200 units each of the second 2 weeks, 300 units each of the third 2 weeks, and ..
You have just used the capability index (Cpk) formulas to compute the two values "min [2, 2.5]." Which of the following is the proper interpretation of these numbers?
Money R’Us is an all-purpose financial institution located in Dayton’s financial district. Money R’Us has 6 departments and a supervisory staff as shown below. Customers arrive at each department at random (i.e. a Poisson process) with mean arrival r..
While telemarketing can be a difficult career, companies continue to utilize inbound and outbound telemarketing activities because they are effective and cost efficient. Web-driven service technologies offer ever-expanding modes of communicating with..
Compare and contrast the different types of drawings and discuss their importance to an effective and efficient construction process. Support the paper with research from the online course material, text, and outside sources if necessary.
The warehouse manager asked you to create an example inventory list for his staff. The inventory list is a comprehensive chart that lists all of the company's internal resources: equipment, machines, technology, furniture, office supplies, etc.
Cesar Rogo Computers, a Mississippi chain of computer hardware also software retail outlets, supplies both educational also commercial customers with memory also storage devices.
Discuss the use of PERT/CPM techniques for managing projects. Describe what PERT/CPM does. Discuss advantages and disadvantages of using it. What other techniques might you choose to manage your project?
Discuss an instance when you identified a weakness in the skill set in an employee (or in yourself ). If you had limited financial resources, where would you look for training to close the gap on these skill sets
Identify the activities to be included in a critical path schedule for your project.
develop exponential smoothing forecast for February through January next year c. Resolve problem b) with ? = 0.6 d. What are the MADs for models ( a),(b), and (c) e. What forcast is the most accurate?
Determine the capacity utilization for labor and machine for each of the four weeks. In which weeks do you foresee a problem? What options would you suggest to resolve any problems?
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd