Read the case study then Answer the following questions:

1. How does multitasking confuse the resource availability of project team personnel?

2. In modern organizations, it is impossible to eliminate multitasking for the average employee? Do you agree or disagree with this statement? Why?

3. How would resource loading and/or resource leveling help this situation?

The Problems of Multitasking

An eastern U.S. financial services company found itself way behind schedule and over budget on an important strategic program. Both the budget and schedule baselines had begun slipping almost from the beginning, and as the project progressed, the lags became severe enough to require the company to call in expert help in the form of a project management-consulting firm. After investigating the organization's operations, the consulting firm determined that the primary source of problems both with this project in particular and the company's project management practices in general was a serious failure to accurately forecast resource requirements. In the words of one of the consultants, "Not enough full-time [human] resources had been dedicated to the program."

The biggest problem was the fact that too many of the project team members were working on two or more projects simultaneously-a clear example of multitasking. Unfortunately, the program's leaders developed their ambitious schedule without reflecting on the availability of resources to support the project milestones. With their excessive outside responsibilities, no one was willing to take direct ownership of their work on the program, people were juggling assignments, and everyone was getting farther behind in all the work. Again, in the words of the consultant, "Project issues would come up and there would be nobody there to handle them [in a timely fashion]." Those little issues, left unattended, eventually grew to become big problems. The schedule continued to lag, and employee morale began to bottom out.

Following their recognition of the problem, the first step made by the consultants was to get top management to renegotiate the work assignments with the project team. First, the core team members were freed from other responsibilities so they could devote their full-time attention to the program. Then, other support members of the project were released from multitasking duties and assigned to the project on a full-time or near full-time basis as well. The result, coupled with other suggestedchanges by the consultants, was to finally match up the project's schedule and activity duration estimates with a realistic understanding of resources needs and availability. In short, the program was put back on track because it was finally resource-leveled, particularly through creating full-time work assignments for the project team that accurately reflected the need to link resource management with scheduling.

Reference no: EM13740126

Questions Cloud

Voluntary and involuntary turnover : This assignment is designed to integrate the reflection of personal experience, and the information covered in the textbook. Using what you have learned about Juanita, answer the following questions:
Performance excellence with its business objectives : The quality methodologies or practices that the company uses or plans to use to align performance excellence with its business objectives,
Compensation program that will link pay to performance : Pay for performance is just as important in non-for-profit organizations. Assume you are founder of a non-profit public charity of your choice. Create a compensation program that will link pay to the performance of your employees.
Explain concept of descent with modification and evolution : The concept of descent with modification, or evolution, has a great deal of evidence in its support. Indicate the major types of evidence. In what ways is the human primate a typical primate?
Resource availability of project team personnel : Read the case study then Answer the following questions: 1. How does multitasking confuse the resource availability of project team personnel?
How did we implement our strategy statement : How did we implement our strategy statement and Which market segments did we emphasize and how did we manage them
Research current trends in labor in the united states : With the current legal environment, how are labor unions and companies affected? ( About 400 words) How is outsourcing affecting the labor movement? (About 400 words)
Assume a specific factors economy produces two goods : Assume a specific factors economy produces two goods, cloth and food, and that when representing the output of this economy graphically, cloth is on the x-axis and food is on the y-axis. movement of labor from a Foreign country to the domestic (Home)..
Critical thinking analysis : "Critical Thinking analysis, evaluation, and a synthesizing of fact, ideas, opinions, and theories" (Jones, 2013, para. 1) Critically think (analyze, evaluate, synthesize) the key concepts about leadership behaviors and theories, and include point..

Reviews

Write a Review

HR Management Questions & Answers

  Improve problem solving capabilities within organization

Types of teams as to their effectiveness that will improve problem solving capabilities within organizations.

  Influence tactics help in reducing organizations politics

Explain the different types of influence tactics that will be of a help “if adopted” in reducing the organizational politics.

  Report on citigroup''s hr service level agreement

Human Resources or Human Resource Management deals with HR Service Level Agreement. HR Service Level Agreement is an agreement made between the employer and the employee, which states that the employee would work under any client and sometimes any ti..

  A project report on hrm

Human Resource Management as the name suggests, it is a management discipline which deals with the human i.e. the workforce aspect of organizations. Need and practices of HRM are inevitable in present scenario of extreme competition where "Talent War..

  Hrp: recruitment and selection

Recruitment and Selection is the initial ladder of any Human Resource Planning process and contains an immense significance for any organisation.

  A project report on study of statutory complainces

Statutory compliance and its immense knowledge are crucial to be understood in an organization. It contains all the forms, procedures and acts applicable in a company.

  Operant conditioning and Reinforcement

Operant conditioning is a learning process where behaviour is controlled by its consequences. In this process an individual's behaviour can be modified through the use of positive or negative reinforcement.

  Effectiveness of training programs in achieving customers an

The main motive for conducting this research is to provide broad range of research of the literature and their reviews related to training and development and assisting the employees in providing customers satisfaction.

  A critical analysis of hr processes and practices in fedex c

FedEx is illustrious for its novel HR processes and practices that have greatly accounted for its success.

  Integrating culture and diversity in decision making

People in the organization are known as Google where they share common goals and have common vision.

  Impact of employee attrition on people management in organis

Talent management implies recognizing a person's inherent skills, traits, personality and offering him a matching job.

  Labour dissonance at maruti suzuki india limited: a case stu

This Case Study focuses on various issues related to Labour Unrest at Maruti Suzuki India Limited.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd