You are a Consultant for the professional service firm, BUSI 2083 LLP. Your firm specializes in providing a wide variety of internal business solutions for different clients. It is your first day on the job and a Manager asks you for some help with a client in the Technology & Entertainment sector. Eager to please on your first day, you start reading the background information provided by the Manager.

4D Entertainment, a division of Wave of the Future Corporation, manufactures two large-screen television models: the Zenith, which has been produced since 2008 and sells for $1,700, and the Pinnacle, a new model introduced in early 2008, which sells for $2,200.

Based on the following income statement for the year ended November 30, 2014, senior management at Wave of the Future have decided to concentrate 4D Entertainment's marketing resources on the Pinnacle model and begin to phase out the Zenith model.

Additional Information:

4D Entertainment

Income Statement

For the Year Ended November 30, 2014

 

Zenith

Pinnacle

Total

Sales

$30,600,000

$4,400,000

$35,000,000

COGS

19,890,000

3,080,000

22,970,000

Gross Margin

10,710,000

1,320,000

12,030,000

Selling and Admin Expense

8,032,500

925,000

8,957,500

Operating Income

$2,677,500

$395,000

$3,072,500

Units Sold

18,000

2,000

 

Operating Income per Unit Sold

$148.75

$197.50

 

Unit costs for Zenith and Pinnacle are as follows:

 

Zenith

Pinnacle

Direct Material

$540.00

$1,089.00

Direct Labor

 

 

Zenith (2.5 hours x $18 per hr)

45.00

 

Pinnacle (7.0 hours x $18 per hr)

 

126.00

Machine costs*

 

 

Zenith (8 hours x $25 per hr)

200.00

 

Pinnacle (5 hours x $25 per hr)

 

125.00

Other Manufacturing Overhead**

320.00

200.00

Total

$1,105.00

$1,540.00

*Machine costs include leasing of the machine, repairs, and maintenance.

** Other manufacturing overhead is allocated on the basis of machine hours at a rate of $40 per machine hour.

4D's controller, Tina Wesley, is advocating the use of activity-based costing (ABC) and activity based management (ABM), and has gathered the following information about the company's manufacturing overhead costs for the year ended November 30, 2014.

 

 

Units of Cost Driver

 

Total Activity Costs

Zenith

Pinnacle

Soldering

$1,872,400

1,296,000

214,000

Shipments

1,480,000

1,500

500

Quality Control

1,749,600

54,000

18,000

Purchase Orders

582,400

16,640

4,160

Machine Power

61,600

144,000

10,000

Machine Set-up

414,000

360

100

Total Manufacturing Overhead

$6,160,000

 

 

Soldering is based on the number of solder points, shipments based on the number of shipments, quality control based on the number of inspections, purchase orders based on the number of PO's, machine power based on machine hours, machine setups based on the number of setups.

After completing her analysis, Wesley showed the results to Donald Warden, the 4D Entertainment Division President. Warden did not like what he saw. "If you show headquarters this analysis, they are going to ask us to phase out the Pinnacle line, which we have just introduced. This whole costing thing has been a major problem for us. First Zenith was not profitable and now Pinnacle.

"Looking at the ABC analysis, I see two problems. We do many more activities than the ones you have listed. If you had included all activities, maybe your conclusions would have been different. Second, you used number of setups and number of inspections as allocation bases. The numbers would have been different had you used setup hours and inspection hours instead. I know that measurement problems precluded you from using these other cost allocation bases, but at least you ought to make some adjustments to our current numbers to compensate for these issues. I know you can do better. We can't afford to phase out either product."

Wesley knew her numbers were fairly accurate. On a limited sample, she had calculated the profitability of Zenith and Pinnacle using different allocation bases. The set of activities and activity rates she had chosen resulted in numbers that approximated closely those based on more detailed analyses. She was confident that headquarters, knowing that Pinnacle was introduced only recently, would not ask 4D Entertainment to phase it out. She was also aware that a sizable portion of Warden's bonus was based on division sales. Phasing out either product would adversely affect the bonus. Still, she felt some pressure from Warden to do something.

4D Entertainment is unsure of the strategies to properly reflect information for their parent company. The manager would like the following questions addressed as soon as possible:

REQUIRED

1. Using activity-based costing (ABC), calculate the profitability of the Zenith and Pinnacle models.

2. Explain briefly why these numbers differ from the profitability of the Zenith and Pinnacle models calculated using 4D Entertainment's existing costing system.

3. Comment on Warden's concerns about the accuracy and limitations of ABC.

4. How might 4D Entertainment find the ABC information helpful in managing its business?

5. What should Tiny Wesley do?

Reference no: EM13762896

Questions Cloud

Create while-end repetition structure includes a nested if : Create your own While-End (or For-End) repetition structure that includes a nested if-then selection structure. You decide the theme. You should provide both the pseudocode and the flowchart of your example.
Underestimate the value of output : GDP measures underestimate the value of output produced by an economy because they include services not transferred through markets? T or F
Issues based on agricultural industary : The discharge rate of the wastewater to maintain at least 5 mg/L critical DO concentration in the river
Advanced information technology of u : Assess the relationship of systems analysis, design, implementation, and development processes as they relate to the management of information technology systems
Profitability of the zenith and pinnacle models : Using activity-based costing (ABC), calculate the profitability of the Zenith and Pinnacle models.
Are you to support federal welfare programs : Are you to support federal welfare programs, or are we to let people starve on the streets? There can be no truth in Nietzsche's philosophy, for Nietzsche was a man who deserted his friends and betrayed those who trusted him.
Specific innovation of the airmouse technology : Specific innovation of the airmouse technology, Potential risks in using this technology for an organization, How this technology can be 'integrated' in the organization
Basic present value calculations : Calculate the present value of the following cash flows, rounding to the nearest dollar:
Rate of inflation in the future-market risk premium : Calculate the required rate of return for Climax Inc., assuming that (1) investors expect a 4.0% rate of inflation in the future, (2) the real risk-free rate is 3.0%, (3) the market risk premium is 5.0%, (4) the firm has a beta of 2.40, and (5) its r..

Reviews

Write a Review

Accounting Basics Questions & Answers

  Compute the number of equivalent units with respect to both

during april the production department of a process manufacturing system completed a number of units of a product and

  How the company coca cola could best allocate

Determine how the company Coca cola could best allocate costs to divisions, plants, departments, contracts, and / or products. Explain your rationale.

  Given the following information determine the cost of goods

given the following information determine the cost of goods manufactured and the cost of goods sold for the year ended

  3-year insurance policy

On July 1, 2014, Crowe Co. pays $30,000 to Zubin Insurance Co. for a 3-year insurance policy. Both companies have fiscal years ending December 31. For Crowe Co., journalize the entry on July 1 and the adjusting entry on December 31.

  In 2012 x companys revenue was 236250 its total variable

in 2012 x companys revenue was 236250 its total variable costs were 128250 and its fixed costs were 92400. assume that

  Assume that at the end of 2012 clampett inc an s

assume that at the end of 2012 clampett inc. an s corporation distributes long-term capital gain property fair market

  Eagle company makes the musicfinder a sophisticated

eagle company makes the musicfinder a sophisticated satellite radio. eagle has experienced a steady growth in sales for

  Indicate how engle wouldreport the unsold boats and for how

engle marine builds 30-foot fiberglass fishing boats which itmarkets through a network of 3rd party dealers on

  Generic strategy and grand strategy

Write a paper of no more than 1,400 words that evaluates alternatives an organization must consider to realize growth. Identify the best value discipline, generic strategy, and grand strategy for your organization.

  Suppose you want to estimate the proportion of cars that

suppose you want to estimate the proportion of cars that are sport utility vehicles suvs being driven in kansas city

  What is the maturity risk premium

Assume that real risk-free rate = 3%. Inflation rate is expected to be 8% in year 1, 5% in year 2, and 4% thereafter. Also assume that all T-bonds are highly liquid and free of default risk. If 2-year T-bond yields 13%, what is the maturity risk p..

  The man-hour estimate for test and evaluation was based on

the man-hour estimate for test and evaluation was based on using expert opinion to come up with optimistic pessimistic

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd