What are the critical activities

Assignment Help Science
Reference no: EM131691812

1. Consider the following project network and activity times (in weeks):

608_029826EC-6BD2-4A39-B2DA-4E649B9F08B7.jpeg

Activity

A

B

C

D

E

F

G

H

Time

5

3

7

6

7

3

10

8

a. Identify the critical path.

b. How much time will be needed to complete this project?

c. Can activity D be delayed without delaying the entire project? If so, by how many weeks?

d. Can activity C be delayed without delaying the entire project? If so, by how many weeks?

e. What is the schedule for activity E?

2. Davison Construction Company is building a luxury lakefront home in the Finger Lakes region of New York. Coordination of the architect and subcontractors will require a major effort to meet the 44-week (approximately 10-month) completion date requested by the owner. The Davison project manager prepared the following project network:

608_029826EC-6BD2-4A39-B2DA-4E649B9F08B7.jpeg

Estimates of the optimistic, most probable, and pessimistic times (in weeks) for the activities are as follows:

Activity

Optimistic

Most Probable

Pessimistic

A

4

8

12

B

6

7

8

C

6

12

18

D

3

5

7

E

6

9

18

F

5

8

17

G

10

15

20

H

5

6

13

a. Find the critical path.

b. What is the expected project completion time?

c. Based only on the critical path, what is the estimated probability the project can be completed in the 44 weeks as requested by the owner?

d. Based only on the critical path, what is the estimated probability the building project could run more than 3 months late? Use 57 weeks for this calculation.

e. What should the construction company tell the owner?

3. Embassy Club Condominium, located on the west coast of Florida, is undertaking a summer renovation of its main building. The project is scheduled to begin May 1, and a September 1 (17-week) completion date is desired. The condominium manager identified the following renovation activities and their estimated times:

Activity

Immediate Predecessor

Time

A

-

3

B

-

1

C

-

2

D

A, B, C

4

E

C, D

5

F

A

3

G

D, F

6

H

E

4

a. Draw a project network.

b. What are the critical activities?

c. What activity has the most slack time?

d. Will the project be completed by September 1?

4. At a local university, the Student Commission on Programming and Entertainment (SCOPE) is preparing to host its first rock concert of the school year. To successfully pro¬duce this rock concert, SCOPE has listed the requisite activities and related information in the following table (duration estimates measured in days).

Activity

Immediate Predecessor(s)

Optimistic

Most Probable

Pessimistic

A: Negotiate contract with selected musicians

-

8

10

15

B: Reserve site

-

7

8

9

C: Manage travel logistics for music group

A

5

6

10

D: Screen & hire security personnel

B

3

3

3

E: Arrange advertising

B, C

1

5

9

F: Hire parking staff

D

4

7

10

G: Arrange concession sales

E

3

8

10

a. Draw the project network.
b. Compute the expected duration and variance of each activity.
c. Determine the critical path in the project network.
d. What is the expected duration and variance of the critical path?
e. What is the likelihood that the project will be completed within 30 days?
f. If activity B is delayed by six days beyond its early start time, how does this affect the expected project duration?

5. The manager of the Oak Hills Swimming Club is planning the club's swimming team program. The first team practice is scheduled for May 1. The activities, their immediate predecessors, and the activity time estimates (in weeks) are as follows:

Activity Description  Immediate Predecessor Optimistic Time (weeks) Most Probable Pessimistic
A Meet with board - 1 1 2
B Hire coaches A 4 6 8
C Reserve pool A 2 4 6
D Announce program B. C 1 2 3
E Meet with coaches B 2 3 4
F Order team suits A 1 2 3
G Register swimmers D 1 2 3
H Collect fees G 1 2 3
I Plan first practice E, H, F 1 1 1

a. Draw a project network.
b. Develop an activity schedule.
c. What are the critical activities, what is the expected project completion time?
d. If the club manager plans to start the project on February 1, what is the probability the swimming program will be ready by the scheduled May 1 date (13 weeks)? Should the manager begin planning the swimming program before February 1?

6. The product development group at Landon Corporation has been working on a new computer software product that has the potential to capture a large market share. Through outside sources, Landon's management learned that a competitor is working to introduce a similar product. As a result, Landon's top management increased its pressure on the product development group.

The group's leader turned to PERT/CPM as an aid to scheduling the activities remaining before the new product can be brought to the market. The project network is as follows:

608_029826EC-6BD2-4A39-B2DA-4E649B9F08B7.jpeg

The activity time estimates (in weeks) are as follows:

Activity Optimistic Most Probable Pessimistic
A 3 4 5
B 3 3.5 7
C 4 5 6
D 2 3 4
E 6 10 14
F 7.5 8.5 12.5
G 4.5 6 7.5

7.

 608_029826EC-6BD2-4A39-B2DA-4E649B9F08B7.jpeg

Activity

A

B

C

D

E

F

G

H

Time

5

3

7

6

7

3

10

8

The crashing data for this project are as follows:

  Time (days) Cost ($)
Activity Normal Crash Normal Crash
A 3 2 800 1400
B 2 1 1200 1900
C 5 3 2000 2800
D 5 3 1500 2300
E 6 4 1800 2800
F 2 1 600 1000
G 2 1 500 1000

a. Find the critical path and the expected project completion time.

b. What is the total project cost using the normal times?

8. Consider the following project network and activity times (in weeks):

608_029826EC-6BD2-4A39-B2DA-4E649B9F08B7.jpeg

Activity

A

B

C

D

E

F

G

H

Time

5

3

7

6

7

3

10

8

The crashing data for this project are as follows:

  Time (days) Cost ($)
Activity Normal Crash Normal Crash
A 3 2 800 1400
B 2 1 1200 1900
C 5 3 2000 2800
D 5 3 1500 2300
E 6 4 1800 2800
F 2 1 600 1000
G 2 1 500 1000

9. Refer to Problem 8. Assume that management desires a 12-day project completion time.

a. Formulate a linear programming model that can be used to assist with the crashing Dicisions.

b. What activities should be crashed

c. What is the total project cost for the 12-day completion time?

10. Office Automation, Inc., developed a proposal for introducing a new computerized office system that will standardize the electronic archiving of invoices for a particular company. Contained in the proposal is a list of activities that must be accomplished to complete the new office system project. Use the following relevant information about the activities:

      Time (weeks) Cost ($1000s)
Activity Description Immediate Predecessor Normal Crash Normal Crash
A Plan needs _ 10 8 30 70
B Order equipment A 8 6 120 150
C Install equipment B 10 7 100 160
D Set up training lab A 7 6 40 50
E Conduct training course D 10 8 50 75
F Test system C, E 3 3 60 _

a.Develop an activity network.

b.Develop an activity schedule.

c.What are the critical activities, and what is the expected project completion time?

d.Assume that the company wants to complete the project in six months or 26 weeks. What crashing decisions do you recommend to meet the desired completion time at the least possible cost? Work through the network and attempt to make the crashing decisions by inspection.
e.Develop an activity schedule for the crashed project.
f.What added project cost is required to meet the six-month completion time?

Reference no: EM131691812

Questions Cloud

Indicators of potential staffing discrimination : What are the limitations of disparate impact statistics as indicators of potential staffing discrimination?
What is chromosome non-disjunction : What is chromosome non-disjunction? At what specific stage in cell cycle would it occur? What is a human condition that is caused by chromosome non-disjunction
What are the two main types of probability : What is an event? What is the union of two events? What is the intersection of two events?
What was the average annual economic growth rate : What was the average annual economic growth rate in Singapore over the 19.00 years from 1958 to 1977?
What are the critical activities : What are the critical activities, and what is the expected project completion time
Calculate the player scores in a game against team a : Consider the event that a player scores a point in a game against team A and the event that the same player scores a point in a game against team B.
Calculate expected value at every node : A fast food restaurant chain is considering a store expansion program. Calculate expected value at every node.
Different corporate level strategies : What are the different levels of diversification firms can pursue by using different corporate level strategies.
Draw the venn diagram of the sample space : A die is tossed twice and the two outcomes are noted. Draw the Venn diagram of the sample space and indicate the event "the second toss is greater.

Reviews

Write a Review

Science Questions & Answers

  Journal of pharmaceutical sciences

This journal is a scientific publication of Indian Pharmaceutical Association and highlights various bright points of it.

  Optical fibres

This document discuss about the main attributes and characteristics of optical fibres.

  Micro organisms

This project report reveals the fact and proves a specific objective mentioned to be studied upon.

  Describing histology of an organ

The discussion of the technique should include a literature review on the evolution of the technique.

  Interpret the sensitivity of mammography

Calculate and interpret the sensitivity of mammography. Diagnostic test with Sensitivity 50%, Specificity 50% and prevalence 50%. Crude mortality rate. Damage caused by motor vehicle accidents.

  Discuss the role that science plays in your daily life

Role that science plays in your daily life and Integrity, Intensity, Innovation, and involvement in scientific field

  Prepare a flexible budget gator divers

Prepare a Flexible Budget Gator Divers is a company that provides diving services such as underwater ship repairs to clients in the Tampa Bay area.

  Neurological disorders

Designing a neuroprosthesis for the neurological disorders

  Complexity of cell surfaces

Lipid rafts provide another example of the complexity of cell surfaces in both their structural character and biologic functionality. Please explain the nature of these structures and their functionality.

  Exploratory activity on bird beaks

Describe how natural selection and evolution are demonstrated by this activity

  Spatial and temporal variation of heat content in the upper

In this study the temporal and spatial variation of heat content in the upper 70m layer of the Arabian Sea was for a period of 1991 to 2008 have been attempted.

  Earthquake databases

Earthquake Databases

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd