The probability that the project will completed in 88 days

Assignment Help Basic Statistics
Reference no: EM13954257

1) A PERT project has 45 activities, 19 of which are on the critical path. The estimated time for the critical path is 120 days. The sum of all activity variances is 64, while the sum of variances along the critical path is 36. The probability that the project can be completed between days 108 and 120 is

a) 0 -2.00
b) 0.0227
c) 0.1058
d) 0.4773
e) 0.9773

2) A project being analyzed by PERT has 38 activities, 16 of which are on the critical path. If the estimated time along the critical path is 90 days with a project variance of 25, the probability that the project will be completed in 88 days or less is

a) 0.0228
b) 0.3446
c) 0.6554
d) 0.9772
e) 18

3) Analysis of a PERT problem shows the estimated time for the critical path to be 108 days with a variance of 64. There is a .90 probability that the project will be completed before approximately day ________.

a) 98
b) 108
c) 109
d) 115
e) 118

Reference no: EM13954257

Questions Cloud

Include as part of new employee orientation : Because of a large number of recently retired employ-eyes you have been hiring more employees in recent years. The average age of the workforce at your com-pay has changed drastically. The typical age of your employees used to be around 40; Going for..
Calculate the atomic weight of naturally occurring potassium : Calculate the atomic weight of naturally occurring potassium. What is the daughter nucleus of 40K? Explain why. What percentage of 40K nuclei will decay in the next 10 000 years?
Based on the pregnancy discrimination act : You recently learned that two of your key female employees will be taking maternity leave around the same time. What procedures or rules do you need to be aware of based on the Pregnancy Discrimination Act (PDA)?
Identify the four common types of sensitivity analysis : Identify the four common types of sensitivity analysis and explain how an analyst might use each to expand a base case forecast
The probability that the project will completed in 88 days : A project being analyzed by PERT has 38 activities, 16 of which are on the critical path. If the estimated time along the critical path is 90 days with a project variance of 25, the probability that the project will be completed in 88 days or less..
What is disparate-treatment discrimination : What is Disparate-treatment discrimination? List five protected classes of workers. Can gender be a bona fide occupational qualification and if yes, give an example
Beginning to be visible as separate bodies : Tall corn plants (T) are dominant to dwarf plants (tt). Solid green leaves (G) are dominant to leaves with a white tip (gg). A cross between two corn plants yielded the following phenotypes:
What circumstances can worker file worker compensation claim : Under what circumstances can a worker file a workers compensation claim? What is the significance of the whistleblower and the FMLA statutes?
What is the half-life of the isotope in seconds : A radioactive isotope has a decay constant lambda = 0.0582 s-1. What is the half-life of the isotope in seconds? What fraction of the activity of a sample of the isotope will remain after 30 seconds?

Reviews

Write a Review

Basic Statistics Questions & Answers

  Information regarding the understand the population

Statistics is about more than calculations. It is about turning data into information and using this information to understand the population. A statistician will be asked to help solve real world problems by designing a study

  Mean immigrants improve a state economy

Does this mean immigrants tend to earn more than other people? Or does it mean immigrants improve a state's economy? If not, what could explain the correlation?

  Interpret the findings of a correlation

How would you interpret the findings of a correlation study that reported a linear correlation coefficient of +0.3?

  You conducted a chi-square goodness of fit test in your

you conducted a chi-square goodness of fit test in your asci 691 capstone project. unfortunately you did not get the

  Description of decision theory

Construct the payoff table for this decision situation. Compute the expected value of each alternative amount of milk that could be stocked, and select the best decision.

  A sample of 2 different calculators is randomly selected

a sample of 2 different calculators is randomly selected from a group containing 18 that are defective and 37 that have

  Draw the tree for oranges decision problem and determine

the management of orange computers was considering launching a new product called whopper101. the problem was that if a

  From their 50 data points washington dc not in the study

from their 50 data points washington dc not in the study the researchers calculated a correlation of 0.988. based on

  Enzymatic method and confidence level

Enzymatic method: 13.1, 12.7, 12.6, 13.3, 13.3. GC method: 13.5, 13.3, 13.0, 12.9. Does the enzymatic method give the same value as the GC method at the 95% confidence level?

  Create a linear regression model to predict mpg

Develop a linear regression model to predict MPG using horsepower as the only independent variable. Develop another model with weight as the independent variable. Which of these two models is better?

  Determine histogram and level of significance

A civil service exam is given to 200 job applicants. In recent years, grades have followed a normal distribution with mean 66.5 and variance 100. The grades of the job applicants are distributed as follows:

  Determine the test value for hypothesis

their average cost was 340.00 with standard deviation of 80.00. Dean of students thinks that costs are greater this semester. Determine the test value for this hypothesis.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd